Download PDF

South Africa Judgment

South Gauteng High Court, Johannesburg

Steve Biko Foundation v Frese NO and Another (A5008/2017) [2018] ZAGPJHC 446 (7 March 2018)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The appeal succeeded because the relief sought by the applicant was to make the adjudicator's award an order of court, not to enforce a contractual obligation or obtain payment. The contract distinguished between an award and enforcement of contractual obligations. The adjudicator's award was not final, as arbitration had not been held and the award was subject to the outcome of arbitration. The applicant did not lay the necessary factual basis for enforcement of contractual obligations, and the court a quo erred in granting relief not sought or pleaded. Proper procedure requires that parties be given notice and opportunity to address any altered claim. Accordingly, the application was dismissed with costs.

Court disposition

Appeal upheld; application dismissed with costs.

Orders

  • The application is dismissed with costs.

02

Material facts

Parties

Steve Biko Foundation

Appellant Counsel: AJ Eyles SC

Jorg Rainer Frese NO

Respondent Counsel: J Daniels

Rainbow Construction (Pty) Limited

Respondent

Amounts and remedies

  • Contract Price: ZAR 74,000,000

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From Judgment of Mahalelo J in the Court a Quo

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that, in terms of clause 40.3.3 of the contract and Rule 7.2.2 of the adjudication rules, the adjudicator's award was binding and enforceable on the parties unless and until revised by an arbitrator. The applicant contended that it was entitled to have the adjudicator's award made an order of court and that the notice of dissatisfaction did not detract from its enforceability.
Respondent
The respondent submitted that the relief sought was to make the adjudicator's award an order of court, not to enforce a contractual obligation or obtain payment. The respondent argued that the award was not final, as the arbitration had not been held, and that the applicant had not laid the necessary factual basis for enforcement of contractual obligations. The respondent further contended that the court a quo was not entitled to grant relief not sought or pleaded by the applicant.

05

Court’s reasoning

  1. 01

    Vidavsky v Body Corporate of Sunhill Villas 2005 (5) SA 200 (SCA) at para 17

    To enforce an award as an order of court, the applicant must possess an award that can properly form the subject of a court order.

  2. 02

    Kauesa v Minister of Home Affairs and Others 1996 (4) SA 965 and 973; Johannesburg City Council v Bruma Thirty-Two (Pty) Limited 1984 (4) SA 87 (T)

    If a matter is to be decided on a basis other than that pleaded, proper notice must be given to the parties to allow them to address the altered claim.

  3. 03

    Cool Ideas 1186 CC v Hubbard and Another 2014 (4) SA 474 (CC)

    An application for enforcement of an arbitration award is distinguishable from a claim for payment of money.

06

Ratio, limits and disposition

Ratio decidendi

The appeal succeeded because the relief sought by the applicant was to make the adjudicator's award an order of court, not to enforce a contractual obligation or obtain payment. The contract distinguished between an award and enforcement of contractual obligations. The adjudicator's award was not final, as arbitration had not been held and the award was subject to the outcome of arbitration. The applicant did not lay the necessary factual basis for enforcement of contractual obligations, and the court a quo erred in granting relief not sought or pleaded. Proper procedure requires that parties be given notice and opportunity to address any altered claim. Accordingly, the application was dismissed with costs.

Obiter and limits

  • The distinction between making an award an order of court and enforcing contractual obligations is critical in adjudication and arbitration proceedings.
  • Proper notice and opportunity to address altered claims are essential for procedural fairness in litigation.

Court disposition

Appeal upheld; application dismissed with costs.

  • The application is dismissed with costs.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Judgment

[2018] ZAGPJHC 446

REPUBLIC

OF SOUTH AFRICA

IN

THE HIGH COURT OF SOUTH AFRICA

GAUTENG LOCAL DIVISION, JOHANNESBURG

Case Number: A5008/2017

NOT

REPORTABLE

NOT

OF INTEREST TO OTHER JUDGES

REVISED

7/3/2018

In the matter between:

STEVE

BIKO FOUNDATION

(IT3566/1998)

Appellant

(represented by its trustees for the time being) (1st Respondent in court a quo)

and

JORG

RAINER FRESE N .O 1ST Respondent

(in his capacity as the business rescue (Applicant

in court a quo)

Practitioner of Rainbow Construction (Pty) Ltd,

In business rescue/under supervision)

RAINBOW CONSTRUCTION (PTY) LIMITED 2nd Respondent

(in business rescue/under supervision) (2nd Respondent in court a quo)

JUDGMENT

MOKOSE AJ

[1] This is an appeal against the judgement of Mahalelo J. For the sake of convenience, the parties are referred to herein as they were referred to in the application before the court a quo. The applicant, the business rescue practitioner of the second respondent, brought an application against both the first and second respondents seeking the following relief:

“1. That the adjudicator’s award published on 10 January 2013 and annexed to the Notice of Motion as X.1, be made an order of court.

2. That the adjudicator’s award published on 28 January 2013 and annexed to the Notice of Motion as X2, be made an order of court.

3. Directing the first respondent to pay the costs of this application.

4. Further and/or alternative relief.”

[2] On 15 October 2010 the first and second respondent (which was at the time not subject to business rescue proceedings) concluded a building contract in terms of which the second respondent was to perform certain works for the first respondent for a contract price of approximately R74 million. The second respondent commenced the works and was in the process of completing the works when it was placed under business rescue in September 2011. The second respondent continued with the works notwithstanding that it was placed under business rescue. During December 2012 disputes arose between the parties. The disputes fell to be determined in accordance with the procedure set out in the contract.

[3] Clause 40 of the contract dealt with what was to occur in the event of a disagreement between the parties. Clause 40.1 provides that in the event of a disagreement arising either party may give notice to the other to resolve such disagreement. Clause 40.2 provides that if the disagreement is not resolved within 10 working days of receipt of notice, the disagreement is deemed to be a dispute and shall be referred by the party which gave such notice to either adjudication (clause 40.2.1) or arbitration (clause 40.2.2). The disputes were referred to adjudication and an adjudicator appointed. In due course the adjudicator published two awards annexed to the notice of motion as X1 and X2.

[4] The first respondent was dissatisfied with the awards and gave notice to the second respondent and the adjudicator of such dissatisfaction

within the required time and referred the dispute to arbitration. The notice given by the first respondent was in accordance with the provisions of clause 40.3.4 which read as follows:

“40.3.4 Should either party be dissatisfied with the decision given by the adjudicator….the dissatisfied party shall refer the dispute to arbitration.”

[5] In consequence of the steps taken by the first respondent the awards were not final but were subject to the outcome of the arbitration.

During January 2013 the applicant requested the first respondent to confirm that it was approaching the Association of Arbitrators for the appointment of an arbitrator. The first respondent proposed that before it approached the Association of Arbitrators the parties attempt to agree on the appointment of a mutually acceptable arbitrator. During April 2013 the applicant advised the first respondent that it would revert to the first respondent concerning the proposal. The applicant never reverted. The applicant’s written consent to proceed with the arbitration was never given as required by Section 165 of the Companies Act 71 of 2008. The first respondent has not yet approached the Association of Arbitrators and the arbitration is pending.

[6] The applicant brought an application to this court seeking to make the awards orders of court notwithstanding that the arbitration had not been finalised. The applicant sought the relief set out above and expressly stated the following:

“7. I depose to this affidavit in support of an application to have an adjudicator’s award made an order of court…”

[7] The applicant submitted that by reason of clause 40.3.3 of the contract, notwithstanding the referral to arbitration, the adjudicator’s award was binding on the parties who were obliged to give effect to it without delay unless and until it was subsequently revised by an arbitrator. The applicant’s further submission was that in terms of the adjudication rules and in particular, Rule 7.2.2, it was entitled to apply to court for the enforcement of the determination as a contractual obligation.

[8] The court a quo accepted that the award could not be made an order of court but held that the applicant’s use of terminology had not prejudiced the first respondent. The court accordingly held that the adjudicator’s award was enforceable and that the notice of dissatisfaction did not detract from its enforceability. The court accordingly made the following order:

“51.1 The respondent is ordered to forthwith give effect to the adjudicator’s determination handed down on 10 January 2013 and annexed to the notice of motion as X1 and 28 January 2013 annexed to the Notice of Motion as X2;

51.2 That the order in paragraph 1 above shall endure until such time, if at all, that the said decision of the adjudicator is revised in amicable settlement or an arbitral award;

51.3 The respondent shall pay the applicant’s costs of the application.”

[9] The relief claimed by the applicant as well as the cause of the action which founded that relief was to make the awards orders of court. The relief claimed by the applicant was not directed towards obtaining payment of money or enforcing a contractual

obligation. Had the applicant claimed enforcement of the contractual obligations arising out of the contract, the relief

sought would have been different, other allegations would have had to have been made and the first respondent would have had the

opportunity of dealing with the allegations to raise whatever defences and factual matters it had in relation thereto.

[10] The contract between the first and second respondents recognises the difference between an award and the enforcement of contractual

obligations. To establish a right to enforce the award, the applicant was required to establish that it is in possession of an award that can properly form the subject of an order of court. See: Vidavsky v Body Corporate of Sunhill Villas 2005 (5) SA 200 (SCA) at paragraph 17.

[11] There was no arbitration award which could be made an order of court as no arbitration had been held and as the adjudication itself had not been finalised. As such, the award was subject to the outcome of the arbitration.

[12] The court a quo was not entitled to consider whether or not a contractual provision was to be enforced as this was not the issue before it. The applicant did not seek relief in the form of the enforcement of a contractual obligation. There was no factual basis laid for relief in the form of the enforcement of the contractual obligation. If the matter was to be decided on a basis otherwise than that laid out, proper notice had to be given to the parties who would be entitled to be afforded appropriate time to deal with the altered claim. See: Kauesa v Minister of Home Affairs and Others 1996 (4) SA 965 and 973. See also: Johannesburg City Council v Bruma Thirty-Two (Pty) Limited 1984 (4) SA 87 (T).

[13] The matter before us is distinguishable in that it is an application for the enforcement of an arbitration award as opposed to a claim for the payment of money. See Cool Ideas 1186 CC v Hubbard and Another 2014 (4) SA 474 (CC)

[14] In the premises, the appeal is upheld with costs and the order of the court a quo substituted as follows:

“The application is dismissed with costs.”

________

SNI

MOKOSE

ACTING

JUDGE OF THE HIGH COURT OF SOUTH AFRICA

I agree

_______

CG

LAMONT

JUDGE

OF THE HIGH COURT OF SOUTH AFRICA

MA

MAKUME

For the Appellant:

AJ EYLES SC instructed by

Bowman Gilfillan Inc

For the First Respondent

J DANIELS instructed by

Frese Moll & Partners

Date of hearing: 26 February 2018

Date of judgement: 19 March 2018

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Vidavsky v Body Corporate of Sunhill Villas 2005 (5) SA 200 (SCA)

Case cited

Kauesa v Minister of Home Affairs and Others 1996 (4) SA 965 and 973

Case cited

Johannesburg City Council v Bruma Thirty-Two (Pty) Limited 1984 (4) SA 87 (T)

Case cited

Cool Ideas 1186 CC v Hubbard and Another 2014 (4) SA 474 (CC)

Case cited

Companies Act 71 of 2008

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.