Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Standard Bank of South Africa Limited v Sindile Project Enterprise CC and Others (32975/2014) [2016] ZAGPPHC 337 (29 April 2016)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the Bank failed to prove the existence and terms of the alleged oral agreement for the overdraft facility with Sindile Project Enterprise CC. The evidence, primarily electronic Notepad entries and a certificate of balance, did not establish the amount advanced, the applicable interest rate, or the repayment terms. The certificate of balance was not supported by proven facts and was disputed. As the principal debt was not established, the claim against the Sureties also failed, since their liability was contingent on the Bank proving indebtedness of the principal debtor. The court held that the Bank did not meet the burden of proof required for its claims.

Court disposition

Plaintiff's claim dismissed with costs.

Orders

  • The plaintiff's claim against the first, second, and third defendants is dismissed with costs.

02

Material facts

Parties

Standard Bank of South Africa Limited

Plaintiff Counsel: U Lottering

Sindile Project Enterprise CC

Defendant Counsel: HP West

Sindile Sewula Mthombeni

Defendant Counsel: HP West

Thulani Patrick Mthombeni

Defendant Counsel: HP West

Amounts and remedies

  • Claimed Overdraft Amount: ZAR 339,246.12
  • Suretyship Limit: ZAR 500,000

03

Procedural history

  1. Posture

    Civil Trial / Judgment After Trial

04

Questions and positions

Legal issues

Party arguments

Applicant
The Bank argued that Sindile Project Enterprise CC requested and was granted an overdraft facility, evidenced by electronic Notepad system entries and a certificate of balance. The Bank relied on section 15(4) of the Electronic Communications and Transactions Act to admit electronic records as evidence. The Bank asserted that the Sureties are liable up to R500,000 if the principal debt is proven, and that the certificate of balance constitutes prima facie proof of indebtedness.
Respondent
Sindile Project Enterprise CC denied the existence of any oral agreement and disputed the terms, particularly the interest rate and calculation method. The Sureties admitted signing the suretyship but limited liability to proven indebtedness. Defendants challenged the admissibility of the electronic records and certificate of balance, arguing that the Bank failed to prove the amount owed and the terms of the alleged agreement, and that the certificate was not signed by a manager as required.

05

Court’s reasoning

  1. 01

    Electronic Communications and Transactions Act 25 of 2002, s 15

    Section 15 of the Electronic Communications and Transactions Act provides for the admissibility and evidential weight of electronic data messages in legal proceedings, subject to reliability and certification requirements.

  2. 02

    McWilliams v First Consolidated Holdings (Pty) Ltd 1982 (2) SA 1 (A); Christie RH and Bradfield GB Christie's The Law of Contract in South Africa

    A plaintiff relying on an oral agreement must prove the parties, place, date, and material terms of the agreement, including the amount advanced and repayment terms.

  3. 03

    Muller and others v Botswana Development Corporation Ltd [2002] 3 All SA 663 (SCA)

    A surety may rely on any defence available to the principal debtor that arises from the obligation (defence in rem), but not from personal privilege (defence in personam).

06

Ratio, limits and disposition

Ratio decidendi

The court found that the Bank failed to prove the existence and terms of the alleged oral agreement for the overdraft facility with Sindile Project Enterprise CC. The evidence, primarily electronic Notepad entries and a certificate of balance, did not establish the amount advanced, the applicable interest rate, or the repayment terms. The certificate of balance was not supported by proven facts and was disputed. As the principal debt was not established, the claim against the Sureties also failed, since their liability was contingent on the Bank proving indebtedness of the principal debtor. The court held that the Bank did not meet the burden of proof required for its claims.

Obiter and limits

  • The court noted that electronic records may be admissible under the ECTA if properly certified and reliable, but mere production does not guarantee evidential weight without supporting facts.
  • The Sureties' liability is strictly dependent on the existence of proven indebtedness of the principal debtor, regardless of the certificate of balance provisions.

Court disposition

Plaintiff's claim dismissed with costs.

  • The plaintiff's claim against the first, second, and third defendants is dismissed with costs.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2016] ZAGPPHC 337

IN THE HIGH COURT

OF SOUTH AFRICA

GAUTENG DIVISION, PRETORIA

29/4/16

CASE NO: 32975/2014

Not reportable

Not of interest to other judges

Revised.

In the matter between:

THE STANDARD BANK

OF SOUTH AFRICA LIMITED Plaintiff

and

SINDILE PROJECT

ENTERPRISE CC First

Defendant

SINDILE SEWULA MTHOMBENI Second

Defendant

THULANI PATRICK MTHOMBENI Third

Defendant

DATE

OF HEARING : 26 FEBRUARY 2016

DATE OF JUDGMENT : 29 APRIL 2016

JUDGMENT

MANAMELA AJ

Introduction

[l] Plaintiff (the Bank) claims an amount of R339 246.12 first defendant (Sindile Project) in respect of an overdraft facility based on an alleged oral agreement. Second and third defendants (the Sureties) are before the court due to a limited suretyship agreement they signed for indebtedness of Sindile Project to the Bank.

[2] Sindile Project denies entering into an oral agreement with the Bank. On the other hand, the Sureties admit liability to the Bank to the extent proven by the Bank against Sindile Project. In other words the success of the Bank's case against Sindile Project will trigger the liability of the Sureties for the proven amount.

[3] The matter came before me as an trial on 26 February 2016 and the parties agreed, with my approval, at the end of the trial to file heads of argument by 04 March (for the plaintiff) and 08 March 2016 (for the defendants). I am grateful for the filed heads of argument. I will deal with the material from the heads of argument, including the events at the trial a bit later. First the pleaded cases of the contending parties.

The Bank's pleaded case

[4] The Bank pleaded, m its particulars of claim, the following case against Sindile Project. Sindile Project holds or held at the

material times, a business current account with the Bank (the Bank Account).[1] On or about 26 October 2006, at Brakpan, the Bank and Sindile Project entered into an oral agreement for an overdraft facility, for an unspecified amount, based on the Bank Account.[2] The express, alternatively implied terms[3] of the oral agreement were, among others, that Sindile Project would be liable for interest at the rate of 17.10% or as advised from time to time;[4] the money due on the overdraft facility would become immediately due and payable on demand by the Bank,[5] and a certificate signed by any manager or administrator of the Bank, whose appointment need not be proved shall be proof of the contents thereof until shown or proven otherwise.[6] The Bank demanded payment of the amount of R339 246.12, plus interest at the rate of 17.10% calculated daily and compounded monthly in arrears from 25 February 2014 to date of payment from Sindile Project, but in vain.[7] The claimed amount also appears on a certificate of balance attached to the particulars of claim.[8]

[5] Against the Sureties, the Bank essentially pleaded the following case. On or about 15 March 2012 at Brakpan,[9] the Sureties, other than binding themselves as such, also bound themselves as co-principal debtors in solidum to the Bank in respect of Sindile Project's existing (then) and any future liability[10] to the Bank. The "salient terms" of the suretyship were that the Sureties, among others, are jointly and severally bound; and a certificate signed by any manager or accountant of the Bank, whose appointment need not be proved shall be prima facie proof of the contents thereof. The Bank demanded payment of the outstanding amount from the Sureties and complied with the requirements of National Credit Act 34 of 2005, but in vain.[11] No payment was received from the Sureties.

Sindile Project's pleaded defence

[6] As stated above, Sindile Project denies the alleged oral agreement and its terms.[12] It does not appear to deny operating the Bank Account though.[13] Consequently, it denies liability and dispute the certificate of balance verifying the outstanding amount.

The Sureties' pleaded defence

[7] On the other hand, the Sureties admit signing the suretyship, but deny, in some respects, the terms thereof as pleaded by the Bank.[14] The essence of the Sureties' defence is captured in the following:

"To the extent that the Plaintiff may be successful in obtaining judgement against the First Defendant in terms of this proceedings, the Second and Third Defendants admit their liability for payment thereof as sureties in terms of the Deed of Suretyship "B", limited to the amount of R5 00 000-00."[15]

[underlining added]

[8] The Sureties also admit receiving notices from the Bank in terms of section 129 of the National Credit Act.

The Trial

[10] At the trial, the Bank called as witnesses, two of its employees, namely Ms Somayya Koobair and Ms Nyameka Jaca. Both of them were not subjected to cross-examination by Mr HP West, appearing on behalf of the defendants. This means they simply stepped down after being led by Ms U Lottering, on behalf of the Bank.

[11] Ms Koobair, was the relationship manager of business accounts. Ms Koobair assisted the second defendant, Mr Sindile Mthombeni to open up the Bank Account of Sindile Project at Brakpan. For the rest of her evidence, she relied on printouts or extracts from an electronic or computer system called CCDS, also called the Notepad system. The Notepad system is used by employees of the Bank and is only accessible to them. In the form of entries captured on the Notepad system, employees of the Bank record activities on customers' accounts, including telephonic and personal communications with customers. The entries are numbered sequentially and once captured they cannot be deleted. Correction of entries made or data already captured is only possible by means of subsequent or new entries of the system.

[12] Ms Koobair further testified as follows. The "Customer" called the Bank and requested "overdraft facility or working capital" on 24 June 2006.[17] She explained that the reference to the "Customer" is to Sindile Project. The telephone call would in all probabilities have been made by the second defendant acting on behalf of Sindile Project.[18] The Bank Account belongs to Sindile Project.[19] The overdraft facility was to be for R300 000.00,[20] which was awarded against security of the suretyship. She also referred to other Notepad system entries between 16 and 24 March

2012.[21] These entries refer to an overdraft facility of R300 000.00. The note made on 24 March 2012 reads in the material part:

"R500K held as per previous notes ... Out of NCA. Agreed to facility R300K @ prime + 8.60% until 2013.03.24 as same is scored and justified by t/o generated . Subject to por confirming FICA compliance. Once condition has been met, kindly contact Tracy Murugan for the limit to be loaded.”[22]

[13] She also referred to statement issued by the Bank to Sindile Project dated 31 March 2012.[23] This statement states the overdraft limit as R300 000 and applicable rate of interest of 17.600% on the Bank Account. She said that the facility did not reflect frequent deposits or payments and ultimately it was placed in what is called "lock-up". She explained this to mean that, although deposits may be made into the account no withdrawals are possible when an account is in "lock-up". This appears to have happened twice in this matter. The Sureties had made payment after the first "lock-up" and the account released. She also referred to other entries on the Notepad system.

[14] Ms Jaca, employed as the Bank's business lending and manager at the Bank's call centre, also relied on the printouts or extracts from the Notepad system for her testimony. For most of her testimony she repeated what was said by Koobair. She confirmed that she knew the author of the balance certificate as her senior manager[24] and also commented on the outstanding amount as reflected thereon. She was the second and final witness for the Bank. The Bank closed its case after her testimony.

[15] The defendants did not lead any evidence and closed their case without calling any witness. As indicated above, there was no

cross-examination of the two witnesses for the Bank. The parties agreed with the sanction of the court to file heads of argument in lieu of closing legal arguments.[25]

The Bank's heads of argument

[16] The heads of argument quite expectedly served as a substitute for closing arguments by counsel on behalf of the parties. Therein, the Bank appreciated the obligation to establish the oral agreement regarding the overdraft facility between itself and Sindile Project. In this regard, it is submitted that, the Bank needs to prove the essentialia of the contract between the parties consisting of the parties; material terms; date and place of the agreement.[26]

[17] It is submitted that the extracts or printout from the Bank's Notepad system as certified and confirmed under oath by the Bank's manager: legal, personal and business banking credit division[27] should be accepted in terms of section 15(4) of the Electronic Communications and Transactions Act 25 of 2002.[28]

[18] The submissions conclude that the Bank has acquitted itself well regarding proving its case against the defendants. The court must accept the version placed before the court by the witnesses on behalf of the Bank, as no questions were posed to the witnesses and no version was put to the witnesses on behalf of the defendants.

Defendants' Heads of argument

[19] The Bank's case against the defendants is ex contractu and is premised on an oral agreement in respect of Sindile Project and written suretyship in respect of the Sureties, it is submitted. The cause of action against Sindile Project is distinct from the cause of action against the Sureties, although the two are closely related.

[20] Regarding the terms of the oral agreement, it is submitted that although there is mention of the rate of interest at 17.10% or as advised from time to time in the summons,[29] there is no specificity on how and when the interest would be calculated. The argument on behalf of the defendants in this regard

is the conclusion that it is "improbable that parties would agree to such a vague term regarding interest".[30] Further, in the Notepad entries and the bank statement, reference is made to an interest rate of 17.6%, which is at odds with the rate of 17.10% allegedly agreed upon by the parties upon conclusion of the oral agreement.

[21] It is also submitted that it is improbable that the parties would have agreed to a term providing that a balance certificate is to be used for proof of a loan and/or any other amount and did not mention or refer to the overdraft facility. Further, it is pointed out that the Bank may have been able to prove the capital amount drawn in terms of the overdraft, but this is not the pleaded case for the Bank. Therefore, the Bank has also failed to prove the other terms and conditions of the alleged oral agreement, it is contended.

[22] Regarding the claim against the Sureties it is submitted that they bound themselves as sureties and co-principal debtors in solidum to the Bank. The Bank has to prove the causa debitis in respect of the principal debtor's undertaken liability[31] and the amount owed or indebtedness of the principal debtor. It is submitted that there may be a conundrum in terms of the latter issue as the suretyship provides that a certificate signed by any of the Bank's managers constitute sufficient proof of any amount due in terms of the suretyship until the contrary is proved. However, it is submitted that the Sureties are entitled to raise or rely on any defence, which is in rem (i.e. arising from the obligation) available to Sindile Project, as the principal debtor. As indicated above, the Sureties rely on the Bank's failure to prove the amount owed by Sindile Project, as both its witnesses could not give admissible evidence regarding the outstanding balance.[32]

[23] Further the defendants dispute the validity of the Bank's reliance on provisions of the Electronic Communications and Transactions Act 25 of 2002 (the ECTA) for the bank statements referred to during the trial. It is argued that the certificate accompanying the documents only refer "the actual copies of the data stored" on the Bank's electronic computer system, and not the bank statements.[33] Therefore, the bank statement is not admissible as evidence in terms of the Bank's certificate prepared in terms of the provisions of the ECTA. It is argued that the certificate also did not identify the Sureties and the witnesses failed to establish the signatory to the certificate as a manager of the Bank. This, it is argued, makes the balance certificate not to be admissible or renders it lacking of prima facie proof as it is not signed by a manager of the Bank.

Applicable legal principles

[24] The evidence in this matter is significantly located in the printouts of data from the Bank's Notepad system. Section 15 of the ECTA carries the most relevant legal principles in this regard. It reads in the material part:

"15. Admissibility and evidential weight of data messages.--(l) In any legal proceedings, the rules of evidence must not be applied so as to deny the admissibility of a data message, in evidence-

(a) on the mere grounds that it is constituted by a data message; or

(b) if it is the best evidence that the person adducing it could reasonably be expected to obtain, on the grounds that it is not in its original form.

(2) Information in the form of a data message must be given due evidential weight.

(3) In assessing the evidential weight of a data message, regard must be had to-

(a) the reliability of the manner in which the data message was generated, stored or communicated;

(b) the reliability of the manner m which the integrity of the data message was maintained;

(c) the manner in which its originator was identified; and

(d) any other relevant factor.

(4) A data message made by a person in the ordinary course of business, or a copy or printout of or an extract from such data message certified to be correct by an officer in the service of such person, is on its mere production in any civil, criminal, administrative or disciplinary proceedings under any law, the rules of a self regulatory organisation or any other law or the common law, admissi ble in evidence against any person and rebuttable proof of the facts contained in such record, copy, printout or extract."

[I added underlining for emphasis]

[25] This provision was relied upon by the Bank for establishing admissibility and evidential weight of the Notepad entries. In terms of section 1 of the ECTA "data message" is

"data generated, sent, received or stored by electronic means and includes-

(a) voice, where the voice is used in an automated transaction; and

(b) a stored record"

[26] Without much ado on this, I accept that the Notepad entries relied upon by the Bank constitute data messages and therefore their admissibility and evidential weight is competent through compliance with provisions of section 15 of the ECTA.[34] I also find that the Bank has met the statutory requirements to rely on this evidence.

[27] It is common cause that the Bank needs to establish and prove, for a successful claim based on an oral agreement, against Sindile Project, the following formalities: parties, place, date and terms of agreement.[35] It is also common cause that the alleged agreement between the parties, concerns monies lent and advanced in terms of the overdraft facility. Therefore, the terms of the alleged agreement has to include the amount advanced; how and when is the money repayable.[36] I make use of subheadings to deal with the evidence on these issues.

Parties, date and place of agreement

[28] From the evidence led at the trial in the form of Notepad entries, there was a telephone call or calls on behalf of Sindile Project requesting "overdraft facility or working capital" on 24 June 2006.[37] Ms Koobair testified that the reference to the "Customer" on the entry is to Sindile Project. The telephone call probably made by the second or third defendant on behalf of Sindile Project.[38] The Bank Account belongs to Sindile Project.[39] Other entries made between 16 and 24 March 2012, were also referred to by Ms Koobair.[40] These entries refer to an overdraft facility of R300 000.00.

[29] With these I am convinced that the parties to the alleged agreement have been established or proven as the Bank and Sindile Project. Both parties have acted through their representatives who orally interacted with each other.

[30] However, the dates of the aforementioned entries differ with the pleaded date of the agreement: 26 October 2006.[41] It may be that this date was erroneous, as it is when the bank account for Sindile Project was opened, which is in writing,[42] and not the agreement for overdraft facility. The possible date of agreement is either 24 March 2012 or 24 June 2006 or both. The same error appears to have been made in respect of the place of agreement.[43]

Terms of agreement

[31] Although the Notepad entry above refers to the request for an overdraft facility or working capital, it also refers to other issues which are not clear whether they formed part of the call or were notes made by the recipient of the call on behalf of the Bank. For example, the note on 24 June 2006 refers to "FICA compliant. Suretyship held as per previous history note. Interest rate loaded as per GRG. Limit loaded into CL and BRI"[44] [italics added] Be that as it may, the only relevant aspect of the italicised words, in my view, is the reference to the interest rate. But the rate and how it is to be computed is not indicated. The amount agreed upon for the overdraft facility is also not stated.

[32] Further, in terms of the note made on 15 June 2006, Sindile Project needed 10% deposit towards a motor vehicle; to make payment to SARS on 25 June 2006 and "requested overdraft of R30k to assist with payments".[45] Therefore, according to this note the overdraft was for R30 000.00. However, in terms of the Notepad entries 125-128 between 16 and 24 March 2012, there was another request for an overdraft.[46] The amount for the latter request or overdraft facility was R300 000.00.[47]

[33] Therefore, from the above entries there were requests for an overdraft facility in June 2006 for R30 000.00 and March 2012 for R300 000.00. With regard to the R300 000.00 facility, there is also mention of the applicable rate of interest stated as prime plus 8.60% and it also appears that the facility was until 24 March 2013, which would have been about a year from date of the note (i.e. 24 March 2012). There is no mention of how the rate is to be calculated and at what intervals. It ought to be borne in mind that the Bank's pleaded case, in this regard, is that Sindile Project is liable for interest on all overdue accounts at the rate of 17.10% or as advised from time to time.[48] The rate of interest is also stated on statement issued by the plaintiff to Sindile Project dated 31 March 2012. However, there is no evidence confirming that this was the only rate of interest used for calculating the outstanding amount or whether there were any changes. Also there is no evidence confirming that Sindile Project accepted this and other terms of the alleged agreement with the plaintiff. Therefore, I find that the Bank has failed to establish the existence of an oral agreement with Sindile Project as alleged.

[34] Although, it is clear that monies were advanced in terms of the overdraft facility, there is no evidence on the repayment terms

thereof. Although, Ms Koobair testified about the balance of R339 246.12 reflected on bank statement as at 28 February 2014, as owing, there was no evidence of how the amount is made up. The certificate of balance is also not sustained by the proven facts, as it is grounded on existence of the oral agreement. As stated above the overdraft facility was in a capital amount of R300 000.00 and therefore the outstanding amount comprises the capital amount and interest charges. It is also conceivable that there would have been other charges by the Bank for operation of the Bank Account and availing or "initiating" the overdraft facility.[49] The certificate of balance attached to the papers is disputed and therefore unhelpful in this regard.

Suretyship and the Sureties

[35] Now briefly on the suretyship and the Sureties. There is no real dispute between the Bank and the Sureties, as the Sureties have admitted liability in respect of any amount the Bank successfully proves against Sindile Project up to their suretyship limit of R500 000.00. They rely on the same defence raised by Sindile Project as the principal debtor, being to deny existence of the indebtedness based on the oral agreement. This is a defence in rem as opposed to a defence in personam to the principal debtor.[50] In Muller and others v Botswana Development Corporation Ltd[51] the following was said:

“The general rule relating to sureties is that a surety may rely on any defence which is open to the principal debtor, provided such defence arises upon the obligation (one in rem) and not from some personal privilege granted to the debtor (a defence inpersonam).”

[quoted without accompanying authorities]

[36] Therefore, in my view, the claim against the Sureties will fail because of the failure of the claim against Sindile Project. This is so, despite the fact that the certificate of balance, in terms of the suretyship agreement, constitutes prima facie proof of indebtedness against the Sureties. Such certificate is only a form or means of proving indebtedness and not the substance of the indebtedness. Absent proof of indebtedness on the side of the Sureties due to failure of the Bank's case against Sindile Project, the certificate is incompetent of proving any liability for the Sureties.

Conclusion and Order

[37] Against the backdrop of what is stated above, I find that the claim by the Bank, as plaintiff, against Sindile Project, as first defendant, and the Sureties, as second and third defendants, is unsuccessful. Costs will follow this result.

[38] In the premises, I make the following order:

(a) The plaintiff's claim against first. second and third defendants is dismissed with costs.

_____

K. La M. Manamela

Acting Judge of the High Court

29 April 2016

Appearances:

For the Plaintiff

:

Adv U Lottering

Instructed by

:

Findlay & Niemeyer Attorneys Pretoria

For the 151, 2nd and 3rd Defendants :

Adv HP West

Instructed by

:

Locketts Attorneys Pretoria

[1] See par 5 of the particulars of claim on indexed p 4 of the pleadings bundle; pp 1-6 of the trial bundle.

[2] Ibid.

[3] See par 6 of the particulars of claim on indexed p 4 of the pleadings bundle.

[4] See par 7.2 of the particulars of claim on indexed p 4 of the pleadings bundle.

[5] See par 7.1 of the particulars of claim on indexed p 4 of the pleadings bundle.

[6] See par 7.3 of the particulars of claim on indexed pp 4-5 of the pleadings bundle.

[7] See prayer 2 of the particulars of claim on indexed p 17 of the pleadings bundle; par 8 of the particulars of claim on indexed p 5.

[8] See par 7.4 of the particulars of claim on indexed p 5; annexure "A" on indexed p 19 of the pleadings bundle.

[9] See par 9 of the particulars of claim on indexed p 5; annexure "B" on indexed p 20 of the pleadings bundle.

[10] The liability or indebtedness included loans; promissory notes; overdrafts and credit and debit card transactions. See pars 10.2.3-1

1.6 of the particulars of claim on indexed pp 6-10 of the pleadings bundle.

[11] See par 15 of the particulars of claim on indexed pp 14-16 of the pleadings bundle.

[12] See pars 3-5 of the first, second and defendants' plea (defendants' plea) on indexed p 30 of the pleadings bundle.

[13] See par 3 of the defendants' plea on indexed p 30 of the pleadings bundle.

[14] See pars 7 and 8 of the defendants' plea on indexed p 31 of the pleadings bundle.

[15] See par 9 of the defendants' plea on indexed p 31 of the pleadings bundle.

[16] See par I 0.1 on indexed p 7 of the pre-trial bundle.

[17] See trial bundle p 21.

[18] The pronoun used is "he" and the rest of the material attributed to the telephone conversation leaves no doubt that it was someone in authority from Sindile Project.

[19] See trial bundle pp 1-6.

[20] See Notepad entries 125-128 on 16-24 March 2012 on indexed pp 51-55 of the pre-trial bundle.

[21] See trial bundle pp 51-55.

[22] See trial bundle pp 55.

[23] See trial bundle pp 111.

[24] See annexure "A" on indexed p 19 of the pleadings bundle.

[25] See par 3 above.

[26] See Harms LTC Amler's Precedents of Pleadings 8th edition (LexisNexis Durban 2015) (Amlers) at pp 104-110; Christie RH and

Bradfield GB Christie's The Law of Contract in South Africa 6th edition (LexisNexis Durban 2011) at pp 164-165; generally McWilliams

v First Consolidated Holdings (Pty) Ltd 1982 (2) SA I (A).

[27] See trial bundle pp 70-71.

[28] See par 24 below.

[29] See par 7.2 on p 4 of the pleadings bundle.

[30] See par 3.2 of the defendants' heads of argument.

[31] See Dowson & Dobson Industrial ltd v Van der Werf 1981 (4) SA 417 (C) 431.

[32] See La Consortium & Vending CC t/a LA Enterprises v MTN Service Provider (Pty) ltd 201 1 (4) SA 577 (GSJ) at 5920 at par 19.

[33] See generally la Consortium & Vending CC t/a LA Enterprises v MTN Service Provider (Pty) ltd 201 1 (4) SA 577 (GSJ).

[34] See La Consortium & Vending CC tla LA Enterprises v MTN Service Provider (Pty) Ltd 2011 (4) SA 577 (GSJ) at 5920 at par 19.

[35] See Amlers at pp 104-105; Christie RH and Bradfield GB Christie's The Law of Contract in South Africa 61 edition (LexisNexis Durban 201 1) at pp 164-165; generally McWilliams v First Consolidated Holdings (Pty) Ltd 1982 (2) SA 1 (A).

[36] See Amlers at p 144.

[37] See trial bundle p 21.

[38] The pronoun used is "he" and the rest of the material attributed to the telephone conversation leaves no doubt that it was someone in authority from Sindile Project.

[39] See trial bundle pp 1-6.

[40] See trial bundle pp 51-55.

[41] See par 5 on pleadings bundle p 4; par 7 of the defendants' heads of argument.

[42] See trial bundle pp 1-6.

[43] Ibid.

[44] See trial bundle p 21.

[45] See trial bundle p 20.

[46] See trial bundle pp 51-55.

[47] See trial bundle p 55; pars 12 and 28 above.

[48] See pleadings bundle on p 4; par 14 of plaintiff s heads of argument.

[49] See trial bundle p 53.

[50] See Du Bois F (ed) Wille 's Principles of South African Law 9th edition (Juta Cape Town 2007) on pp 1022- 1025.

[51] [2002] 3 All SA 663 (SCA).

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

McWilliams v First Consolidated Holdings (Pty) Ltd 1982 (2) SA 1 (A)

Case cited

Muller and others v Botswana Development Corporation Ltd [2002] 3 All SA 663 (SCA)

Case cited

Dowson & Dobson Industrial Ltd v Van der Werf 1981 (4) SA 417 (C)

Case cited

La Consortium & Vending CC t/a LA Enterprises v MTN Service Provider (Pty) Ltd 2011 (4) SA 577 (GSJ)

Case cited

Electronic Communications and Transactions Act 25 of 2002

Legislation

Legislation referenced in the available case record.

National Credit Act 34 of 2005

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.