Van Immerzeel & Pohl and Another v Samancor Ltd (543/98) [2000] ZASCA 79; 2001 (2) SA 90 (SCA); [2001] 2 All SA 235 (A) (30 November 2000)
The Supreme Court of Appeal held that the contractor under the construction contract was the firm, not the close corporation, based on the contract wording, tender documents, and conduct. Prescription had not run against the firm because the plaintiff reasonably believed the debtor was the close corporation and only learned otherwise less than three years before joinder. The cession of claims from the employer to the plaintiff was valid and included the damages claim. The employer suffered damage as it had a contractual right to claim the cost of re-executing defective work, regardless of land ownership. ACE was a nominated sub-contractor, making the firm liable for its defective work....
- Citation
- [2000] ZASCA 79
- Parties
- Appellant: Van Immerzeel & Pohl; Appellant: Cocciante Construction; Respondent: Samancor Ltd
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 30 November 2000
- Case Number
- 543/98
- Procedural Posture
- Civil Appeal / Appeal Against Judgment of the Transvaal Provincial Division
- Outcome
- Appeals of both appellants dismissed with costs, including costs of two counsel, and damages awards adjusted for retention money deduction.
- Judges
- Olivier, Schutz, Farlam, Brand, Chetty
- Legal Topics
- Construction Contracts, Prescription Act, Cession of Claims, Damages Assessment, Contractual Liability, Professional Services Liability
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Van Immerzeel & Pohl
Appellant
Cocciante Construction
Appellant
Samancor Ltd
Respondent
Procedural Posture
Civil Appeal / Appeal Against Judgment of the Transvaal Provincial Division
Legal Issues
- 1 Whether the contractor under the construction contract was the firm or the close corporation.
- 2 Whether the claim against the contractor had prescribed before joinder and service of amended particulars of claim.
- 3 Whether the employer's claim was validly ceded to the plaintiff.
Ratio Decidendi
The Supreme Court of Appeal held that the contractor under the construction contract was the firm, not the close corporation, based on the contract wording, tender documents, and conduct. Prescription had not run against the firm because the plaintiff reasonably believed the debtor was the close corporation and only learned otherwise less than three years before joinder. The cession of claims from the employer to the plaintiff was valid and included the damages claim. The employer suffered damage as it had a contractual right to claim the cost of re-executing defective work, regardless of land ownership. ACE was a nominated sub-contractor, making the firm liable for its defective work....
Court Disposition
Appeals of both appellants dismissed with costs, including costs of two counsel, and damages awards adjusted for retention money deduction.
Orders
- The appeals of both appellants are dismissed with costs, including those occasioned by the employment of two counsel.
- The order of the court below is altered by substituting the amount of R910 570 for R973 544-48 in paragraph 1.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment