Strijdom Park Extension 6 (Pty) Ltd. v Abcon (Pty) Ltd. (662/95) [1998] ZASCA 57; 1998 (4) SA 844 (SCA); [1998] 4 All SA 117 (A) (28 August 1998)
The Supreme Court of Appeal found that the respondent breached the building contract by failing to construct the slab in a proper and workmanlike manner, specifically by not assembling the reinforcement mats according to accepted construction practice. The evidence established that the collapse of the slab was due to the contractor's failure, not defective engineering design. The contractual exclusion of liability under clause 13 did not apply because the defect did not appear within the patent defects liability period and was not discoverable by reasonable examination at that time. The onus to prove that a reasonable examination would have disclosed the defect rested on the respondent,...
- Citation
- [1998] ZASCA 57
- Parties
- Appellant: Strijdom Park Extension 6 (Pty) Ltd.; Respondent: Abcon (Pty) Ltd.
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 28 August 1998
- Case Number
- 662/95
- Procedural Posture
- Civil Appeal / Appeal From Trial Court Judgment
- Outcome
- Appeal upheld. Respondent held liable for damages and costs.
- Judges
- Howie, Hefer, Zulman
- Legal Topics
- Building Contracts, Breach of Contract, Contractual Exclusion of Liability, Onus of Proof, Damages for Defective Work
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Strijdom Park Extension 6 (Pty) Ltd.
Appellant
Abcon (Pty) Ltd.
Respondent
Procedural Posture
Civil Appeal / Appeal From Trial Court Judgment
Legal Issues
- 1 Whether the respondent breached the building contract by failing to construct the slab in a proper and workmanlike manner.
- 2 Whether the collapse of the slab was attributable to defective engineering design or solely to the contractor's workmanship.
- 3 Whether the contractor could rely on the contractual exclusion of liability under clause 13 for defects not listed within the patent defects liability period.
Ratio Decidendi
The Supreme Court of Appeal found that the respondent breached the building contract by failing to construct the slab in a proper and workmanlike manner, specifically by not assembling the reinforcement mats according to accepted construction practice. The evidence established that the collapse of the slab was due to the contractor's failure, not defective engineering design. The contractual exclusion of liability under clause 13 did not apply because the defect did not appear within the patent defects liability period and was not discoverable by reasonable examination at that time. The onus to prove that a reasonable examination would have disclosed the defect rested on the respondent,...
Court Disposition
Appeal upheld. Respondent held liable for damages and costs.
Orders
- The appeal succeeds, with costs, including the costs of two counsel.
- The order of the Court a quo is set aside and substituted with: 'The claim succeeds. Defendant is ordered to pay plaintiff R585 928,86 as damages, the qualifying fees of specified experts, and costs of suit including the costs of two counsel.'
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment