Umlazi Civils Pty Ltd v Concor Construction t/a Conradie Development and Another (20967/2021) [2023] ZAWCHC 161 (10 July 2023)

Umlazi Civils Pty Ltd v Concor Construction t/a Conradie Development and Another (20967/2021) [2023] ZAWCHC 161 (10 July 2023)

The court held that the FIDIC contract did not confer on interim payment certificates an absolute or temporarily final right to payment in the face of a dispute. The contract's arbitration and adjudication provisions expressly allow for certificates to be opened up, reviewed, and revised by the arbitrator. The...

Source-derived case information.

Citation
[2023] ZAWCHC 161
Parties
Applicant: Umlazi Civils (Pty) Ltd; Respondent: Concor Construction (Pty) Ltd t/a Conradie Development; Respondent: BVI Consulting Engineers Western Cape (Pty) Ltd t/a BVI
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
20967/2021
Procedural Posture
Civil Application / Final Determination of Opposed Motion for Payment Under Interim Certificate
Outcome
Application dismissed except for admitted sum; order of absolution from the instance regarding the disputed balance.
Judges
Binns-Ward
Legal Topics
Building Contracts, Interim Payment Certificates, Arbitration Clauses, Contractual Defences, Liquid Documents
Commercial and Corporate Civil Procedure Building Contracts Interim Payment Certificates Arbitration Clauses Contractual Defences Liquid Documents

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Umlazi Civils (Pty) Ltd

Applicant

Concor Construction (Pty) Ltd t/a Conradie Development

Respondent

BVI Consulting Engineers Western Cape (Pty) Ltd t/a BVI

Respondent

Procedural Posture

Civil Application / Final Determination of Opposed Motion for Payment Under Interim Certificate

  1. 1 Whether an interim payment certificate under the FIDIC building contract entitles the contractor to immediate payment despite pending arbitration.
  2. 2 Whether the certificate constitutes a binding admission of indebtedness by the employer.
  3. 3 Whether the employer may raise contractual defences or set-off against the amount certified in the interim certificate.

Ratio Decidendi

The court held that the FIDIC contract did not confer on interim payment certificates an absolute or temporarily final right to payment in the face of a dispute. The contract's arbitration and adjudication provisions expressly allow for certificates to be opened up, reviewed, and revised by the arbitrator. The authorities relied on by the applicant do not establish a general rule of binding effect for interim certificates; rather, the effect depends on the specific contract terms. The employer retains the right to raise contractual defences and set-off, and the disputes regarding the certified amounts are pending before the arbitrator. The applicant is entitled only to the amount admitted...

Court Disposition

Application dismissed except for admitted sum; order of absolution from the instance regarding the disputed balance.

Orders

  • The first respondent's application for admission of its supplementary answering affidavit is granted; costs of that application to be paid by the first respondent.
  • The first respondent is ordered to pay the applicant the sum of R613,924.07 pursuant to interim payment certificate no.17, together with interest a tempore morae in terms of the contract calculated with reference to clause 14.7(b).