Thabula Trade and Invest 3 (Pty) Ltd v Ruwacon (Pty) Ltd and Others (866/2016) [2016] ZAFSHC 76 (2 June 2016)

Thabula Trade and Invest 3 (Pty) Ltd v Ruwacon (Pty) Ltd and Others (866/2016) [2016] ZAFSHC 76 (2 June 2016)

The court found that the dispute resolution clause in the subcontracts was permissive, not mandatory, and did not preclude the applicant from seeking relief in court. The retention clauses in both subcontracts were interpreted to mean that retention monies became payable upon final completion as certified by the...

Source-derived case information.

Citation
[2016] ZAFSHC 76
Parties
Applicant: Thabula Trade & Invest 3 (Pty) Ltd; Respondent: Ruwacon (Pty) Ltd; Respondent: MEC: Free State Provincial Government Department of Human Settlements
Court
Free State High Court, Bloemfontein
Jurisdiction
South Africa
Case Number
866/2016
Procedural Posture
Civil Application / Final Judgment
Outcome
Application granted in favour of the applicant.
Judges
P. Zietsman
Legal Topics
Retention Money, Construction Contracts, Contractual Interpretation, Interest on Debt, Dispute Resolution Clause
Commercial and Corporate Civil Procedure Retention Money Construction Contracts Contractual Interpretation Interest on Debt Dispute Resolution Clause

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Thabula Trade & Invest 3 (Pty) Ltd

Applicant

Ruwacon (Pty) Ltd

Respondent

MEC: Free State Provincial Government Department of Human Settlements

Respondent

Procedural Posture

Civil Application / Final Judgment

  1. 1 Whether the applicant is entitled to payment of retention monies withheld under two subcontracts.
  2. 2 Whether the dispute resolution clause in the subcontracts precludes direct court proceedings.
  3. 3 How the retention clause in the subcontracts should be interpreted regarding the timing and conditions for payment.

Ratio Decidendi

The court found that the dispute resolution clause in the subcontracts was permissive, not mandatory, and did not preclude the applicant from seeking relief in court. The retention clauses in both subcontracts were interpreted to mean that retention monies became payable upon final completion as certified by the engineer, and not subject to a further defects liability period or contingent on the main contractor first receiving payment from the employer. The court accepted the close-out reports from the engineer as certification of final completion and satisfaction with the retention work. The application was not premature as the amounts claimed excluded retention sums not yet due. The...

Court Disposition

Application granted in favour of the applicant.

Orders

  • The first respondent is ordered to pay the applicant the amount of R1 085 655.07.
  • The first respondent is ordered to pay interest on the aforesaid amount at 9.5% per year a tempore morae as follows: on the Hobhouse project from 5 November 2015 until date of payment; on the Ladybrand project from 27 December 2015 until date of payment.