Thermaine Invetments (Pty) Ltd t/a Improvair v Pareto Ltd and Others (5449/2011) [2011] ZAWCHC 99 (28 April 2011)

Thermaine Invetments (Pty) Ltd t/a Improvair v Pareto Ltd and Others (5449/2011) [2011] ZAWCHC 99 (28 April 2011)

The court found that the applicant failed to establish a prima facie right to the interim interdict sought. The procurement policy and tender specifications did not impose a peremptory requirement for a B-BBEE certificate from a SANAS accredited agency, and deviations were permissible. The applicant's right was...

Source-derived case information.

Citation
[2011] ZAWCHC 99
Parties
Applicant: Therm Aire Investments (Pty) Ltd t/a Improvair; Respondent: Pareto Limited; Respondent: Metropolitan Life Limited; Respondent: Triocon Consulting Engineers (Pty) Limited; Respondent: WBHO Construction (Pty) Limited; Respondent: Two Oceans Air Conditioning (Pty) Limited
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
5449/2011
Procedural Posture
Urgent Application / Application for Urgent Interim Interdict Pending Final Relief
Outcome
Application dismissed with costs.
Judges
Dlodlo
Legal Topics
Tender Process, Interim Interdict, Contractual Rights, B Bbee Certificate, Procurement Policy
Commercial and Corporate Civil Procedure Tender Process Interim Interdict Contractual Rights B Bbee Certificate Procurement Policy

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 29 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Therm Aire Investments (Pty) Ltd t/a Improvair

Applicant

Pareto Limited

Respondent

Metropolitan Life Limited

Respondent

Triocon Consulting Engineers (Pty) Limited

Respondent

WBHO Construction (Pty) Limited

Respondent

Two Oceans Air Conditioning (Pty) Limited

Respondent

Procedural Posture

Urgent Application / Application for Urgent Interim Interdict Pending Final Relief

  1. 1 Whether the applicant is entitled to urgent interim interdict restraining respondents from concluding or implementing the HVAC contract pending final relief.
  2. 2 Whether the tender process required a B-BBEE certificate from a SANAS accredited agency as a peremptory requirement.
  3. 3 Whether the applicant has a contractual right to have its tender adjudicated strictly in accordance with the bid invitation and procurement policy.

Ratio Decidendi

The court found that the applicant failed to establish a prima facie right to the interim interdict sought. The procurement policy and tender specifications did not impose a peremptory requirement for a B-BBEE certificate from a SANAS accredited agency, and deviations were permissible. The applicant's right was limited to having its tender opened and considered, which occurred. The contract between the joint venture and Two Oceans had already been concluded, rendering the relief sought moot. The applicant could pursue damages if a breach occurred, and interdictory relief was inappropriate where damages would suffice. The court dismissed the application and ordered the applicant to pay the...

Court Disposition

Application dismissed with costs.

Orders

  • The application is dismissed.
  • The applicant shall pay the costs of the first, second, and third respondents, including the costs occasioned by the employment of two counsel.