Sutherland v Drake Flemmer & Orsmond Incorporated and Another (1576/2015) [2015] ZAECPEHC 65 (24 November 2015)

Sutherland v Drake Flemmer & Orsmond Incorporated and Another (1576/2015) [2015] ZAECPEHC 65 (24 November 2015)

The court held that while damages for breach of contract are generally assessed as at the date of breach, this is not a rigid rule. In cases of professional negligence by attorneys, especially where the breach involves failure to pursue claims for prospective losses, it is necessary and fair to admit evidence...

Source-derived case information.

Citation
[2015] ZAECPEHC 65
Parties
Plaintiff: William Arnold Wentworth-Rex Sutherland; Defendant: Drake Flemmer & Orsmond Incorporated; Defendant: Le Roux Incorporated
Court
Eastern Cape High Court, Port Elizabeth
Jurisdiction
South Africa
Case Number
1576/2015
Procedural Posture
Civil Trial / Point in Limine on Admissibility of Post Breach Evidence
Outcome
Defendants' point in limine dismissed with costs.
Judges
E Revelas
Legal Topics
Professional Negligence, Breach of Mandate, Quantification of Damages, Assessment of Evidence, Under Settlement, Loss of Earnings
Civil Procedure Delict Commercial and Corporate Professional Negligence Breach of Mandate Quantification of Damages Assessment of Evidence Under Settlement +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

William Arnold Wentworth-Rex Sutherland

Plaintiff

Drake Flemmer & Orsmond Incorporated

Defendant

Le Roux Incorporated

Defendant

Procedural Posture

Civil Trial / Point in Limine on Admissibility of Post Breach Evidence

  1. 1 Whether damages in a professional negligence claim against attorneys must be assessed only as at the date of breach.
  2. 2 Whether evidence obtained after the date of breach is admissible for quantification of damages.
  3. 3 Whether the plaintiff is entitled to lead expert evidence obtained post-settlement to establish quantum.

Ratio Decidendi

The court held that while damages for breach of contract are generally assessed as at the date of breach, this is not a rigid rule. In cases of professional negligence by attorneys, especially where the breach involves failure to pursue claims for prospective losses, it is necessary and fair to admit evidence obtained after the date of breach to properly quantify damages. Restricting admissible evidence to that available at the date of breach would prevent the plaintiff from being placed in the position he would have occupied had the contract been properly performed. The authorities cited support a pragmatic approach, allowing post-breach evidence where it facilitates accurate...

Court Disposition

Defendants' point in limine dismissed with costs.

Orders

  • The defendants' point in limine is dismissed.
  • The defendants are ordered to pay the costs of the point in limine.