Download

South Africa Judgment

Northern Cape High Court, Kimberley

Liciano Coal (Pty) Ltd v Assmang Ltd and Another (2406/2016) [2016] ZANCHC 39 (2 December 2016)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the applicant was entitled to restoration of access to the property, as the previous order of Pakati J did not lapse due to late payment. The payments referred to in the order related to obligations during the operation of the interim interdict, not the initial payment, and Assmang could not rely on late payment to deny access. The breaches alleged by Assmang were either not relevant to the applicant or not properly invoked under the Access agreement, which required written notice and opportunity to remedy. The court held that the applicant had no adequate alternative remedy, as damages would not provide similar protection, and the urgency was justified given the imminent expiry of the prospecting agreement and ongoing losses. The application was substantially successful, and costs were awarded on the ordinary scale.

Court disposition

Application granted; access to property restored; costs awarded to applicant.

Orders

  • First respondent is ordered to restore the applicant's access to the property known as Farm Doornfontein 446 forthwith.
  • First respondent is interdicted and restrained from refusing or in any way prohibiting the applicant access to the property known as Farm Doornfontein 446.
  • First respondent is ordered to pay the costs of the application on the party and party scale.

02

Material facts

Parties

Liciano Coal (Pty) Ltd

Applicant Counsel: MJ Cooke

Assmang Ltd

Respondent Counsel: Y Alli

Ochre Shimmer Trade and Invest 78 (Pty) Ltd

Respondent

Amounts and remedies

  • Daily Equipment Loss: ZAR 35,000
  • Estimated Monthly Productivity Loss: ZAR 4,000,000
  • Payment Ordered by Pakati J (plus Vat): ZAR 1,387,700

03

Procedural history

  1. Posture

    Urgent Application / Final Judgment After Urgent Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that it had complied with the previous court order by making payment to Ochre Shimmer, albeit late, and was therefore entitled to access the property. It contended that Assmang's refusal to allow access was unjustified, especially as the order of Pakati J did not lapse due to late payment. The applicant further submitted that the breaches alleged by Assmang were either not relevant to it or not properly invoked under the Access agreement, and that the urgency was genuine due to the imminent expiry of the prospecting agreement and ongoing financial losses.
Respondent
Assmang argued that the order of Pakati J had lapsed due to the applicant's late payment, and that the applicant had entered into subsequent agreements which imposed further obligations that were not disclosed. Assmang also contended that breaches of contract and environmental obligations justified denial of access, and that the applicant had an alternative remedy in damages. Assmang disputed the urgency of the application, claiming it was self-created by the applicant's delay in payment and launching the application.

05

Court’s reasoning

  1. 01

    Order of Pakati J (21 August 2015)

    A court order for interim interdict does not lapse due to late payment unless expressly stated; payment obligations are enforceable by execution, not by denying access.

  2. 02

    Fakie NO v CCII Systems (Pty) Ltd [2006] ZASCA 52; 2006 (4) SA 326

    Contempt of court requires both wilful and mala fide non-compliance; honest belief in justification negates contempt.

  3. 03

    Setlogelo v Setlogelo 1914 AD 221

    The absence of similar protection by any other ordinary remedy is required for an interdict; damages are not necessarily a bar to interdictory relief.

  4. 04

    Access agreement between Assmang and Ochre Shimmer, clause 14

    Contractual breaches must be addressed in accordance with the procedure set out in the contract, including written notice and opportunity to remedy.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the applicant was entitled to restoration of access to the property, as the previous order of Pakati J did not lapse due to late payment. The payments referred to in the order related to obligations during the operation of the interim interdict, not the initial payment, and Assmang could not rely on late payment to deny access. The breaches alleged by Assmang were either not relevant to the applicant or not properly invoked under the Access agreement, which required written notice and opportunity to remedy. The court held that the applicant had no adequate alternative remedy, as damages would not provide similar protection, and the urgency was justified given the imminent expiry of the prospecting agreement and ongoing losses. The application was substantially successful, and costs were awarded on the ordinary scale.

Obiter and limits

  • Assmang's reliance on breaches of agreements to which it was not a party is misplaced and cannot justify denial of access.
  • The Environmental Management Plan does not prohibit prospecting during rehabilitation; rehabilitation is to be done concurrently or within 60 days of termination.
  • A punitive cost order is not warranted unless dishonesty, improper conduct, or mala fides are shown.

Court disposition

Application granted; access to property restored; costs awarded to applicant.

  • First respondent is ordered to restore the applicant's access to the property known as Farm Doornfontein 446 forthwith.
  • First respondent is interdicted and restrained from refusing or in any way prohibiting the applicant access to the property known as Farm Doornfontein 446.
  • First respondent is ordered to pay the costs of the application on the party and party scale.

Source and reliance status

Northern Cape High Court, Kimberley

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Full judgment text is not available for this record.

Use the source document link when available.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Fakie NO v CCII Systems (Pty) Ltd [2006] ZASCA 52; 2006 (4) SA 326

Case cited

Setlogelo v Setlogelo 1914 AD 221

Case cited

Peri-Urban Areas Health Board v Sandhurst Gardens 1965(1) SA TPD 683

Case cited

Mineral and Petroleum Resources Development Act, 28 of 2002

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.