Trencon (Pty) Ltd v Industrial Development Corporation of South Africa Ltd and Another (58961/2012, 70100/2012) [2013] ZAGPPHC 147 (3 June 2013)

Trencon (Pty) Ltd v Industrial Development Corporation of South Africa Ltd and Another (58961/2012, 70100/2012) [2013] ZAGPPHC 147 (3 June 2013)

The court found that IDC's decision to declare Trencon's bid non-responsive and award the tender to Basil Reed was materially influenced by an error of law regarding escalation fees for delayed site handover. The tender documents permitted escalation for such delays, and Trencon's bid remained compliant and...

Source-derived case information.

Citation
[2013] ZAGPPHC 147
Parties
Applicant: Trencon (Pty) Ltd; Respondent: Industrial Development Corporation of South Africa Ltd; Respondent: Basil Reed (Pty) Ltd
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
58961/2012, 70100/2012
Procedural Posture
Review Application / Judgment on Review and Substitution
Outcome
Application granted; IDC's decision reviewed, set aside, and substituted with an award of the tender to Trencon. Costs awarded to Trencon.
Judges
Mothle
Legal Topics
Tender Review, Promotion of Administrative Justice Act, Procedural Fairness, Material Error of Law, Substitution of Administrative Decision
Administrative Law Commercial and Corporate Tender Review Promotion of Administrative Justice Act Procedural Fairness Material Error of Law Substitution of Administrative Decision

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Trencon (Pty) Ltd

Applicant

Industrial Development Corporation of South Africa Ltd

Respondent

Basil Reed (Pty) Ltd

Respondent

Procedural Posture

Review Application / Judgment on Review and Substitution

  1. 1 Whether the IDC's decision to declare Trencon's tender non-responsive and award the tender to Basil Reed was influenced by a material error of law.
  2. 2 Whether the acceptance and evaluation of Basil Reed's late RFP was procedurally unfair.
  3. 3 Whether the circumstances justified substitution of the administrative decision by the court.

Ratio Decidendi

The court found that IDC's decision to declare Trencon's bid non-responsive and award the tender to Basil Reed was materially influenced by an error of law regarding escalation fees for delayed site handover. The tender documents permitted escalation for such delays, and Trencon's bid remained compliant and responsive. Furthermore, IDC's acceptance and evaluation of Basil Reed's late RFP was procedurally unfair and contrary to its own procurement policy, which only allowed late bids where no acceptable bids were received on time. The court held that these irregularities warranted review and setting aside of the decision. Exceptional circumstances justified substitution, as Trencon...

Court Disposition

Application granted; IDC's decision reviewed, set aside, and substituted with an award of the tender to Trencon. Costs awarded to Trencon.

Orders

  • The decision of the First Respondent to declare the Applicant's tender non-responsive and to award the tender to the Second Respondent is reviewed, set aside, and substituted with an award of the tender to the Applicant in terms of section 8(1)(c)(ii)(aa) of PAJA.
  • The contract sum shall be R110,633,822.28 plus VAT of R15,488,735.12.