Trencon Construction (Pty) Ltd v South African Airways (Pty) Ltd and Another (17452/13) [2014] ZAGPJHC 384 (7 November 2014)

Trencon Construction (Pty) Ltd v South African Airways (Pty) Ltd and Another (17452/13) [2014] ZAGPJHC 384 (7 November 2014)

The court found that the applicant was not responsible for the defects alleged by the respondents, as these were caused by a previous contractor and the contract did not impose liability on the applicant for such defects. The principal agent failed to issue a defects list within the required period, and as a result,...

Source-derived case information.

Citation
[2014] ZAGPJHC 384
Parties
Applicant: Trencon Construction (Pty) Ltd; Respondent: South African Airways (Pty) Ltd; Respondent: Focus Project Management
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
17452/13
Procedural Posture
Stay Application / First Instance
Outcome
Application granted in favour of the applicant.
Judges
P L Carstensen
Legal Topics
Specific Performance, Construction Contracts, Arbitration Clause, Final Completion Certificate
Commercial and Corporate Civil Procedure Specific Performance Construction Contracts Arbitration Clause Final Completion Certificate

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Trencon Construction (Pty) Ltd

Applicant

South African Airways (Pty) Ltd

Respondent

Focus Project Management

Respondent

Procedural Posture

Stay Application / First Instance

  1. 1 Whether the applicant is entitled to payment under the construction contract despite alleged defects in the works.
  2. 2 Whether the arbitration clause requires the dispute to be referred to arbitration before court proceedings.
  3. 3 Whether the applicant is liable for defects caused by a previous contractor.

Ratio Decidendi

The court found that the applicant was not responsible for the defects alleged by the respondents, as these were caused by a previous contractor and the contract did not impose liability on the applicant for such defects. The principal agent failed to issue a defects list within the required period, and as a result, the certificate of final completion is deemed to have been issued in terms of the contract. The arbitration clause was not properly invoked, as no notice of dissatisfaction was given by the respondents prior to the hearing. Consequently, the applicant is entitled to payment of the outstanding amount and costs.

Court Disposition

Application granted in favour of the applicant.

Orders

  • The First Respondent is ordered to pay the Applicant the amount of R552 040.38 within 10 days from date of this order.
  • The First Respondent is ordered to pay the Applicant’s costs.