Topigs Norsvin SA Proprietary Limited v Eskom Holdings SOC Ltd and Others (013715/2022) [2024] ZAGPPHC 561 (19 June 2024)

Topigs Norsvin SA Proprietary Limited v Eskom Holdings SOC Ltd and Others (013715/2022) [2024] ZAGPPHC 561 (19 June 2024)

The court found that while the applicant established a clear right to an unpolluted environment and demonstrated ongoing pollution and degradation of downstream water resources by Eskom, it failed to satisfy the requirement of absence of alternative remedy. Section 28(12) of NEMA provides a statutory mechanism for...

Source-derived case information.

Citation
[2024] ZAGPPHC 561
Parties
Applicant: Topigs Norsvin SA Proprietary Limited; Respondent: Eskom Holdings SOC Ltd; Respondent: Andre Marinus de Ruyter; Respondent: Calib Cassim; Respondent: Malegapuru William Makgoba; Respondent: Banothile Charity Makhubela; Respondent: Pulane Elsie Molokwane; Respondent: Busisiwe Mavuso; Respondent: Roderick de Brassic Crompton; Respondent: Tshepo Herbert Tong-Mongalo; Respondent: Mlawuli Mayor Majingolo; Respondent: Deidre Herbst; Respondent: Bongumusa Mashazi; Respondent: Lesiba Kgobe; Respondent: Minister of Water and Sanitation; Respondent: Director-General: Department of Water and Sanitation; Respondent: Minister of Forestry, Fisheries and the Environment; Respondent: Forestry, Fisheries and the Environment; Respondent: Minister of Mineral Resources and Energy; Respondent: National Energy Regulator of South Africa; Respondent: Clive Raymond Le Roux; Respondent: Paul Mpho Makwana; Respondent: Austin Leslie Mkhabela; Respondent: Busisiwe Vilakazi; Respondent: Lwazi Leon Goqwana; Respondent: Fathima Bee Bee Abdul Gany; Respondent: Anyanda Pearl Zinhle Mafuleka; Respondent: Tskani Lotten Mthombeni; Respondent: Beki Zacharia Ntshalintshali; Respondent: Nteto Nyathi; Respondent: Tryphosa Ramano; Respondent: Clauselle von Eck
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
013715/2022
Procedural Posture
Structural Interdict Application / Judgment
Outcome
Application dismissed with no order as to costs.
Judges
ML Twala
Legal Topics
Water Use Licence Compliance, Structural Interdict, Subsidiarity Principle, Duty of Care, Constitutional Environmental Rights, Enforcement of Environmental Laws
Environmental Law Administrative Law Water Use Licence Compliance Structural Interdict Subsidiarity Principle Duty of Care Constitutional Environmental Rights Enforcement of Environmental Laws

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 24 Party arguments 2
Sign in to unlock

Parties

Topigs Norsvin SA Proprietary Limited

Applicant

Eskom Holdings SOC Ltd

Respondent

Andre Marinus de Ruyter

Respondent

Calib Cassim

Respondent

Malegapuru William Makgoba

Respondent

Banothile Charity Makhubela

Respondent

Pulane Elsie Molokwane

Respondent

Busisiwe Mavuso

Respondent

Roderick de Brassic Crompton

Respondent

Tshepo Herbert Tong-Mongalo

Respondent

Mlawuli Mayor Majingolo

Respondent

Deidre Herbst

Respondent

Bongumusa Mashazi

Respondent

Lesiba Kgobe

Respondent

Minister of Water and Sanitation

Respondent

Director-General: Department of Water and Sanitation

Respondent

Minister of Forestry, Fisheries and the Environment

Respondent

Forestry, Fisheries and the Environment

Respondent

Minister of Mineral Resources and Energy

Respondent

National Energy Regulator of South Africa

Respondent

Clive Raymond Le Roux

Respondent

Paul Mpho Makwana

Respondent

Austin Leslie Mkhabela

Respondent

Busisiwe Vilakazi

Respondent

Lwazi Leon Goqwana

Respondent

Fathima Bee Bee Abdul Gany

Respondent

Anyanda Pearl Zinhle Mafuleka

Respondent

Tskani Lotten Mthombeni

Respondent

Beki Zacharia Ntshalintshali

Respondent

Nteto Nyathi

Respondent

Tryphosa Ramano

Respondent

Clauselle von Eck

Respondent

Procedural Posture

Structural Interdict Application / Judgment

  1. 1 Whether Eskom has failed to comply with conditions of environmental authorisations and water use licences for Kusile Power Station.
  2. 2 Whether the State respondents failed to enforce compliance by Eskom with legal requirements under NEMA and NWA.
  3. 3 Whether the applicant is entitled to a structural interdict against Eskom and the State respondents.

Ratio Decidendi

The court found that while the applicant established a clear right to an unpolluted environment and demonstrated ongoing pollution and degradation of downstream water resources by Eskom, it failed to satisfy the requirement of absence of alternative remedy. Section 28(12) of NEMA provides a statutory mechanism for compelling the Director-General to take remedial action against polluters, which the applicant did not invoke. The court held that the principle of subsidiarity precludes direct constitutional relief where legislation exists to give effect to the right, and the applicant should have relied on or challenged the adequacy of NEMA and NWA. Granting the structural interdict sought...

Court Disposition

Application dismissed with no order as to costs.

Orders

  • The application is dismissed.
  • Each party is to pay its own costs.