Download PDF

South Africa Judgment

South Gauteng High Court, Johannesburg

Vanske Team Consulting CC v Zwelothando Minerals and Resources (Pty) Ltd (10957/2013) [2013] ZAGPJHC 136 (30 May 2013)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that there was a material dispute of fact regarding possession of the property and the keys. The applicant failed to demonstrate that the respondent's version was clearly untenable, far-fetched, or implausible. The evidence did not establish that the applicant was in peaceful and undisturbed possession or exercising a builder's lien at the relevant time. Accordingly, the applicant did not discharge the burden required for final relief in motion proceedings, and the spoliation order previously granted was set aside.

Court disposition

Application for reconsideration succeeds; previous spoliation order set aside; costs awarded against applicant.

Orders

  • The order granted on 2 April 2013 is set aside.
  • The applicant is to pay the costs of this and the previous application.

02

Material facts

Parties

Vanske Team Consulting CC

Applicant Counsel: Adv. A.R. Van Der Merwe

Zwelothando Minerals and Resources (Pty) Ltd

Respondent Counsel: Adv. C Van Der Merwe

03

Procedural history

  1. Posture

    Urgent Application / Reconsideration of Spoliation Order Under Rule 6(12)(c)

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant, a building contractor, contends it was in peaceful possession of the property at 59 and 61 Bowling Road, Johannesburg, and entitled to remain there despite cancellation of the contract, as it was exercising a valid builder's lien. The applicant claims to have always possessed the only set of keys and controlled access to the property. It argues that the respondent's actions in employing a security guard to prevent access constituted spoliation.
Respondent
The respondent, a property developer, asserts that the applicant never had full access or control over the property. The respondent's caretaker, Mawale, was in charge of the premises and keys, which were handed to the applicant's representative only temporarily. The respondent claims to have requested the return of the keys, which the applicant refused. The respondent maintains that the applicant was not in peaceful possession and was not exercising a lien at the relevant time.

05

Court’s reasoning

  1. 01

    National Director of Public Prosecutions v Zuma [2009] ZASCA 1; 2009 (2) SA 277 (SCA) at [26]

    In motion proceedings, final relief may only be granted if the facts averred in the applicant's affidavits, which have been admitted by the respondent, together with the respondent's alleged facts, justify such order. Where disputes of fact arise, a final order can only be granted if the respondent's version is clearly untenable, far-fetched, or palpably implausible.

  2. 02

    Oosthuizen v Mijs 2009 (6) SA 266 (W)

    The court must consider the matter de novo when reconsidering an order under Rule 6(12)(c).

06

Ratio, limits and disposition

Ratio decidendi

The court found that there was a material dispute of fact regarding possession of the property and the keys. The applicant failed to demonstrate that the respondent's version was clearly untenable, far-fetched, or implausible. The evidence did not establish that the applicant was in peaceful and undisturbed possession or exercising a builder's lien at the relevant time. Accordingly, the applicant did not discharge the burden required for final relief in motion proceedings, and the spoliation order previously granted was set aside.

Obiter and limits

  • The applicant's reliance on an email as evidence of intention to exercise a builder's lien was insufficient, as the email did not explicitly state such intention.
  • The standard for rejecting a respondent's version in motion proceedings is stringent and requires the applicant to show that the version is clearly untenable.

Court disposition

Application for reconsideration succeeds; previous spoliation order set aside; costs awarded against applicant.

  • The order granted on 2 April 2013 is set aside.
  • The applicant is to pay the costs of this and the previous application.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Judgment

[2013] ZAGPJHC 136

NOT REPORTABLE

IN THE SOUTH GAUTENG HIGH COURT

(JOHANNESBURG)

CASE NO: 10957/2013

DATE: 30/05/2013

In the matter between:

VANSKE TEAM CONSULTING CC...................................................................................Applicant

and

ZWELOTHANDO MINERALS AND RESOURCES (PTY) LTD....................................Respondent

JUDGMENT

WEINER J

[1] In this matter, the applicant obtained a spoliation order against the Respondent on the 02 April 2013. The respondent has applied in terms of Rule 6(12)(c) for the matter to be reconsidered. The principles relating to this procedure were dealt with in Oosthuizen v Mijs1, where it was held that in such a case, the court should consider the matter de novo.

THE FACTS

[2] The applicant is a building contractor that was contracted by the respondent, a property developer, to renovate certain immovable property situate at 59 and 61 Bowling Road, Johannesburg (“the property”). The applicant was represented by Warren Skene (Skene) and the respondent by Ms Vavi (Vavi)

[3] The precise terms and conditions of the building contract are in dispute. The applicant submits that they are partly written and partly oral. The respondent contends that they were oral. It is common cause that the written agreement was handed over to the respondent and that she never signed it. Vavi states that she never expressed an intention to sign and that she, in fact, never looked through it in its entirety. The applicant submits that Vavi did express an intention to sign and as such it should form part of their agreement. It is not necessary in these proceedings to determine this issue.

[4] The issue to be decided is whether the respondent committed an act of spoliation when it employed a security guard to prevent the applicant having access to the property. The applicant contends that it was always in peaceful possession of the property and is entitled to remain there, despite the contract being cancelled, as it is exercising a valid builder’s lien over the property.

POSSESSION

[5] The issue as to whether there was a spoliation depends upon which party was in peaceful, undisturbed possession when the respondent barred the applicant from entry.

[6] There is a dispute of fact on this point. The applicant states that it, at all times after they moved onto the premises, has been in possession of the only set of keys. Their representative, Vusi would allow other parties access when necessary.

[7] The respondent, however, says that the applicant never had full access to or complete control over the property. It contends that access was controlled solely by their representative, one Mawale. He was in charge of the premises and had the keys thereto. He handed the keys to the applicant’s representative on the 2nd April 2013, when he was requested to do so, on a temporary basis. According to his version, he expected that they would be returned at the end of the day. The respondent states that Mawale asked for the keys back the next day but that the applicant refused to give them back. The applicant contends that this did not

occur as it was always in possession of both the original and a duplicate set of keys and had no need to obtain same from Mawale.

They remain in possession of same.

THE LAW/FINAL RELIEF

[8] In essence, the dispute in question is purely factual. The applicant seeks final relief.

In regard to determining factual disputes in motion proceedings, the judgment of Harms DP in National Director of Public Prosecutions v Zuma2 is of relevance, particularly at [26]:

“Motion Proceedings, unless concerned with interim relief, are all about the resolution of legal issues based on common cause facts. Unless the circumstances are special they cannot be used to resolve factual issues because they are not designed to determine probabilities. It is well established under the Plascon-Evans rule that where in motion proceedings disputes of facts arise on the affidavits, a final order can be granted only if the facts averred in the applicant’s affidavits, which have been admitted by the respondent, together with the facts alleged by the latter, justify such order. It may be different if the respondent’s version consists of bald or uncreditworthy denials, raises fictitious disputes of fact, is palpably implausible, far-fetched or so clearly untenable that the court is justified in

rejecting them merely on the papers.”3(my emphasis)

[9] The issue in casu is who was in possession of the property on the 19th April 2013 when the security guard prevented the applicant from entering the premises. The question to decide is whether the respondent’s version is bona fide or whether such version can be rejected as being; a “bald or uncreditworthy denial”4; whether it “raises fictitious disputes of fact, is palpably implausible, far-fetched or so clearly untenable”5 that justify the Court deciding this factual dispute in favour of the applicant. I, therefore, turn to the version put forward by the respondent. In so doing, the issue as to whether there are aspects of the respondent’s version which corroborate those of the applicant for purposes of final relief, will be considered6.

THE RESPONDENT’S VERSION

[10]The respondent contends that they, as owner of the property, had employed the caretaker Mawale to be the custodian of the keys and access to the building site. Mawale confirms this. The respondent submitted in its answering affidavit the applicant came into possession of the keys when they “insisted” that the caretaker furnish the applicant with the keys to the premises, on the understanding that same would be handed back that day. Counsel for the applicant argued that they are in possession of both sets of keys, which suggests that Mawale handed over both the original and a set of duplicates. This does not necessarily follow.

[11] The respondent requested the keys be returned on several occasions. The applicant sent an email to the Respondent on 19 March stating that he could not hand over the keys. The applicant relies on this email as evidence of its intention to exercise its builder’s lien. However, this is not stated. Mention is made that the applicant’s supervisor, Vusi has keys to the “office doors”. The refusal to hand over the keys to the “office doors” is refused pending receipt of the “completion certificates”.

[12] The Court is, accordingly, unable to find that the applicant was, at all material times, in peaceful and undisturbed possession of the property when the respondent prevented access thereto. Nor can it be found that the applicant was, at the time, exercising its lien.

[13] The version of the applicant is not such that the respondent’s version can be found to be “untenable” and “far-fetched”. The standard set by Harms DP in National Director of Public Prosecutions v Zuma7 is quite stringent as the applicant has to show that the version of the respondent is “clearly untenable.” This burden has not been successfully overcome by the applicant and as such there exists a material dispute of fact. The issue as to who was in possession of the keys to the property and, therefore, in symbolic possession of the property, remains in dispute and not resoluble, on the papers, in applicant’s favour.

[14] In the circumstances, I make the following order:

The order granted on the 2nd April is set aside.

The applicant is to pay the costs of this and the previous application.

___

Weiner J

Date of hearing: 3 May 2013

Date of judgment: 30 May 2013

Counsel for Applicant: Adv. A.R. Van Der Merwe

Attorneys for Applicant: Scholtz Attorneys

Counsel for Respondent: Adv.C Van Der Merwe

Attorneys for Respondent: Read Hope Phillips Attorneys

1 2009 (6) SA 266 (W)

2 [2009] ZASCA 1; 2009 (2) SA 277 (SCA).

3 Ibid [26].

4 Ibid.

5 Ibid.

6 NDPP V Zuma supra fn 2.

7 Supra, fn 1.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Oosthuizen v Mijs 2009 (6) SA 266 (W)

Case cited

National Director of Public Prosecutions v Zuma [2009] ZASCA 1; 2009 (2) SA 277 (SCA)

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.