Sussman v Nedbank Ltd (30501/2020) [2023] ZAGPJHC 240 (15 March 2023)
The court found that Nedbank's delay in filing the summary judgment application was minor and satisfactorily explained. No material prejudice was suffered by Ms Sussman, and Nedbank discharged its onus to obtain condonation. The Rule 30 application to strike out was dismissed as the condonation was granted. Furthermore, Nedbank established a prima facie right and satisfied the requirements for interim interdict relief, justifying the order for the Sheriff to take possession of the motor vehicle pending finalization of the main dispute.
- Citation
- [2023] ZAGPJHC 240
- Parties
- Applicant: Roslyn Sussman; Respondent: Nedbank Ltd; Plaintiff: Nedbank Ltd; Defendant: Roslyn Sussman
- Court
- South Gauteng High Court, Johannesburg
- Jurisdiction
- South Africa
- Judgment Date
- 15 March 2023
- Case Number
- 30501/2020
- Procedural Posture
- Civil Application / Application for Condonation and Interim Interdict; Rule 30 Strike Out
- Outcome
- Condonation for late delivery of the summary judgment application is granted. The Rule 30 application to strike out is dismissed. Interim interdict relief is granted in favour of Nedbank.
- Judges
- Turner
- Legal Topics
- Condonation of Late Filing, Summary Judgment, Interim Interdict, Rule 30 Strike Out
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Roslyn Sussman
Applicant
Nedbank Ltd
Respondent
Nedbank Ltd
Plaintiff
Roslyn Sussman
Defendant
Procedural Posture
Civil Application / Application for Condonation and Interim Interdict; Rule 30 Strike Out
Legal Issues
- 1 Whether condonation should be granted for the late delivery of the summary judgment application.
- 2 Whether the Rule 30 application to strike out Nedbank's summary judgment application should be upheld.
- 3 Whether Nedbank is entitled to interim interdict relief pending finalization of the main dispute.
Ratio Decidendi
The court found that Nedbank's delay in filing the summary judgment application was minor and satisfactorily explained. No material prejudice was suffered by Ms Sussman, and Nedbank discharged its onus to obtain condonation. The Rule 30 application to strike out was dismissed as the condonation was granted. Furthermore, Nedbank established a prima facie right and satisfied the requirements for interim interdict relief, justifying the order for the Sheriff to take possession of the motor vehicle pending finalization of the main dispute.
Court Disposition
Condonation for late delivery of the summary judgment application is granted. The Rule 30 application to strike out is dismissed. Interim interdict relief is granted in favour of Nedbank.
Orders
- The late delivery and non-compliance with Rule 6 in the service of the application for summary judgment is condoned.
- Pending finalization of the dispute, the defendant is directed to deliver the specified motor vehicle into the possession of the Sheriff.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment