Siemens (Pty) Ltd v Eskom Holdings (SOC) Ltd and Another (29841/2019) [2021] ZAGPJHC 128 (16 August 2021)
Eskom's invitation to tender for the Camden Power Station contract specified three prequalification criteria, expressed disjunctively, meaning that a tenderer needed to meet only one to qualify. Siemens met the criterion of committing to subcontract 30% of the work to qualifying QSEs and EMEs, as confirmed by Eskom's own evaluation report and admitted in Eskom's answering affidavit. Eskom's decision to disqualify Siemens for not meeting all criteria was contrary to the terms of the invitation and lacked a rational connection to its stated purpose, violating section 6(2)(b) and 6(2)(f)(ii)(aa) of PAJA. The irregularity was material, affecting the lawfulness of the tender process and the...
- Citation
- [2021] ZAGPJHC 128
- Parties
- Applicant: Siemens (Pty) Ltd; Respondent: Eskom Holdings (SOC) Ltd; Respondent: Senta Square (Pty) Ltd
- Court
- South Gauteng High Court, Johannesburg
- Jurisdiction
- South Africa
- Judgment Date
- 16 August 2021
- Case Number
- 29841/2019
- Procedural Posture
- Review Application / Judgment on Review and Remedy Directions
- Outcome
- The award of the tender to Senta Square was declared unlawful, but the declaration is suspended pending determination of a just and equitable remedy. The parties are directed to provide further factual information and submissions, and the matter is set down for a further hearing. Eskom is ordered to pay Siemens'...
- Judges
- S D J Wilson
- Legal Topics
- Public Procurement, Preferential Procurement Policy Framework Act, Promotion of Administrative Justice Act, Tender Irregularity, B Bbee Prequalification, Remedy Under Paja
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Siemens (Pty) Ltd
Applicant
Eskom Holdings (SOC) Ltd
Respondent
Senta Square (Pty) Ltd
Respondent
Procedural Posture
Review Application / Judgment on Review and Remedy Directions
Legal Issues
- 1 Whether Eskom lawfully disqualified Siemens from the second tender process for control and instrumentation maintenance at Camden Power Station.
- 2 Whether the prequalification criteria in the tender were correctly interpreted and applied by Eskom.
- 3 Whether Siemens met at least one of the prequalification criteria and was thus improperly excluded.
Ratio Decidendi
Eskom's invitation to tender for the Camden Power Station contract specified three prequalification criteria, expressed disjunctively, meaning that a tenderer needed to meet only one to qualify. Siemens met the criterion of committing to subcontract 30% of the work to qualifying QSEs and EMEs, as confirmed by Eskom's own evaluation report and admitted in Eskom's answering affidavit. Eskom's decision to disqualify Siemens for not meeting all criteria was contrary to the terms of the invitation and lacked a rational connection to its stated purpose, violating section 6(2)(b) and 6(2)(f)(ii)(aa) of PAJA. The irregularity was material, affecting the lawfulness of the tender process and the...
Court Disposition
The award of the tender to Senta Square was declared unlawful, but the declaration is suspended pending determination of a just and equitable remedy. The parties are directed to provide further factual information and submissions, and the matter is set down for a further hearing. Eskom is ordered to pay Siemens'...
Orders
- It is declared that Eskom's award of the tender for control and instrumentation maintenance at Camden Power Station between 1 March 2019 and 28 February 2022 to Senta Square was unlawful.
- The declaration of unlawfulness is suspended pending determination of a just and equitable remedy.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment