Siemans (Pty) Limited v Eskom Holdings SOC Limited and Others (026621/2024) [2024] ZAGPJHC 555 (7 June 2024)

Siemans (Pty) Limited v Eskom Holdings SOC Limited and Others (026621/2024) [2024] ZAGPJHC 555 (7 June 2024)

The court found that Hitachi was disqualified from Part A of the tender by operation of the RFP's technical gatekeeper provisions prior to the request for extension of the validity period. Therefore, only Siemens and GE remained as valid tenderers for Part A, and both extended their validity periods. Eskom was not...

Source-derived case information.

Citation
[2024] ZAGPJHC 555
Parties
Applicant: Siemens (Pty) Limited; Respondent: Eskom Holdings SOC Limited; Respondent: GE Digital South Africa (Pty) Limited; Respondent: Hitachi Energy South Africa (Pty) Ltd
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
026621/2024
Procedural Posture
Review Application / Judgment
Outcome
Application dismissed with costs, including costs of interim relief and costs of two counsel on Scale C.
Judges
Unterhalter
Legal Topics
Public Procurement, Tender Validity Period, Judicial Review of Administrative Action, Competitive Bidding, Disqualification of Tender, Incumbency Advantage
Administrative Law Commercial and Corporate Public Procurement Tender Validity Period Judicial Review of Administrative Action Competitive Bidding Disqualification of Tender Incumbency Advantage

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Siemens (Pty) Limited

Applicant

Eskom Holdings SOC Limited

Respondent

GE Digital South Africa (Pty) Limited

Respondent

Hitachi Energy South Africa (Pty) Ltd

Respondent

Procedural Posture

Review Application / Judgment

  1. 1 Whether Eskom's award of the tender to GE Digital South Africa (Pty) Ltd after the expiry of the tender validity period was lawful.
  2. 2 Whether the failure of Hitachi to extend the tender validity period invalidated the tender process for all bidders.
  3. 3 Whether Siemens was unfairly disqualified for alleged non-compliance with tender requirements.

Ratio Decidendi

The court found that Hitachi was disqualified from Part A of the tender by operation of the RFP's technical gatekeeper provisions prior to the request for extension of the validity period. Therefore, only Siemens and GE remained as valid tenderers for Part A, and both extended their validity periods. Eskom was not required to seek extension from a disqualified bidder. The award to GE was made within the extended validity period and was thus lawful. Siemens' challenges regarding unfair disqualification and incumbency advantage were rejected on the evidence, as Eskom's evaluation was found to be objective and competitive, and no material unfairness or lack of transparency was established....

Court Disposition

Application dismissed with costs, including costs of interim relief and costs of two counsel on Scale C.

Orders

  • The application is dismissed with costs, which costs include the costs of the application for interim relief, on Scale C, inclusive of the costs of two counsel.