Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Thungela Operations (Pty) v Ltd Xakwa Coal (Pty) Ltd and Others (24010/2022) [2022] ZAGPPHC 889 (18 November 2022)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the applicant acted reasonably in launching and maintaining the application, given the ongoing discharge of mine-impacted water and the absence of regulatory intervention at the time. The subsequent issuance of a directive by the Department of Water and Sanitation rendered the relief sought unnecessary, justifying withdrawal. Section 32(2) of NEMA applies, as the applicant acted in the public interest and sought enforcement of statutory duties. The court exercised its discretion to order that each party pay its own costs, considering that no final determination was made on the disputed facts and neither party pursued further relief. The applicant should not be penalized with costs for acting to protect the environment and public interest, nor should it be rewarded with costs absent a final determination.

Court disposition

Application withdrawn; each party to pay its own costs.

Orders

  • The applicant and the fourth respondent shall each pay its own costs.

02

Material facts

Parties

Thungela Operations (Pty) Ltd

Applicant Counsel: B L Manentsa

Xakwa Coal (Pty) Ltd

Respondent

Wealthage House of Capital Pty Ltd

Respondent

Bentech Mining (Pty) Ltd

Respondent

Thabo Machete

Respondent Counsel: R Andrews

Minister of Water and Sanitation

Respondent

Minister of Mineral Resources and Energy

Respondent

03

Procedural history

  1. Posture

    Urgent Application / Costs Determination Following Withdrawal of Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that it was justified in launching and maintaining the application until the Department of Water and Sanitation issued a directive under the National Water Act, which rendered further court relief unnecessary. The applicant maintained that it acted reasonably and in the public interest, seeking enforcement of statutory duties under NEMA and NWA. It contended that the DWS is the proper authority to compel compliance and that, following the directive, it was appropriate to withdraw the application without an adverse costs order.
Respondent
The fourth respondent argued that the applicant should bear the costs of the withdrawn application, asserting that the applicant conceded the water in question emanated from its property and that the application was unnecessary. The respondent relied on expert hydrological evidence and contended that the applicant failed to prove entitlement to relief. The respondent also argued that, absent a final determination, the applicant should be treated as the unsuccessful party for costs purposes.

05

Court’s reasoning

  1. 01

    Germishuys v Douglas Besproeiingsroad 1973 (3) SA 299 (NC)

    The general rule is that a party withdrawing its application is liable for costs as an unsuccessful litigant, unless exceptional circumstances justify a departure.

  2. 02

    Reuben Rosenblum Family Investments (Pty) Ltd and Another v Marsuban (Pty) Ltd 2003 (3) SA 547 (C)

    Courts retain a discretion to deprive the successful party of costs, especially where the applicant acted reasonably and circumstances changed after proceedings commenced.

  3. 03

    Section 32(2) of National Environmental Management Act 107 of 1998

    Section 32(2) of NEMA allows a court not to award costs against a party acting reasonably out of concern for the public interest or environmental protection, even if relief is not obtained.

  4. 04

    Section 28 of National Environmental Management Act 107 of 1998

    The duty of care under section 28 of NEMA obliges landowners to prevent pollution or environmental degradation, regardless of the source of the water.

  5. 05

    Silvermine Valley Coalition v Sybrand van der Spuy Boerderye and Others 2002 (1) SA 478 (CC)

    A court's discretion on costs is unfettered where statutory conditions are met, freeing it from ordinary principles.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the applicant acted reasonably in launching and maintaining the application, given the ongoing discharge of mine-impacted water and the absence of regulatory intervention at the time. The subsequent issuance of a directive by the Department of Water and Sanitation rendered the relief sought unnecessary, justifying withdrawal. Section 32(2) of NEMA applies, as the applicant acted in the public interest and sought enforcement of statutory duties. The court exercised its discretion to order that each party pay its own costs, considering that no final determination was made on the disputed facts and neither party pursued further relief. The applicant should not be penalized with costs for acting to protect the environment and public interest, nor should it be rewarded with costs absent a final determination.

Obiter and limits

  • The court noted that the factual disputes regarding the source and direction of water flow could not be resolved without oral evidence, and thus no final determination was made.
  • The court observed that the principles in Wildlife & Environmental Society of SA v MEC for Economic Affairs, Environment & Tourism, Eastern Cape and Others regarding costs in environmental litigation apply to the present matter.
  • The court remarked that neither party should bear the costs of the other's experts, given the absence of a final determination on their opinions.

Court disposition

Application withdrawn; each party to pay its own costs.

  • The applicant and the fourth respondent shall each pay its own costs.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2022] ZAGPPHC 889

HIGH

COURT OF SOUTH AFRICA

(GAUTENG DIVISION, PRETORIA)

CASE NO: 24010/2022

(1) REPORTABLE: NO

(2) OF INTEREST TO OTHER JUDGES: NO

(3)

REVISED

DATE: 18 NOVEMBER 2022

In the matter between:

THUNGELA OPERATIONS (PTY) LTD Applicant

and

XAKWA COAL (PTY) LTD First Respondent

WEALTHAGE HOUSE OF CAPITAL PTY LTD Second

Respondent

BENTECH MINING (PTY) LTD Third Respondent

THABO MACHETE Fourth Respondent

MINISTER OF WATER AND SANITATION Fifth Respondent

MINISTER OF MINERAL RESOURCES AND ENERGY Sixth Respondent

Summary: Withdrawal of application – despite this each party to pay its own costs – applicant justified in having pursued relief until a directive in terms of the National Water Act has been issued.

ORDER

The applicant and the fourth respondent shall each pay its own costs.

J

U D G M E N T

This matter has been heard in open court and is otherwise disposed of in terms of the Directives of the Judge President of this Division. The judgment and order are accordingly published and distributed electronically.

DAVIS, J

Introduction

[1] On 17 May 2022 Fourie J delivered a judgment in respect of the initial hearing of this matter. At the conclusion of the judgment, the applicant’s application against two erstwhile holders of mining permits on the property adjacent to that of the applicant was dismissed. At the same time, interim interdicts were granted against two other respondents, being another mining company and the neighbouring landowner, the fourth respondent, on an unopposed basis. The fourth respondent subsequently entered the fray and opposed the granting of the final interdict. Before the matter could be heard on an extended return day, the Department of Water and Sanitation (DWS) had issued a directive against the fourth respondent in terms of sections 19(3) and 53(1) of the National Water

Act 36 of 1998 (NWA). The applicant, being of the view that this intervention obviated the need for a final court order, subsequently

withdrew its application. In the final instance, the matter then proceeded in respect of the issue of costs only.

The principles pertaining to costs when a matter is withdrawn

[2] The general principle is that a party withdrawing an application launched by it becomes liable, as an unsuccessful litigant to pay the costs of the proceedings initiated by it[1].

[3] Following Germishuys, it has been held that

“… it is only in exceptional circumstances that a party that has been put to the expense of opposing withdrawn proceedings will not be entitled to all the costs caused thereby”[2].

[4] The court, however, retains a discretion to “deprive” the successful party, that is the party against whom the application was initially launched, of its costs[3].

[5] The above principles do not detract from or limit a court’s ordinary discretion[4].

[6] In exercising its discretion, which is to be exercised judicially, a court

“… should have due regard to the question whether, objectively viewed, the applicant [had] acted reasonably in launching the main proceedings

but was subsequently driven to withdraw it in order to save costs because facts emerging for the first time from, for instance, the respondent’s answering affidavit in the main proceedings or because the relief was no longer necessary or obtainable because of developments taking place after the launching of the main proceedings[5]”.

[7] The last-mentioned comment quoted above, was made by the learned authors of Erasmus with reference to Wildlife & Environmental Society of SA v MEC for Economic Affairs, Environment & Tourism, Eastern Cape and Others 2005 (6) SA 123 (ECD) (Wildlife). In that matter, the additional considerations were whether applicants who seek to enforce Constitutional rights, particularly for the sake of protection of the environment and who sought to obtain relief in the public interest, should be spared costs orders, should they withdraw their applications. These considerations also apply to the present matter.

Summary of background facts

[8] The adjacent properties in question are portions of the Farm Kromdraai 297 JS Emalahleni situated in Mpumalanga. The applicant’s properties have loosely been referred to as portions 10 and 11 and the fourth respondent’s property as portion 23.

[9] The history of the matter regarding these two sets of properties have been set out by Fourie J in his judgment and it is not necessary to repeat that here. What has, however, become clearer by way of papers delivered since his judgment, is that mine-impacted water is continually being discharged from a dam on the fourth respondent’s property into the environs thereof.

[10] Due principally to historical mining operations on the sets of adjacent properties, the underground mining pillars between the properties have either become compromised or may have been breached, resulting in inter-mine flow of mine impacted drainage.

[11] There is a dispute as to whether there is drainage or surface seepage of such water from the applicant’s properties to the fourth respondent’s property or not. The fact of the matter is however, that the applicant has taken steps to contain the discharge of mine-impacted water from its property and/or its mining operations while the fourth respondent’s attempts to

do the same, has fallen short, particularly in respect of the water flowing from dam 2 on the edge of the old Xakwa mine on its property. While measures taken by the fourth respondent appear to have been successful in respect of the remainder of its property, the discharge or overflow from the Xakwa dam continued virtually unabated.

A brief history of the litigation

[12] The applicant launched its application on an urgent basis, intending for it to be heard on 10 May 2022. In the end, it was heard on 12 and 13 May 2022. The relief sought was to interdict the respondents (which expressly included the fourth respondent) from “… discharging or permitting the discharge …” of mine-impacted water from the fourth respondent’s property onto adjacent properties, erosion trenches, the applicant’s

water holding and treatment facility or “causing … significant pollution and degradation and erosion of the environment …”. The applicant also sought an order directing the respondents to fulfil their duties of care contemplated in section 28 of the National Environmental Management Act 107 of 1998 (NEMA) and the NWA.

[13] The rule nisi issued by Fourie J on 17 May 2022, returnable on 14 July 2022, contained the relief as claimed by the applicant, as an interim order with immediate effect.

[14] Ten days later, on 24 May 2022 the DWS, whose Minister had been cited as the fifth respondent, issued a notice of intention to issue a directive in terms of sections 19(3) and 53(1) of the NWA, to the third and fourth respondents.

[15] On 28 June 2022 the fourth respondents made representations to the DWS in response to the aforesaid notice and thereafter delivered its answering affidavit in the present matter on 8 July 2022.

[16] On the initial return day of the rule nisi, the interim order was confirmed against the third respondent and the rule nisi was extended to 15 September 2022. The very next day the DWS conducted follow-up inspections on the fourth respondent’s property. Hereafter, on 8 August 2022 the fourth respondent delivered a supplementary answering affidavit.

[17] On 14 September 2022, being the day before the extended return day of the rule nisi, the DWS, under signature of the Provincial Head, Mpumalanga Provincial Operations, issued a directive in terms of the relevant sections of the NWA to the third and fourth respondents, requiring them to provide authorisations for their water use and to immediately stop any unlawful use upon failure

to provide such authorization and to:

“3. Provide a written corrective Plan of Action (PoA) in which you specify measures that will be employed by the mine to manage the pollution of Acid Mine Drainage emanating from the pits within fourteen (14) working days of the receipt of this directive.

4. Appoint a suitably registered professional to compile a rehabilitation plan for all the affected areas (pits, nearby water resources and the environment) within thirty (30) working days upon receipt of the directive which must be submitted to the Department for recommendation. The rehabilitation plan must entail amongst- others; the nature and extent of the impact that the water se activities have had or may have on the water resources and measures that will be implemented to remediate or mitigate the impacts with clear timeframes and descriptions of how and when each remedial/mitigation action will be implemented.

5. The rehabilitation plan must further indicate the cost estimated of the entire rehabilitation process; and

6. Implement all the recommendations contained in the rehabilitation plan and rehabilitate the areas affected by the water use activities within thirty (30) working days of the Departmental recommendation of the Rehabilitation Plan”.

[18] Subsequent to the above, the rule nisi was further extended to 7 November 2022, on which date the applicant did not persist with seeking confirmation of the rule nisi. This intention had been conveyed to the fourth respondent’s attorneys shortly before, resulting in a dispute about costs. The applicant’s position had been set out in heads of argument delivered on its behalf as follows:

“The effect of the DWS Directive is that it is no longer necessary to obtain a final interdict against the fourth respondent. In the notice of motion [the applicant] had sought the interim interdict against the respondents pending compliance in full with the DWS directives. It has taken the DWS four months to issue the Directive. But, in any event, [the applicant] had always recognized that the DWS is the proper authority that is empowered to compel the fourth respondent (and any persons responsible for the pollution) to take steps to ensure that the discharge of the mine-impacted water is stopped. It is now for the DWS to ensure that the fourth respondent complies with the Directives. For that reason the applicant no longer intends on pursuing the relief which it sought in this application against the fourth respondent”.

Evaluation

[19] The fourth respondent contended forcefully, both in its papers and by way of argument in court, that the influx of water into the Xakwa dam emanates from the applicant’s properties. It relied on the opinion of a hydrologist in this regard and the fact that it (and/or the third respondent) had stopped pumping water into dam 2 of the old Xakwa mine, yet the water levels continued to rise. It alleged that the applicant had conceded that the water in question emanated from its properties.

[20] Dealing with the last-mentioned contention first: on my reading of the papers, the applicant only conceded that there was inter-mine flow of water due to the boundary pillars of mining activities not having been observed or maintained. It however continued to deny the fourth respondent’s contentions. In fact, the applicant’s experts asserted that the lowest point in the underground mining activities (described as the seam floor) was on the applicant’s properties and that there “… is a depression from portion 23 [the fourth respondent’s property] into portion 11 [the applicant’s property]”. The seepage of groundwater and direction of the flow of sub-surface water is also disputed. The purported concession relied on by the fourth respondent is therefore either disputed or by no means unequivocal.

[21] In argument in court, much was also made by the applicant of the fact that the duties imposed on a landowner in terms of NEMA, obliged it to manage water on its property to prevent pollution or degradation, irrespective of the source of the water[6].

[22] I need not finally determine these issues as the applicant is no longer seeking relief against the fourth respondent and neither did the fourth respondent persist with a counter-application alluded to in its opposing papers. I therefore need not determine the factual issues regarding the source or origin of the water flow (which the fourth respondent in any event contends cannot be determined without oral evidence), I need only determine whether the launch of the application had been reasonable in the circumstances. The overflow of water from the “old Xakwa mine pit” (dam 2) had been common cause prior to the launch of the application and where it is apparent that this had not been contained, I find that the applicant had reasonable cause to launch the application. In the absence of action by the DWS to stop the discharge of such mine-impacted water, it was not unreasonable for the applicant to have kept the application “alive” even after delivery of the fourth respondent’s answering affidavit, from which contents the admission of the discharge appeared, albeit that it was coupled with a disputed accusation as to the cause thereof.

[23] In addition to the above, in Wildlife the court accepted the argument that a party relying on the enforcement of the duties imposed by NEMA, should not necessarily carry the burden of costs in the event of it being unsuccessful. Section 32(2) of NEMA provides as follows:

“A court may decide not to award cost against a person who, or group of persons which, fails to secure the relief sought in respect of any breach of threatened breach of any provision concerned with the protection of the environment or the use of natural resources if the court is of the opinion that the person or group of persons acted reasonably out of a concern for the public interest or in the interest of protecting the environment and had made due efforts to use other means reasonably available for obtaining the relief sought”.

[24] In seeking the enforcement of the duties imposed by section 28 of NEMA (in paragraphs 2.6 of its notice of motion) the applicant in this matter was entitled to rely on section 32(2) of NEMA. This section has further been held to “free the court from the fetter of ordinary principles, on the basis of compliance with certain conditions”[7].

[25] In these circumstances, not only do I find that the applicant has satisfied the abovementioned “conditions” but I find that the applicant should not be saddled with costs despite the fact that it became the “unsuccessful” party, once the events set in motion by the DWS overtook the need for a final interdict.

[26] Having made the above finding however, I am not of the view that it goes so far as to convert the applicant into a “successful” party, making it entitled to costs. To reach that point, a determination would have had to be made on the disputed facts or at least on the question of whether the applicant would have been entitled to a final interdict, an exercise which the applicant elected not to pursue. By the same token, the fourth respondent also did not pursue the claim for an “opposite” interdict referred to askance in its papers.

[27] Taking all this into consideration, in the exercise of the court’s discretion, I find that it would be equitable to order each party to pay its own costs. This would, it seems to me, be fair in the circumstances[8]. In reaching this conclusion, I have also taken into account that no final determination had or could be made in respect of the correctness of the opinions of opposing experts relied on by the parties and therefore neither party should be liable for the costs of the other party’s experts.

Order

[28] The following order is made:

N

DAVIS

Judge of the High Court

Gauteng Division, Pretoria

Date of Hearing: 7

November 2022

Judgment delivered: 18

November 2022

APPEARANCES:

For the Applicant: Adv

B L Manentsa

Attorney for the Applicant: Webber

Wentzel Attorneys, Johannesburg

c/o Hills Incorporated, Pretoria

For the Fourth Respondent: Adv

R Andrews

Attorney for the Fourth Respondent: Dhooge Law Inc, Benoni

c/o Legal Serve Serve Centre, Pretoria

[1] Germishuys v Douglas Besproeiingsroad 1973 (3) SA 299 (NC) (Germishuys).

[2] Reuben Rosenblum Family Investments (Pty) Ltd and Another V Marsuban (Pty) Ltd (Forward Enterprises (Pty) Ltd and Others intervening) 2003 (3) SA 547 (C) at 550C-D

[3] Waste Products Utilisation (Pty) Ltd v Wilkes (Biccari interested party) 2003 (2) SA 590 (W) at 597A.

[4] Erasmus v Grunow and Another 1980 (2) SA 793 (O) at 797H – 798C.

[5] Van Loggerenberg, Erasmus superior Court Practice, Second Edition at D1 – 55 (Erasmus)

[6] This duty of care emanates from section 28 of NEMA

[7] Silvermine Valley Coalition v Sybrand van der Spuy Boerderye and Others 20002 (1) SA 478 (CC) at 491 I.

[8] See the Oft-relied on case of Fripp v Gibbon & Co 1913 AD 354 at 363.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Germishuys v Douglas Besproeiingsroad 1973 (3) SA 299 (NC)

Case cited

Reuben Rosenblum Family Investments (Pty) Ltd and Another v Marsuban (Pty) Ltd 2003 (3) SA 547 (C)

Case cited

Waste Products Utilisation (Pty) Ltd v Wilkes 2003 (2) SA 590 (W)

Case cited

Erasmus v Grunow and Another 1980 (2) SA 793 (O)

Case cited

Wildlife & Environmental Society of SA v MEC for Economic Affairs, Environment & Tourism, Eastern Cape and Others 2005 (6) SA 123 (ECD)

Case cited

Silvermine Valley Coalition v Sybrand van der Spuy Boerderye and Others 2002 (1) SA 478 (CC)

Case cited

Fripp v Gibbon & Co 1913 AD 354

Case cited

National Water Act 36 of 1998

Legislation

Legislation referenced in the available case record.

National Environmental Management Act 107 of 1998

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.