AfriRent (Pty) Ltd v Rand West City Local Municipality and Another (2023-052811) [2023] ZAGPJHC 1430 (11 December 2023)
- Citation
- [2023] ZAGPJHC 1430
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- South Gauteng High Court, Johannesburg
- Panel
- S D J Wilson
- Case number
- 2023-052811
More details
- Court
- South Gauteng High Court, Johannesburg
- Panel
- S D J Wilson
- Case number
- 2023-052811
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court held that Rand West City Local Municipality acted rationally in refusing to award the tender to Afrirent due to its failure to provide a statement of tax liability, as requested. Fleet Horizon Solutions (Pty) Ltd was not legally required to submit audited financial statements, and therefore, its bid was lawfully accepted despite its initial representation. The post-award condition required only negotiation to decrease the price, not an actual reduction, and evidence of such negotiation was present. There was no reasonable prospect that another court would reach a different conclusion on any of these issues.
Court disposition
Application for leave to appeal dismissed with costs, including costs of two counsel.
Orders
- The application for leave to appeal is dismissed.
- The applicant is ordered to pay the costs of the application, including the costs of two counsel.
02
Material facts
Parties
AfriRent (Pty) Ltd
Applicant Counsel: AJP ElsRand West City Local Municipality
Respondent Counsel: V Maleka SC, M SalukazanaFleet Horizon Solutions (Pty) Ltd
Respondent Counsel: AC Botha SC, C Cremen03
Procedural history
Posture
Leave to Appeal / Application for Leave to Appeal Following Dismissal of Review Application
04
Questions and positions
Legal issues
- 01
Whether Rand West City Local Municipality acted irrationally in refusing to award the tender to Afrirent due to non-disclosure of a tax liability statement.
- 02
Whether Fleet Horizon Solutions (Pty) Ltd ought to have been disqualified for failing to submit three years of audited financial statements.
- 03
Whether the post-award condition requiring negotiation to decrease Fleet Horizon's tender price was fulfilled.
Party arguments
- Applicant
- Afrirent argued that Rand West acted irrationally by refusing to award the tender based on Afrirent's failure to provide a statement of tax liability, contending that the requirement was unreasonable. Afrirent further submitted that Fleet Horizon should have been disqualified for not submitting three years of audited financial statements, referencing the WDR Earthmoving Enterprises v Joe Gqabi District Municipality case. Lastly, Afrirent claimed that the post-award condition required an actual reduction in Fleet Horizon's price, not merely negotiation.
- Respondent
- Rand West and Fleet Horizon maintained that the request for Afrirent's tax liability statement was rational and justified the refusal to award the tender. They argued that Fleet Horizon was not legally required to submit audited financial statements, distinguishing the facts from the WDR case. Both respondents asserted that the post-award condition only required negotiation, not a mandatory price reduction, and that evidence of negotiation was present in the affidavits.
05
Court’s reasoning
Legal principles
- 01
WDR Earthmoving Enterprises v Joe Gqabi District Municipality 2018 JDR 1295 (SCA)
Strict compliance with statutory requirements and bid conditions is generally required in tender matters, but organs of state are not obliged to exclude bidders for non-compliance with requirements that do not legally apply to them.
- 02
Constitution of the Republic of South Africa, 1996
Rational, lawful, and fair administrative procedure is required under section 33 of the Constitution, and procurement must be fair, equitable, transparent, competitive, and cost-effective under section 217.
06
Ratio, limits and disposition
Ratio decidendi
The court held that Rand West City Local Municipality acted rationally in refusing to award the tender to Afrirent due to its failure to provide a statement of tax liability, as requested. Fleet Horizon Solutions (Pty) Ltd was not legally required to submit audited financial statements, and therefore, its bid was lawfully accepted despite its initial representation. The post-award condition required only negotiation to decrease the price, not an actual reduction, and evidence of such negotiation was present. There was no reasonable prospect that another court would reach a different conclusion on any of these issues.
Obiter and limits
- Strict compliance with tender requirements does not extend to enforcing conditions that are later found not to apply to a bidder.
- The approach advocated by Afrirent would undermine rational and fair administrative procedures and procurement principles.
Court disposition
Application for leave to appeal dismissed with costs, including costs of two counsel.
- The application for leave to appeal is dismissed.
- The applicant is ordered to pay the costs of the application, including the costs of two counsel.
Source and reliance status
South Gauteng High Court, Johannesburg
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
South Gauteng High Court, Johannesburg
Judgment
IN THE HIGH COURT OF
SOUTH AFRICA
(GAUTENG DIVISION, JOHANNESBURG)
Case No. 2023-052811
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
REVISED
11/12/23
In the matter between:
AFRIRENT (PTY) LTD Applicant And
RAND
WEST CITY LOCAL MUNICIPALITY First Respondent
FLEET HORIZON SOLUTIONS (PTY) LTD Second Respondent
JUDGMENT
WILSON J:
1 The applicant, Afrirent, seeks leave to appeal my judgment, dated 23 October 2023, in which I refused its application to review and set aside the award of a tender to the second respondent, Fleet Horizon. The tender was advertised and awarded by the first
respondent, Rand West.
2 The review application turned on three issues. The first was whether Rand West conducted itself irrationally in refusing to award
the tender to Afrirent because Afrirent had failed to hand over a copy of a statement of its liability to the South African Revenue
Service. The second was whether Fleet Horizon ought to have been disqualified for its failure to hand over three years’ worth of audited financial statements. The third was whether a post-award condition that there be a negotiation aimed at reducing Fleet
Horizon’s tender price had been fulfilled.
3 For the most part, Mr. Els, who appeared for Afrirent, trod a familiar path in arguing the application for leave to appeal. He was
unable to convince me that there was any prospect that a court of appeal would interfere with my conclusion on the first issue. Rand West had a rational basis on which to ask Afrirent for a statement of its tax liability. When that statement was not provided, despite two requests for it, Rand West plainly had a rational basis to refuse to award the tender to Afrirent solely because of that non-disclosure.
4 On the second issue, Mr. Els sought to persuade me that I had overlooked the effect of the decision of the Supreme Court of Appeal
in WDR Earthmoving Enterprises v Joe Gqabi District Municipality 2018 JDR 1295 (SCA) (“WDR”). In that case, an unsuccessful bidder had stated in its bid that it was required by law to have its financial statements audited. It followed from that representation that three years’ worth of audited financial statements had to be supplied with the bid. However, the audited statements were not submitted with the bid. On review, the unsuccessful bidder asserted that it was not, after all, legally required to have its financial statements audited, that the requirement to submit audited statements did not apply to it, and that it ought not to have been excluded from consideration for the award of a tender merely because audited statements were not submitted.
5 The Supreme Court of Appeal rejected that submission. The court found that the municipality was entitled to decline the bid on the basis that the bidder had represented that it was required to supply the audited statements, and then failed to submit them, even
if it later turned out that the representation was erroneous. The court went on to hold that the successful bidder, too, ought to have been disqualified, because it had also failed to submit audited financial statements notwithstanding its representation that it was required by law to have its financial statements audited. There was no suggestion that the successful bidder was not in fact legally required to have its statements audited.
6 In this case, like the successful bidder in WDR, Fleet Horizon originally told Rand West that it was required to provide audited financial statements, but Rand West nonetheless accepted Fleet Horizon’s bid without them. However, unlike the successful bidder in WDR, Fleet Horizon was not in fact legally
required to have its financial statements audited. As a result, it was not legally required to submit audited financial statements.
7 The question before me was whether Rand West had acted unlawfully in accepting Fleet Horizon’s bid without the audited statements. I held that Rand West could not have acted unlawfully because it turned out that the requirement did not apply to Fleet Horizon after all, whatever Fleet Horizon had originally said in its bid documents.
8 Mr. Els accepted that Fleet Horizon was not legally required to have its financial statements audited (or at least that there was
no basis on the papers for him to argue otherwise). He nonetheless contended that Rand West ought to have rejected Fleet Horizon’s
bid on the basis that the requirement did apply, because Fleet Horizon had said so in its bid, even though everyone later accepted
that the requirement did not in fact apply.
9 That proposition need only be stated to be rejected. I accept that the approach in tender matters has generally been to require strict compliance with statutory requirements and the bid conditions that give effect to them. However, I am unable to accept that strict compliance means that organs of state must be prevented from appointing service providers who do not conform to requirements that turn out not to apply to them, especially where the tender process was otherwise fair and lawful.
10 Mr. Els’ submission boils down to the proposition that this case should have been determined on the basis of a fact that everyone now accepts is untrue: that Fleet Horizon is required by law to have its financial statements audited. I fail to see how, as Mr.
Els submitted, such an approach would promote either rational, lawful and fair administrative procedure (see section 33 of the
Constitution, 1996), or fair, equitable, transparent, competitive and cost-effective procurement (see section 217 of the Constitution,
1996). I see no basis on which an appeal court would disagree.
11 On the third issue, Mr. Els argued that the post-award condition was not merely that there be a negotiation, but that Fleet Horizon’s price actually be reduced. However, the condition set out in the award letter speaks for itself. It calls for a “negotiation of decreasing” the price. Despite the inelegant turn of phrase, this can only mean one thing: that the parties negotiate. It is incapable of also meaning that they must reach a particular resolution.
12 Mr. Els further argued that, even if that was the meaning to be ascribed to the condition, there was no evidence before me that there had actually been a negotiation. But counsel for Rand West and for Fleet Horizon both pointed out undisputed passages of their
clients’ affidavits which clearly state that there was such a negotiation. On the well-known rules applicable to the evaluation of factual averments in applications for final relief, those allegations must be accepted
13 The application for leave to appeal is dismissed with costs, including the costs of two counsel.
S D J WILSON
Judge of the High Court
This judgment is handed down electronically by circulation to the parties or their legal representatives by email, by uploading to Caselines, and by publication to the South African Legal Information Institute. The date for hand-down is deemed to be 11 December 2023.
HEARD ON: 5 December 2023
DECIDED ON: 11 December 2023
For the Applicant:
AJP Els
Instructed by Albert Hibbert Attorneys
For the First Respondent:
V Maleka SC
M Salukazana
Instructed by Straus Daly
For the Second Respondent:
AC Botha SC
C Cremen
Instructed by Bouwer & Oliver