Telkom SA Ltd v ZTE Mzanzi (Pty) Ltd and Others (383/12) [2013] ZASCA 14 (18 March 2013)
The Supreme Court of Appeal held that the dispute resolution clause incorporated into the RFP did not create a contractual obligation for Telkom to resolve disputes with bidders prior to contract formation. The clause only becomes operative once a contract is concluded with a successful bidder. To interpret the clause otherwise would be unbusinesslike and lead to absurd consequences, such as obliging Telkom to arbitrate with multiple bidders before awarding the tender. The court found that the interim interdict granted by the court below was inappropriate, as the relief sought was in fact final for the period specified and should have been assessed under the rules for final relief. The...
- Citation
- [2013] ZASCA 14
- Parties
- Appellant: Telkom SA Limited; Respondent: ZTE Mzanzi (Pty) Ltd; Respondent: Huawei Technologies Africa (Pty) Ltd; Respondent: Alcatel-Lucent (Pty) Limited
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 18 March 2013
- Case Number
- 383/12
- Procedural Posture
- Civil Appeal / Appeal From North Gauteng High Court, Pretoria
- Outcome
- Appeal upheld; order of the court below set aside and substituted with an order dismissing the application with costs, including the costs of two counsel.
- Judges
- Nugent, Leach, Petse, Schoeman, Saldulker
- Legal Topics
- Tender Process, Contractual Relationship, Dispute Resolution Clause, Interpretation of Contract, Interdict, Arbitration
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Telkom SA Limited
Appellant
ZTE Mzanzi (Pty) Ltd
Respondent
Huawei Technologies Africa (Pty) Ltd
Respondent
Alcatel-Lucent (Pty) Limited
Respondent
Procedural Posture
Civil Appeal / Appeal From North Gauteng High Court, Pretoria
Legal Issues
- 1 Whether the dispute resolution clause in the RFP created a contractual obligation for Telkom to resolve disputes with bidders prior to contract formation.
- 2 Whether the interim interdict granted by the court below was appropriate given the nature of the relief sought.
- 3 How the relevant clauses in the RFP and Standard Terms and Conditions should be interpreted.
Ratio Decidendi
The Supreme Court of Appeal held that the dispute resolution clause incorporated into the RFP did not create a contractual obligation for Telkom to resolve disputes with bidders prior to contract formation. The clause only becomes operative once a contract is concluded with a successful bidder. To interpret the clause otherwise would be unbusinesslike and lead to absurd consequences, such as obliging Telkom to arbitrate with multiple bidders before awarding the tender. The court found that the interim interdict granted by the court below was inappropriate, as the relief sought was in fact final for the period specified and should have been assessed under the rules for final relief. The...
Court Disposition
Appeal upheld; order of the court below set aside and substituted with an order dismissing the application with costs, including the costs of two counsel.
Orders
- The appeal is upheld with costs.
- The order of the court below is set aside.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment