Download PDF

South Africa Judgment

Kwazulu-Natal High Court, Durban

Shamla Chetty t/a Nationwide Electrical v TBP Building and Civils (Pty) Ltd and Another (13677/2010) [2011] ZAKZDHC 67 (8 June 2011)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that a dispute had indeed been declared between the parties, as evidenced by the letter dated 1 November 2010, which referenced non-compliance with contractual obligations and the suspension of work. This triggered the arbitration clause in the agreement, requiring referral of the dispute to arbitration. The applicant failed to discharge the onus of proving that no dispute existed and did not justify bypassing the arbitration process. Applying the Plascon-Evans rule, the court held that the applicant had not established entitlement to the relief sought. Consequently, the application was dismissed with costs.

Court disposition

Application dismissed with costs.

Orders

  • The application is dismissed with costs.

02

Material facts

Parties

Shamla Chetty t/a Nationwide Electrical

Applicant Counsel: H De Beer SC

TBP Building and Civils (Pty) Ltd

Respondent Counsel: M W Collins

KSN Electrical

Respondent

Amounts and remedies

  • Certified Payment Amount in Dispute: ZAR 907,000

03

Procedural history

  1. Posture

    Civil Application / Final Relief Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that no dispute had been declared under the contract, and therefore referral to arbitration was not required. The relief sought was for the production of documents and payment certificates as contractually due under clause 30.3. The applicant maintained that the letter from Pearce, Du Toit and Moodie was merely a notice of suspension and not a declaration of dispute. The applicant argued that the respondent failed to produce the required documentation and that the sum of R907,000 was certified and not properly reversed.
Respondent
The first respondent argued that clause 38.3 of the agreement is sufficiently broad to cover all disputes, and that a dispute had in fact been declared by the letter dated 1 November 2010. The respondent submitted that the applicant's demand for payment certificates was not contractually supported, and that the matter should have been referred to arbitration. The respondent further argued that the applicant bore the onus to prove no dispute existed and failed to discharge it, warranting dismissal of the application with costs.

05

Court’s reasoning

  1. 01

    Clause 38.3 of the subcontract agreement

    Where a contract contains an arbitration clause, disputes arising from the agreement must be referred to arbitration if a dispute is declared.

  2. 02

    Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A) at 634H-I

    The Plascon-Evans rule requires that in final relief applications, factual disputes must be resolved on the respondent's version unless the applicant's version is undisputed.

  3. 03

    Aveng (Africa) Ltd formerly Grinaker-LTA t/a Grinaker-LTA Building East v Midros Investments (Pty) Ltd 2011 (3) SA 631 (KZD); Lufuno Mphaphuli and Associates v Andrews [2009] ZACC 6

    Courts should respect parties' autonomy in choosing arbitration and minimize judicial interference in the arbitration process.

06

Ratio, limits and disposition

Ratio decidendi

The court found that a dispute had indeed been declared between the parties, as evidenced by the letter dated 1 November 2010, which referenced non-compliance with contractual obligations and the suspension of work. This triggered the arbitration clause in the agreement, requiring referral of the dispute to arbitration. The applicant failed to discharge the onus of proving that no dispute existed and did not justify bypassing the arbitration process. Applying the Plascon-Evans rule, the court held that the applicant had not established entitlement to the relief sought. Consequently, the application was dismissed with costs.

Obiter and limits

  • The court emphasized the modern approach to arbitration clauses, which is to respect parties' contractual autonomy and minimize judicial interference.
  • The applicant's reliance on the agreement for relief was inconsistent with its refusal to follow the dispute resolution mechanism provided therein.

Court disposition

Application dismissed with costs.

  • The application is dismissed with costs.

Source and reliance status

Kwazulu-Natal High Court, Durban

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Kwazulu-Natal High Court, Durban

Judgment

[2011] ZAKZDHC 67

IN THE KWAZULU-NATAL HIGH COURT, DURBAN

REPUBLIC OF SOUTH

AFRICA

Case No: 13677/2010

In the matter between

Shamla Chetty t/a Nationwide Electrical …...........................Applicant

and

TBP Building and Civils (Pty) Ltd …..........................First Respondent

KSN Electrical …....................................................Second Respondent

JUDGMENT

Delivered on: 8 June 2011

STEYN J

[1] On 11 April 2011, the applicant sought the following relief:

“(1) That the First Respondent is directed to produce within ten days of the date of this order all payment certificates including all available details concerning the quantities of the subcontract works included in each certificate as defined in clause 1.1.15 of the agreement concluded between the Applicant and the First Respondent on the 12th March 2008 and 28th March 2008 which annexure “A” annexed to the Founding Affidavit disclosing the amounts certified as due for payment to the Applicant for the period 1st July 2009 to the 31st October 2010;

(2) That the Applicant is granted leave to supplement the papers on receipt of the documentation referred to in paragraph 1 of this order to claim the amount so certified as due to the Applicant and to re-approach this Court on notice to the First Respondent for judgment for the amounts certified as due to the Applicant in terms of such certificates.

That the First Respondent be directed to pay the costs of the application excluding the costs of the hearing on the 10th December 2010.”

[2] This application is a sequel to an earlier application. The first application was brought as an opposed application before my brother Wallis J, who struck the matter from the roll with costs. When the application was launched before this court, the applicant changed course and sought amended relief that is final in nature.

[3] The background to this application is that the applicant is the electrical subcontractor and the first respondent is the main contractor, constructing a new multi-level departmental block at the Port Shepstone Hospital. In terms of the contract the applicant had to supply electrical installations as specified in the subcontract agreement. The second respondent is the newly appointed

subcontractor. Essentially the dispute could be described as a building dispute between the applicant on one side, it being the

sub-contractor, and the first respondent, being the main contractor and the employer as per the agreement, to wit the KwaZulu-Natal

Province.

[4] Pivotal to the application is the agreement concluded between all the parties, more so clause 30 of the agreement that reads as follows:

“30.1 The sub-contract shall submit a detailed application for interim payments to the contractor on or before the date stated in clause 39.2.9 of the sub-contract schedule. The contractor shall forward the quantum in such detailed application to the agent or employer provided that such quantum represents a reasonable estimate of:

the total value of the sub-contract works satisfactorily executed at the date of application, making due allowance for authorised variations and adjustments to the sub-contract sum in terms of clause 28.0

the materials and goods subject to the terms of the principal agreement

any expense or loss arising from the provisions of clauses 3.3, 6.4, 7.4, 11.3, 15.0, 18.2, 18.3, 22.0 and 33.0

30.2 The sub-contractor shall furnish to the contractor,

for submission with the application for interim payment, any documents which may be required to substantiate the value of the application.

30.3 After receipt of an interim payment certificate, or after receipt of interim payment should there not be provision for a payment certificate in terms of the principal agreement, the contractor shall, upon an application by the sub-contractor, disclose to the sub-contractor all available details concerning the quantities of the sub-contract works included in the payment certificate or interim payment”

(Emphasis as per original agreement)

In the appointment letter, dated 22 February 2008, the following obligations were added to the original agreement, in terms of MW2. Stipulating the following obligations of the subcontractor:

“2a. The sub-contractor shall submit a detailed application for interim payments to the contractor two working days before the 20th of each month. This shall be a detailed application in Bill of Quantities format.

b. The claims are to be cumulative and represent the total value of the sub contract works satisfactorily executed at the date of application and not simply record the monthly movements.

c. Materials and goods delivered to site must be reflected therein.

3. Should you fail to submit your application for interim payments in sufficient detail or timeously, we will not be responsible for any subsequent non-payment of the claims due to late submission or lack of detail.

4. Original VAT invoices are to be delivered to our offices at 4 Lancaster Terrace, Westville or post to P.O. Box 1293, Westville, 3600, for the attention of the Contract Surveyor, to reach ourselves before due date for payment.

5. No payments will be effected by our accounts department until the signed order together with the required documents has been received by us.”

[5] The only aspect on which the parties agreed upon when the matter was argued is the fact that the relief is final in substance and henceforth that the application should be dealt with in accordance with the Plascon-Evans1 rule.

[6] Mr de Beer SC, acting on behalf of the applicant, has argued that no party has declared any dispute in terms of the contract and henceforth no referral to arbitration is required, as stipulated in the contract viz clause 38. Much emphasis was placed on clause 38.3 that provides as follows:

“38.3 Should any disagreement between the contractor and the subcontractor arise out of this agreement other than a disagreement in terms of clause 38.1, either party may by notice to the other party declare a dispute which shall be referred to arbitration.”

(My emphasis)

[7] According to Mr de Beer the application is not about a dispute, or a referral for arbitration, but about the production of documents and details that the applicant is entitled to in terms of clause 30.3. The respondent failed to produce the aforementioned documentation.2 It needs to be stipulated that the applicant relies on the very agreement in its claim of the payment certificates.

[8] Mr Collins, acting on behalf of the first respondent, asked that the court focus and consider the content of the agreement, especially clause 1.1.15 and what it provides. Clause 1.1.15, which forms part of the definitions and interpretations of the agreement, reads:

“‘PAYMENT CERTIFICATE’ means a certificate indicating the amount due and payable by the employer to the contractor in terms of the principal agreement.”

He submitted that there is no contractual provision that the applicant could rely on in its demand that payment certificates be provided. In addition, Mr Collins, argued that clause 38.3 of the agreement is sufficiently wide enough to cover all disputes, which means that the only question that remains is whether a dispute was in fact declared. In his view, annexure L, page 67 of the papers, is a declaration of a dispute. Page 67 contains a letter sent by the firm Pearce, Du Toit and Moodie, dated 1 November 2010. It reads as follows:

“Electrical Sub-contract: Nationwide Electrical: Port Shepstone Hospital

The seven day notice period referred to in our letter dated 20 October 2010 has now expired and you have not complied with your obligation in terms of clause 30.3 of the contract namely, to disclose details of quantities of the subcontract works which have been certified and included in your payment certificates.

Accordingly, please take notice that our client exercises its right to suspend work. During this suspension period no other electrical contractor may be brought onto site.”

In light of this letter, so it has been argued, the matter ought to have been referred to arbitration and since the applicant contests such a referral, the applicant bore the onus. It was argued that applicant failed to discharge the onus and that the application should be dismissed with costs. Mr de Beer on the other hand has argued that the aforementioned letter does not constitute any dispute since it is purely and simply a notification of suspension of work on the contract. I shall return to this notice later in my judgment.

[9] I shall now turn to the relief sought and then duly consider whether the applicant succeeded in proving, on the papers that she is entitled to the relief sought, since no dispute was declared.

[10] Much of the applicant’s case depends on whether the sum of R907 000 was paid and then reversed. Mr de Beer has argued that the respondent is silent on the fact whether such payment had been received. Mr Collins asked that the court give consideration to the information as reflected on page 104 of the papers, which shows that respondent acknowledged that R907 000 was certified. It was, however, reversed because of the discrepancies in the applicant’s claim.

[11] In my view if it is found that any of the parties in this case more specifically the applicant, has declared a dispute then the matter should have been referred to arbitration, which results in the applicant not succeeding in its claim before this court.

[12] The word ‘dispute’ is defined in the Oxford English dictionary3 as:

“question the correctness on the validity of (a statement or an alleged fact); argue with (a person); contest, strive against, or resist (an action).”

I fail to see how the following could not be interpreted as a dispute:

“you have not complied with your obligation in terms of clause 30.3 . . .”

. . . our client exercises its right to suspend work.”4

It is evident that applicant disputed the fact that the contractor fulfilled its obligations. This much should be abundantly clear, since it is a disagreement between the parties over obligations arising from the agreement.

It is evident from the founding affidavit5 that the parties also disagreed over the existence of their rights and duties and that a referral to arbitration should have followed, considering clause 38.3 and its content. Accordingly, in my view, applicant had to convince this court (1) that there was no dispute and (2) failing so, bore the onus to satisfy this court that it should not exercise its discretion in favour of an arbitration referral.6 I align myself with the views expressed by Wallis J, as he then was, in Aveng (Africa) Ltd formerly Grinaker-LTA t/a Grinaker-LTA Building East v Midros Investments (Pty) Ltd:7

“[13] I am fortified in this approach to clause 40 by the fact that the modern approach to arbitration clauses is to respect the parties’ autonomy in concluding the arbitration agreement and to minimise the extent of judicial interference in the process. The historical desire of courts to protect their own jurisdiction and their consequent suspicion of arbitration as a means of resolving disputes has been replaced by a recognition that arbitration is an acceptable form of dispute resolution with which the courts should not interfere. As O’Regan ADCJ said in Lufuno Mphaphuli and Associates v Andrews:

‘[219] The decision to refer a dispute to private arbitration is a choice which, as long as it is voluntarily made, should be respected by the courts. Parties are entitled to determine what matters are to be arbitrated, the identity of the arbitrator, the process to be followed in the arbitration, whether there will be an appeal to an arbitral appeal body and other similar matters.’ ”

[13] Applicant’s case throughout was that there is no dispute. In my view it is evident that there was a dispute in light of annexure “L” and that applicant should have resorted to the agreement and acted upon it. Instead it elected to persist with litigation. I am not persuaded that the disagreement does not fall within the terms of the arbitration clause.

[14] Having duly considered the papers and in applying the Plascon Evans Rule, I am of the view that the applicant had failed to establish the requirements of the relief sought before me.

[15] Accordingly the application is dismissed with costs.

________

Steyn, J

Date of Hearing: 11 April 2011

Date of Judgment: 8 June 2011

Counsel for the applicant: Adv H De Beer SC

Instructed by: Pearce du Toit & Moodie

Counsel for the respondents Adv M W Collins

Instructed by: V Chetty Inc.

1See Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A) at 634H-I.

1See Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA

623 (A) at 634H-I.

2Clause 30.3 reads: “After receipt of an interim payment certificate, or after receipt of interim payment should there not be provision for a payment certificate in terms of the principal agreement, the contractor shall, upon an application by the sub-contractor disclose to the sub-contractor all available details concerning the quantities of the sub-contract works included in the payment certificate or interim payment.”

2Clause 30.3 reads:

“After receipt of an interim payment certificate, or after receipt of interim payment should there not be provision for a payment certificate in terms of the principal agreement, the contractor shall, upon an application by the sub-contractor disclose to the sub-contractor all available details concerning the quantities of the sub-contract works included in the payment certificate or interim payment.”

3See Shorter Oxford English Dictionary 5th edition (Oxford University Press) 2002 at 709.

3See Shorter Oxford English Dictionary 5th edition (Oxford University Press)

2002 at 709.

4See page 67 of papers.

5See para 24(b) at page 22.

6See Universiteit van Stellenbosch v JA Louw 1983 (4) SA 321(A) at 333H– 334A.

6See Universiteit van Stellenbosch v JA Louw 1983 (4) SA 321(A) at 333H–

334A.

7 2011 (3) SA 631 (KZD).

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A)

Case cited

Aveng (Africa) Ltd formerly Grinaker-LTA t/a Grinaker-LTA Building East v Midros Investments (Pty) Ltd 2011 (3) SA 631 (KZD)

Case cited

Lufuno Mphaphuli and Associates v Andrews [2009] ZACC 6

Case cited

Universiteit van Stellenbosch v JA Louw 1983 (4) SA 321(A)

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.