BWK Project Management Civils CC v Slice Investments (Pty) Ltd (AR 94/2017) [2018] ZAKZPHC 68 (12 October 2018)
The court found that the appellant failed to provide a satisfactory explanation for the excessive delay in prosecuting the appeal, attributing the delay to inadequate conduct by its attorneys. The explanation for the lateness was deemed insufficient, and the appellant had multiple opportunities to remedy the situation but failed to act with the required urgency. The court held that the appellant was in wilful default, as summonses were properly served at its registered address and no adequate reason was given for the failure to respond. The appellant did not establish a bona fide defence, as its arguments regarding cancellation of the lease and service of process were not supported by the...
- Citation
- [2018] ZAKZPHC 68
- Parties
- Appellant: BWK Project Management Civils CC; Respondent: Slice Investments (Pty) Ltd
- Court
- Kwazulu-Natal High Court, Pietermaritzburg
- Jurisdiction
- South Africa
- Judgment Date
- 12 October 2018
- Case Number
- AR 94/2017
- Procedural Posture
- Civil Appeal / Appeal Against Refusal of Rescission and Application for Condonation
- Outcome
- Appellant’s application for condonation is refused. Appeal dismissed with costs.
- Judges
- Masipa, Marks
- Legal Topics
- Condonation, Rescission of Judgment, Lease Agreement, Wilful Default, Service of Process, Prospects of Success
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
BWK Project Management Civils CC
Appellant
Slice Investments (Pty) Ltd
Respondent
Procedural Posture
Civil Appeal / Appeal Against Refusal of Rescission and Application for Condonation
Legal Issues
- 1 Whether condonation should be granted for the late prosecution of the appeal.
- 2 Whether the appellant has shown good cause for rescission of the default judgments.
- 3 Whether the appellant was in wilful default and has a bona fide defence.
Ratio Decidendi
The court found that the appellant failed to provide a satisfactory explanation for the excessive delay in prosecuting the appeal, attributing the delay to inadequate conduct by its attorneys. The explanation for the lateness was deemed insufficient, and the appellant had multiple opportunities to remedy the situation but failed to act with the required urgency. The court held that the appellant was in wilful default, as summonses were properly served at its registered address and no adequate reason was given for the failure to respond. The appellant did not establish a bona fide defence, as its arguments regarding cancellation of the lease and service of process were not supported by the...
Court Disposition
Appellant’s application for condonation is refused. Appeal dismissed with costs.
Orders
- The appellant’s application for condonation is refused.
- The appellant is to pay the respondent’s costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment