The applicant failed to provide sufficient factual averments to substantiate the damages claimed for breach of contract. The calculation of the claimed amount was unclear and unsupported by evidence in the founding affidavit. The applicant did not clarify the legal basis for claiming the value of missing items, nor...

Source-derived case information.

Citation
[2014] ZAECPEHC 27
Parties
Applicant: Teddybear Consulting Trust T/A Blue Bay Food Stop; Respondent: Ronelle Lauren Deysel; Respondent: Steers Cleary Park
Court
Eastern Cape High Court, Port Elizabeth
Jurisdiction
South Africa
Case Number
P343/13
Procedural Posture
Contractual Damages Application / Final Judgment
Outcome
Application dismissed for failure to prove damages claim based on breach of contract.
Judges
R G Lagrange
Legal Topics
Breach of Employment Contract, Notice Pay, Damages Assessment, Restraint of Trade, Proof of Loss
Labour Law Civil Procedure Breach of Employment Contract Notice Pay Damages Assessment Restraint of Trade Proof of Loss

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Teddybear Consulting Trust T/A Blue Bay Food Stop

Applicant

Ronelle Lauren Deysel

Respondent

Steers Cleary Park

Respondent

Procedural Posture

Contractual Damages Application / Final Judgment

  1. 1 Whether the applicant proved damages for breach of contract by the first respondent.
  2. 2 Whether the applicant is entitled to recover the value of missing items allegedly retained by the first respondent.
  3. 3 Whether the calculation of damages claimed is supported by sufficient factual averments.

Ratio Decidendi

The applicant failed to provide sufficient factual averments to substantiate the damages claimed for breach of contract. The calculation of the claimed amount was unclear and unsupported by evidence in the founding affidavit. The applicant did not clarify the legal basis for claiming the value of missing items, nor did it provide supporting documentation. The court is not required to speculate on the calculation of damages or the legal entitlement to the value of items allegedly retained. Accordingly, the applicant did not discharge the onus of proof required for contractual damages.

Court Disposition

Application dismissed for failure to prove damages claim based on breach of contract.

Orders

  • The application is dismissed.
  • No order as to costs.