Volschenk Insulation Converters (Pty) Ltd v Shorts Lifts (Pty) Limited (2009/34076) [2015] ZAGPJHC 138 (10 July 2015)

Volschenk Insulation Converters (Pty) Ltd v Shorts Lifts (Pty) Limited (2009/34076) [2015] ZAGPJHC 138 (10 July 2015)

The court found that the contract required delivery of all materials necessary for installation before the defendant became entitled to 90% of the contract price. The defendant failed to deliver essential items, making proper installation impossible. The defendant's cancellation of the contract was unjustified and...

Source-derived case information.

Citation
[2015] ZAGPJHC 138
Parties
Plaintiff: Volschenk Insulation Converters (Pty) Ltd; Defendant: Shorts Lifts (Pty) Limited
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2009/34076
Procedural Posture
Civil Trial / Final Judgment After Trial
Outcome
Judgment for the plaintiff on both claims; defendant's counterclaim dismissed with costs.
Judges
P Boruchowitz
Legal Topics
Contractual Interpretation, Reciprocal Obligations, Repudiation, Damages for Breach, Contra Preferentem, Mora Interest
Commercial and Corporate Civil Procedure Contractual Interpretation Reciprocal Obligations Repudiation Damages for Breach Contra Preferentem Mora Interest

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Volschenk Insulation Converters (Pty) Ltd

Plaintiff

Shorts Lifts (Pty) Limited

Defendant

Procedural Posture

Civil Trial / Final Judgment After Trial

  1. 1 What is the meaning and effect of the phrase '90% payable on delivery of materials to site' in the revised contract.
  2. 2 Did the defendant deliver all materials necessary for installation, thereby entitling it to payment of 90% of the contract price.
  3. 3 Did the defendant's cancellation of the contract constitute a wrongful repudiation.

Ratio Decidendi

The court found that the contract required delivery of all materials necessary for installation before the defendant became entitled to 90% of the contract price. The defendant failed to deliver essential items, making proper installation impossible. The defendant's cancellation of the contract was unjustified and constituted a repudiation. The plaintiff validly cancelled the contract by accepting the repudiation and was entitled to restitution of payments made, subject to return of materials in its possession. The plaintiff also proved consequential damages for additional accommodation costs incurred due to the breach, which flowed naturally and foreseeably from the defendant's failure...

Court Disposition

Judgment for the plaintiff on both claims; defendant's counterclaim dismissed with costs.

Orders

  • Judgment is entered against the defendant in favour of the plaintiff for payment of R283,988.58, payable against return of materials and equipment in the plaintiff's possession to which the defendant is entitled.
  • Interest on R283,988.58 at 15.5% per annum from 8 February 2008 to date of payment.