Download PDF

South Africa Judgment

Eastern Cape High Court, Makhanda

Tekoa Consulting Engineers (Pty) Ltd v Alfred Nzo District Municipality and Others (1284/2021) [2022] ZAECMKHC 59 (6 September 2022)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the tender process was unlawful due to the improper application of the preference point system and that the applicant's disqualification was not justified. The specifications did not clearly require CIDB registration as a mandatory condition, and the applicant's bid was therefore acceptable. The review proceedings were instituted within the prescribed period, and the grounds for leave to appeal did not raise any reasonable prospects of success. The court stood by its previous findings and relief granted, dismissing the application for leave to appeal and awarding costs against the respondents.

Court disposition

Application for leave to appeal dismissed; costs awarded against respondents jointly and severally.

Orders

  • The application for leave to appeal is dismissed.
  • The respondents are liable for the costs of the application, jointly and severally.

02

Material facts

Parties

Tekoa Consulting Engineers (Pty) Ltd

Applicant Counsel: Adv Nyangiwe

Alfred Nzo District Municipality

Respondent Counsel: Adv Bodlani SC

The Municipal Manager: Alfred Nzo District Municipality

Respondent Counsel: Adv Bodlani SC

Zinzame Consulting Engineers / Cycle Projects / Ubuntu Bam JV

Respondent Counsel: Adv Tshikila

Emlanjeni JV

Respondent Counsel: Adv Tshikila

Olon Consulting Engineers JV IPM Plant Hire

Respondent Counsel: Adv Tshikila

BM Infrastructure JV Magnacorp

Respondent Counsel: Adv Tshikila

03

Procedural history

  1. Posture

    Leave to Appeal / Application for Leave to Appeal Following Judgment on Tender Review

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that the tender process was unlawful, that its disqualification was not justified, and that the specifications did not clearly require CIDB registration as a mandatory condition. The applicant maintained that it acted within the prescribed timeframes and that the award to the third to sixth respondents should be set aside.
Respondent
The respondents contended that the court erred by addressing the formulation of the tender, that the applicant delayed unreasonably in bringing the review, and that the lack of CIDB registration rendered the applicant's bid unacceptable. They argued that the applicant was not entitled to relief and that the tender award should stand.

05

Court’s reasoning

  1. 01

    Promotion of Administrative Justice Act 3 of 2000 (PAJA)

    A tender process must comply with the requirements of lawfulness, fairness, and transparency under administrative law.

  2. 02

    Section 7(1), PAJA

    Review proceedings must be instituted within 180 days from the date the applicant became aware of the decision and reasons therefor.

  3. 03

    Preferential Procurement Policy Framework Act 5 of 2000 (PPPFA)

    An acceptable tender is defined by the Preferential Procurement Policy Framework Act and must meet the specifications and conditions set out in the tender documents.

  4. 04

    Construction Industry Development Board Act 38 of 2000

    Proof of CIDB registration is only mandatory if clearly and unambiguously required by the tender specifications.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the tender process was unlawful due to the improper application of the preference point system and that the applicant's disqualification was not justified. The specifications did not clearly require CIDB registration as a mandatory condition, and the applicant's bid was therefore acceptable. The review proceedings were instituted within the prescribed period, and the grounds for leave to appeal did not raise any reasonable prospects of success. The court stood by its previous findings and relief granted, dismissing the application for leave to appeal and awarding costs against the respondents.

Obiter and limits

  • The distinction between functionality and responsiveness in tender evaluation is critical and must not be conflated.
  • The broad nature of goods and services required for the project did not preclude the applicant from submitting a bid.

Court disposition

Application for leave to appeal dismissed; costs awarded against respondents jointly and severally.

  • The application for leave to appeal is dismissed.
  • The respondents are liable for the costs of the application, jointly and severally.

Source and reliance status

Eastern Cape High Court, Makhanda

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Eastern Cape High Court, Makhanda

Judgment

[2022] ZAECMKHC 59

IN

THE HIGH COURT OF SOUTH AFRICA

EASTERN CAPE DIVISION, MAKHANDA

CASE NO. 1284/2021

In the matter between:

TEKOA CONSULTING ENGINEERS (PTY LTD

Applicant

and

ALFRED

NZO DISTRICT MUNICIPALITY

First Respondent

THE MUNICIPAL MANAGER:

ALFRED

NZO DISTRICT MUNICIPALITY

Second Respondent

ZINZAME CONSULTING ENGINEERS / CYCLE

PROJECTS / UBUNTU BAM JV

Third Respondent

EMLANJENI JV

Fourth Respondent

OLON

CONSULTING ENGINEERS JV

IPM

PLANT

HIRE

Fifth Respondent

BM

INFRASTRUCTURE JV MAGNACORP

Sixth Respondent

JUDGMENT

LAING J

[1] This is an application for leave to appeal against the judgment handed down in relation to the award of a tender for the appointment of a panel of service providers for the planning, design and construction of Water Services Infrastructure Grant (‘WSIG’) funded projects for the Alfred Nzo District Municipality. The parties will be referred to in the same manner as their citation in the main application.

[2] The applicant had sought an order that, inter alia, reviewed and set aside the decision to refuse to appoint it to the panel. It had also sought alternative relief that the decision to appoint the third to sixth respondents be reviewed and set aside and that the decision be referred back to the Bid Evaluation Committee (‘BEC’) and the Bid Adjudication Committee (‘BAC’) for reconsideration.

[3] In its judgment, this court ordered, inter alia, that: the tender process be declared unlawful; the first respondent’s decision to disqualify the applicant’s bid be reviewed, declared unlawful, and set aside; and the second respondent’s decision to award the tender to the third, fourth, fifth and sixth respondents be reviewed, declared unlawful, and set aside.

[4] The first and second respondents’ grounds for application for leave to appeal were to the effect that the court erred in deciding the issue pertaining to the formulation of the tender because no relief was sought by the applicant in that regard. Consequently, the court ought to have found that there had indeed been unreasonable delay on the part of the applicant. Finally, the court ought to have found that the applicant’s failure to have submitted proof of registration with the Construction Industry Development Board (‘CIDB’) meant that its bid did not satisfy the definition of an acceptable tender.

[5] The third, fourth, fifth and sixth respondents’ grounds were, in essence, the same as those raised by the first and second respondents.

[6] The court is of the view that the findings made with regard to the lawfulness of the tender process did not amount to findings on any decision with regard to the actual formulation of the tender itself. That decision was a separate matter entirely and did not form the subject of these review proceedings. Instead, the manner in which the first respondent applied the preference point system

gave rise to one or more of the grounds of review listed under section 6(2) of the Promotion of Administrative Justice Act 3 of 2000 (‘PAJA’) and determined, ultimately, the legality of the tender process itself. This in turn led to the finding that the decision to award the tender to the third, fourth, fifth and sixth respondents was indeed unlawful, as contended by the applicant.

[7] The question of unreasonable delay must be confined to the time period applicable to the institution of review proceedings in relation to the decision to award the tender to the third, fourth, fifth and sixth respondents. The decision with regard to the actual formulation of the tender itself was not the subject of the applicant’s challenge. The 180-day period contemplated under section 7(1) of PAJA only began from the date upon which the applicant had been informed or had become aware of the decision to award the tender and the reasons therefor or upon which it might reasonably have been expected to have acquired such knowledge. The court found that the applicant was within the applicable time period.

[8] The specifications and conditions of the tender did not indicate, clearly and unambiguously, that the submission of proof of registration with the CIDB was a mandatory requirement. Any suggestion to that effect was vague at best. Consequently, the applicant’s failure to have done so did not mean that it had failed to submit an acceptable tender, as defined in terms of section 1 of the Preferential Procurement Policy Framework Act 5 of 2000 (‘PPPFA’).

[9] The respondents’ argument that the provisions of the Construction Industry Development Board Act 38 of 2000 (the CIDB Act’) prevented the applicant from participating in the tender ignores the broad nature of the goods and services required for the project in question. There was nothing to have prevented the applicant from having submitted a bid. Whether it was permitted to supply or whether it was capable of providing the goods and services required was an aspect of the functionality of its bid, not its responsiveness to the specifications and conditions of the tender. The respondents have incorrectly conflated the two concepts.

[10] Overall, the court has considered the grounds of appeal and the submissions made by the parties in terms of their heads of argument and at the hearing itself. Having taken the above into account, including the test for leave to appeal as summarised by counsel for the respondents, the court respectfully stands by the findings made and the relief granted.

[11] In the circumstances, the following order is made:

(a) the application for leave to appeal is dismissed; and

(b) the respondents are liable for the costs of the application, jointly and severally.

JGA

LAING

JUDGE

OF THE HIGH COURT

APPEARANCE

Counsel for the applicant:

Adv Nyangiwe, instructed by Moletsane PN Attorneys Inc, East London.

Counsel for the 1st and 2nd respondents: Adv Bodlani SC, instructed by Funani Attorneys, Mthatha.

Counsel for the 3rd to 6th respondents: Adv Tshikila, instructed by Gilindoda Attorneys, Makhanda.

Date of hearing:

31 August 2022

Date of delivery of judgment:

06 September 2022

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Promotion of Administrative Justice Act 3 of 2000

Legislation

Legislation referenced in the available case record.

Preferential Procurement Policy Framework Act 5 of 2000

Legislation

Legislation referenced in the available case record.

Construction Industry Development Board Act 38 of 2000

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.