Sibeko and Others v A Re Shomeng Project Proprietary Limited and Others (LCC02/2024) [2024] ZALCC 31 (13 September 2024)
The court found that while the respondents submitted the required report three days late, the delay was minor and adequately explained by the applicants' lack of cooperation. The applicants failed to prove wilful or mala fide non-compliance by the respondents, particularly regarding the third respondent. The respondents demonstrated substantial compliance with the court order, providing suitable permanent housing, water, electricity, and arrangements for livestock. The applicants' contempt application was dismissed, and the respondents' counter-application for relocation was granted. The court condoned the late submission of the report and authorised eviction should the occupiers fail to...
- Citation
- [2024] ZALCC 31
- Parties
- Applicant: Letta Sibeko; Applicant: Christina Soko; Applicant: Meisi Emilinah Nkosi; Applicant: Aaron Tatshi Soko; Applicant: Elizabeth Minah Nkosi; Applicant: Sipho Mahlangu; Applicant: Phakamani Johannes Mahlangu; Respondent: A Re Shomeng Holdings Proprietary Limited; Respondent: A Re Shomeng Project Proprietary Limited; Respondent: Joseph Masikwameng
- Court
- Land Claims Court
- Jurisdiction
- South Africa
- Judgment Date
- 13 September 2024
- Case Number
- LCC02/2024
- Procedural Posture
- Urgent Application / Contempt Application and Counter Application; Final Judgment
- Outcome
- Contempt application dismissed; counter-application for relocation granted; late report submission condoned; eviction authorised if relocation not effected; no order as to costs.
- Judges
- Ncube
- Legal Topics
- Contempt of Court, Eviction, Relocation Order, Mining Rights, Alternative Accommodation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Letta Sibeko
Applicant
Christina Soko
Applicant
Meisi Emilinah Nkosi
Applicant
Aaron Tatshi Soko
Applicant
Elizabeth Minah Nkosi
Applicant
Sipho Mahlangu
Applicant
Phakamani Johannes Mahlangu
Applicant
A Re Shomeng Holdings Proprietary Limited
Respondent
A Re Shomeng Project Proprietary Limited
Respondent
Joseph Masikwameng
Respondent
Procedural Posture
Urgent Application / Contempt Application and Counter Application; Final Judgment
Legal Issues
- 1 Whether the respondents are in contempt of Cowen J's court order dated 29 February 2024.
- 2 Whether the respondents' late submission of the required report should be condoned.
- 3 Whether the occupiers must relocate to the newly constructed permanent houses as per the counter-application.
Ratio Decidendi
The court found that while the respondents submitted the required report three days late, the delay was minor and adequately explained by the applicants' lack of cooperation. The applicants failed to prove wilful or mala fide non-compliance by the respondents, particularly regarding the third respondent. The respondents demonstrated substantial compliance with the court order, providing suitable permanent housing, water, electricity, and arrangements for livestock. The applicants' contempt application was dismissed, and the respondents' counter-application for relocation was granted. The court condoned the late submission of the report and authorised eviction should the occupiers fail to...
Court Disposition
Contempt application dismissed; counter-application for relocation granted; late report submission condoned; eviction authorised if relocation not effected; no order as to costs.
Orders
- The application for contempt of court is dismissed.
- The respondents' late submission of the report is condoned.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment