Umgungundlovu District Municipality v MLO, New Boss and Zamisanani JV and Another (5831/2020P) [2021] ZAKZPHC 50 (11 August 2021)

Umgungundlovu District Municipality v MLO, New Boss and Zamisanani JV and Another (5831/2020P) [2021] ZAKZPHC 50 (11 August 2021)

The court found that the parties failed to appoint a member of the Adjudication Board within the prescribed 56-day period as required by clause 10.5.1 of the GCC 2010 contract. The contract specifically provided for dispute resolution by standing adjudication, and did not allow for ad hoc adjudication. As a result,...

Source-derived case information.

Citation
[2021] ZAKZPHC 50
Parties
Applicant: Umgungundlovu District Municipality; Respondent: MLO, New Boss & Zamisanani JV; Respondent: Bryan Westcott
Court
Kwazulu-Natal High Court, Pietermaritzburg
Jurisdiction
South Africa
Case Number
5831/2020P
Procedural Posture
Urgent Application / Final Judgment on Declaratory and Counter Application
Outcome
Declaratory relief granted; adjudication process declared unenforceable and null and void; counter-application dismissed with costs.
Judges
Bezuidenhout
Legal Topics
Construction Contracts, Adjudication Clauses, Arbitration Agreements, Declaratory Relief, Repudiation, Contractual Non Compliance
Commercial and Corporate Civil Procedure Construction Contracts Adjudication Clauses Arbitration Agreements Declaratory Relief Repudiation Contractual Non Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Umgungundlovu District Municipality

Applicant

MLO, New Boss & Zamisanani JV

Respondent

Bryan Westcott

Respondent

Procedural Posture

Urgent Application / Final Judgment on Declaratory and Counter Application

  1. 1 Whether the adjudication process under clause 10 of the GCC 2010 contract is enforceable given non-compliance with clause 10.5.1.
  2. 2 Whether the appointment of an adjudicator after the prescribed period is valid.
  3. 3 Whether the dispute may proceed to arbitration or must be resolved by litigation.

Ratio Decidendi

The court found that the parties failed to appoint a member of the Adjudication Board within the prescribed 56-day period as required by clause 10.5.1 of the GCC 2010 contract. The contract specifically provided for dispute resolution by standing adjudication, and did not allow for ad hoc adjudication. As a result, the adjudication process could not be implemented, and any proceedings conducted in terms thereof are null and void. The failure to comply with the contractual dispute resolution procedure also precludes referral to arbitration, as arbitration is only available if the dispute remains unresolved after adjudication. The court cannot direct the parties to proceed with adjudication...

Court Disposition

Declaratory relief granted; adjudication process declared unenforceable and null and void; counter-application dismissed with costs.

Orders

  • It is declared that the adjudication process as set out in clause 10 of the General Conditions of Contract for Construction Works (2010) 2nd edition (the GCC 2010 contract), as amended by the Contract Data, in respect of the contract for the upgrading of the Nkanyezini Water Supply Scheme, is unenforceable due to...
  • The first respondent is directed to pay the costs of the application, including those costs reserved on 8 September 2020.