Tubular Holdings (Pty) Ltd v DBT Technologies (Pty) Ltd (06757/2013) [2013] ZAGPJHC 155; 2014 (1) SA 244 (GSJ) (3 May 2013)

Tubular Holdings (Pty) Ltd v DBT Technologies (Pty) Ltd (06757/2013) [2013] ZAGPJHC 155; 2014 (1) SA 244 (GSJ) (3 May 2013)

The court held that the FIDIC dispute resolution mechanism requires parties to promptly give effect to a DAB decision, which is binding unless and until revised by arbitration or agreement. The issuance of a notice of dissatisfaction does not suspend this obligation; it merely triggers the right to seek revision in...

Source-derived case information.

Citation
[2013] ZAGPJHC 155
Parties
Applicant: Tubular Holdings (Pty) Ltd; Respondent: DBT Technologies (Pty) Limited
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Judgment Date
3 May 2013
Case Number
06757/2013
Procedural Posture
Urgent Application / First Instance
Outcome
Application granted; respondent ordered to comply with DAB decision and pay costs.
Judges
DTvR Du Plessis
Legal Topics
Fidic Conditions of Contract, Dispute Adjudication Board, Interim Enforcement, Arbitration Clause, Construction Contracts
Commercial and Corporate Alternative Dispute Resolution Fidic Conditions of Contract Dispute Adjudication Board Interim Enforcement Arbitration Clause Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Tubular Holdings (Pty) Ltd

Applicant

DBT Technologies (Pty) Limited

Respondent

Procedural Posture

Urgent Application / First Instance

  1. 1 Whether the decision of the Dispute Adjudication Board (DAB) is binding and enforceable pending arbitration after a notice of dissatisfaction is issued.
  2. 2 Whether the respondent is obliged to promptly give effect to the DAB decision despite having issued a notice of dissatisfaction.
  3. 3 Whether the DAB's determination that the subcontract is re-measurable applies to the entire contract or only to specific claims.

Ratio Decidendi

The court held that the FIDIC dispute resolution mechanism requires parties to promptly give effect to a DAB decision, which is binding unless and until revised by arbitration or agreement. The issuance of a notice of dissatisfaction does not suspend this obligation; it merely triggers the right to seek revision in arbitration. The court found the contractual wording clear and consistent with industry practice and previous judgments, including Bombela, Stocks & Stocks, and Freeman NO v Eskom Holdings. The DAB's determination that the subcontract is re-measurable applies to the entire contract, not just specific claims. Procedural provisions cited by the respondent do not bar the...

Court Disposition

Application granted; respondent ordered to comply with DAB decision and pay costs.

Orders

  • The respondent is ordered to forthwith give effect to the decision of the Dispute Adjudication Board handed down on 5 December 2012.
  • The respondent is ordered to forthwith re-measure and pay the applicant’s Interim Payment Certificate number 37 dated 25 January 2013.