Sizazonke Electrical CC and Others v Eskom Holdings SOC Limited (222/2018) [2019] ZASCA 36 (29 March 2019)
The court held that Eskom did not repudiate the contracts with Sizazonke. The cancellation and suspension were lawful and justified due to Sizazonke's serious breach of health and safety obligations, which resulted in fatalities and injuries. The termination was effected in accordance with the contractual instruments and procedures, and Sizazonke conceded its breach. The argument that Eskom failed to follow the termination procedure under clause 90 of the NEC 3 contract was rejected, as the clause was intended for the benefit of Eskom and did not require Eskom to give notice to itself. The court found no evidence that Eskom elected not to cancel the contracts or waived its right to do so....
- Citation
- [2019] ZASCA 36
- Parties
- Appellant: Sizazonke Electrical CC; Appellant: Roshella Kishun; Appellant: Gert Abraham Cornelius Van Wyk; Respondent: Eskom Holdings SOC Limited
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 29 March 2019
- Case Number
- 222/2018
- Procedural Posture
- Civil Appeal / Appeal From Gauteng Division of the High Court, Pretoria
- Outcome
- Appeal dismissed with costs; appellant liable for wasted costs of trial postponement, including costs of two counsel.
- Judges
- Tshiqi, Mbha, Zondi, Davis, Carelse
- Legal Topics
- Repudiation of Contract, Contractual Damages, Health and Safety Breach, Termination of Contract, Loss of Profits
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sizazonke Electrical CC
Appellant
Roshella Kishun
Appellant
Gert Abraham Cornelius Van Wyk
Appellant
Eskom Holdings SOC Limited
Respondent
Procedural Posture
Civil Appeal / Appeal From Gauteng Division of the High Court, Pretoria
Legal Issues
- 1 Whether Eskom repudiated the contracts with Sizazonke by suspending it from its database and cancelling existing contracts.
- 2 Whether Sizazonke is entitled to damages for loss of profits based on contract or delict.
- 3 Whether Eskom followed the correct termination procedure under the NEC 3 Engineering and Construction Contract.
Ratio Decidendi
The court held that Eskom did not repudiate the contracts with Sizazonke. The cancellation and suspension were lawful and justified due to Sizazonke's serious breach of health and safety obligations, which resulted in fatalities and injuries. The termination was effected in accordance with the contractual instruments and procedures, and Sizazonke conceded its breach. The argument that Eskom failed to follow the termination procedure under clause 90 of the NEC 3 contract was rejected, as the clause was intended for the benefit of Eskom and did not require Eskom to give notice to itself. The court found no evidence that Eskom elected not to cancel the contracts or waived its right to do so....
Court Disposition
Appeal dismissed with costs; appellant liable for wasted costs of trial postponement, including costs of two counsel.
Orders
- The appeal is dismissed with costs.
- The appellant is liable to pay the costs of the postponement of the trial in October 2016, including the costs of two counsel.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment