Tshwarisano Trading CC v Sibonga Intuthuko Construction CC (59854/2011) [2019] ZAGPPHC 130 (17 April 2019)
The court found that the plaintiff proved on a balance of probabilities that it performed the work/services stipulated in the subcontract agreement. The evidence established that the plaintiff sourced and employed local labourers who physically completed the trench excavation, house connection, and backfilling, using machinery provided by the defendant. The defendant's version was uncorroborated and contradicted by the evidence of the plaintiff's witnesses, whose testimony was not challenged in cross-examination. The court accepted that the defendant paid salaries directly to the plaintiff's employees due to the plaintiff's lack of funds, but this amount must be deducted from the contract...
- Citation
- [2019] ZAGPPHC 130
- Parties
- Plaintiff: Tshwarisano Trading CC; Defendant: Sibonga Intuthuko Construction CC
- Court
- North Gauteng High Court, Pretoria
- Jurisdiction
- South Africa
- Judgment Date
- 17 April 2019
- Case Number
- 59854/2011
- Procedural Posture
- Civil Trial / Judgment After Trial
- Outcome
- Plaintiff's claim succeeds with costs. Defendant ordered to pay the plaintiff the contract sum less salaries already paid, with interest.
- Judges
- E.M. Kubushi
- Legal Topics
- Subcontractor Liability, Specific Performance, Proof of Performance, Contractual Dispute
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tshwarisano Trading CC
Plaintiff
Sibonga Intuthuko Construction CC
Defendant
Procedural Posture
Civil Trial / Judgment After Trial
Legal Issues
- 1 Whether the plaintiff performed the work/services stipulated in the subcontract agreement.
- 2 Whether the plaintiff is entitled to payment under the contract for services rendered.
- 3 Whether the defendant's payment of salaries to certain employees should be deducted from the contract sum.
Ratio Decidendi
The court found that the plaintiff proved on a balance of probabilities that it performed the work/services stipulated in the subcontract agreement. The evidence established that the plaintiff sourced and employed local labourers who physically completed the trench excavation, house connection, and backfilling, using machinery provided by the defendant. The defendant's version was uncorroborated and contradicted by the evidence of the plaintiff's witnesses, whose testimony was not challenged in cross-examination. The court accepted that the defendant paid salaries directly to the plaintiff's employees due to the plaintiff's lack of funds, but this amount must be deducted from the contract...
Court Disposition
Plaintiff's claim succeeds with costs. Defendant ordered to pay the plaintiff the contract sum less salaries already paid, with interest.
Orders
- The plaintiff's claim succeeds with costs.
- The defendant is ordered to pay the amount of R228,561.10 to the plaintiff.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment