Steve Tshwete Local Municipality v Steve Tshwete Housing Association (A13 / 2021) [2021] ZAMPMHC 27 (6 October 2021)

Steve Tshwete Local Municipality v Steve Tshwete Housing Association (A13 / 2021) [2021] ZAMPMHC 27 (6 October 2021)

The court held that the contract between the parties stipulated that the respondent was obliged to erect and complete a building within 24 months from the date of sale, which was defined as the date of signature by the last party in February 2012. The respondent failed to comply with this obligation and did not seek...

Source-derived case information.

Citation
[2021] ZAMPMHC 27
Parties
Appellant: Steve Tshwete Local Municipality; Respondent: Steve Tshwete Housing Association
Court
Middelburg High Court, Mpumalanga
Jurisdiction
South Africa
Case Number
A13 / 2021
Procedural Posture
Civil Appeal / Appeal From High Court Judgment Ordering Specific Performance
Outcome
Appeal upheld; order of the court below set aside; application for specific performance dismissed with costs.
Judges
TV Ratshibvumo, SS Mphahlele, MT Mankge
Legal Topics
Specific Performance, Contractual Time Limits, Sale of Land, Alienation of Land Act, Interpretation of Contracts
Land and Property Civil Procedure Commercial and Corporate Specific Performance Contractual Time Limits Sale of Land Alienation of Land Act Interpretation of Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Steve Tshwete Local Municipality

Appellant

Steve Tshwete Housing Association

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Judgment Ordering Specific Performance

  1. 1 Whether the respondent complied with its contractual obligations under the sale agreement.
  2. 2 Whether time was of the essence in the contract for purposes of performance and cancellation.
  3. 3 Whether the respondent was entitled to specific performance given the lapse of time and non-performance.

Ratio Decidendi

The court held that the contract between the parties stipulated that the respondent was obliged to erect and complete a building within 24 months from the date of sale, which was defined as the date of signature by the last party in February 2012. The respondent failed to comply with this obligation and did not seek an extension as provided for in the contract. The contract therefore lapsed in February 2014. The appellant was under no obligation to give notice to the respondent, as time was of the essence and the contract provided for automatic lapse. The respondent's reliance on section 19 of the Alienation of Land Act was misplaced, as the contract had lapsed due to passage of time, not...

Court Disposition

Appeal upheld; order of the court below set aside; application for specific performance dismissed with costs.

Orders

  • The appeal is upheld with costs, including costs of two counsel.
  • The order of the court below is set aside and replaced with: 'Application is dismissed with costs.'