Hemipac Investments (Pty) Ltd v Independent Electoral Commission and Others (EL1219/16) [2017] ZAECELLC 14 (12 July 2017)
The court found that the applicant's bids were lawfully disqualified because they failed to comply with the mandatory requirements of the tender. The bid specifications clearly required a single, all-inclusive price for a 250KVA emergency power generator, with no room for post-submission negotiation or qualification. The applicant's covering letters introduced uncertainty and an invitation to negotiate generator costs after bid closure, which contravened the tender rules. The distinction drawn by the applicant between 'emergency' and 'back-up' generators was found to be contrived and unsupported by the tender documentation or common usage. The court held that the first respondent's...
- Citation
- [2017] ZAECELLC 14
- Parties
- Applicant: Hemipac Investments (Pty) Ltd; Respondent: Independent Electoral Commission; Respondent: Crane Crest Investments 71 (Pty) Ltd t/a Novate Property Investments; Respondent: Harbour Point Fuels (Pty) Ltd; Respondent: 69 Frere Road Trust; Respondent: Ballustrade Properties (Pty) Ltd; Respondent: Sthathu Funding (Pty) Ltd; Respondent: Finishing Touch Trading 260 (Pty) Ltd
- Court
- Eastern Cape High Court, East London Local Court
- Jurisdiction
- South Africa
- Judgment Date
- 12 July 2017
- Case Number
- EL1219/16
- Procedural Posture
- Review Application / Judgment
- Outcome
- Application dismissed with costs, including costs of two counsel and costs occasioned by the interdict application.
- Judges
- Mageza
- Legal Topics
- Public Procurement, Promotion of Administrative Justice Act, Bid Disqualification, Preferential Procurement Policy Framework Act, Procedural Fairness, Tender Specification Compliance
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hemipac Investments (Pty) Ltd
Applicant
Independent Electoral Commission
Respondent
Crane Crest Investments 71 (Pty) Ltd t/a Novate Property Investments
Respondent
Harbour Point Fuels (Pty) Ltd
Respondent
69 Frere Road Trust
Respondent
Ballustrade Properties (Pty) Ltd
Respondent
Sthathu Funding (Pty) Ltd
Respondent
Finishing Touch Trading 260 (Pty) Ltd
Respondent
Procedural Posture
Review Application / Judgment
Legal Issues
- 1 Whether the applicant's bids were lawfully disqualified by the first respondent during the tender process.
- 2 Whether the disqualification was rationally connected to the information before the decision-maker and complied with the requirements of PAJA.
- 3 Whether the tender process was procedurally fair and in accordance with the Preferential Procurement Policy Framework Act.
Ratio Decidendi
The court found that the applicant's bids were lawfully disqualified because they failed to comply with the mandatory requirements of the tender. The bid specifications clearly required a single, all-inclusive price for a 250KVA emergency power generator, with no room for post-submission negotiation or qualification. The applicant's covering letters introduced uncertainty and an invitation to negotiate generator costs after bid closure, which contravened the tender rules. The distinction drawn by the applicant between 'emergency' and 'back-up' generators was found to be contrived and unsupported by the tender documentation or common usage. The court held that the first respondent's...
Court Disposition
Application dismissed with costs, including costs of two counsel and costs occasioned by the interdict application.
Orders
- The application is dismissed with costs.
- Costs to include the costs of two counsel.
Full Case Text
Judgment text and source record