Webb and Others v South African National Roads Agency Ltd (09716/2010) [2012] ZAGPJHC 196 (19 October 2012)

Webb and Others v South African National Roads Agency Ltd (09716/2010) [2012] ZAGPJHC 196 (19 October 2012)

The court found that the respondent had complied with the interim order by constructing the agreed permanent concrete barrier, as confirmed by the applicants' own experts and attorneys. The applicants' subsequent introduction of new issues—noise, drainage, vibrations, and further demands—constituted a new cause of...

Source-derived case information.

Citation
[2012] ZAGPJHC 196
Parties
Applicant: Judith Mary Webb; Applicant: Investibility 38 (Pty) Ltd; Applicant: Jurgens Stephanus Bekker t/a Jurgens Bekker Attorneys; Applicant: Proximity Properties 206 (Pty) Ltd; Applicant: Ernest Bernadus Nel; Applicant: Good Night Guest Lodge CC t/a Good Night Guest Lodge; Respondent: South African National Roads Agency Limited
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
09716/2010
Procedural Posture
Urgent Application / Application to Discharge Interim Interdict
Outcome
Interim interdict discharged; punitive costs order against first to fourth applicants.
Judges
N F Kgomo
Legal Topics
Interim Interdict, Striking Out New Matter, Sanral Act, Costs Punitive, Road Safety Barriers, Delay in Prosecution
Civil Procedure Land and Property Administrative Law Interim Interdict Striking Out New Matter Sanral Act Costs Punitive Road Safety Barriers +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 20 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Judith Mary Webb

Applicant

Investibility 38 (Pty) Ltd

Applicant

Jurgens Stephanus Bekker t/a Jurgens Bekker Attorneys

Applicant

Proximity Properties 206 (Pty) Ltd

Applicant

Ernest Bernadus Nel

Applicant

Good Night Guest Lodge CC t/a Good Night Guest Lodge

Applicant

South African National Roads Agency Limited

Respondent

Procedural Posture

Urgent Application / Application to Discharge Interim Interdict

  1. 1 Whether the respondent complied with the interim order regarding construction of the concrete barrier.
  2. 2 Whether applicants were entitled to raise new matters in replying and supplementary affidavits.
  3. 3 Whether the interim interdict should be discharged due to delay and satisfaction of its terms.

Ratio Decidendi

The court found that the respondent had complied with the interim order by constructing the agreed permanent concrete barrier, as confirmed by the applicants' own experts and attorneys. The applicants' subsequent introduction of new issues—noise, drainage, vibrations, and further demands—constituted a new cause of action not contemplated in the original application. The applicants failed to institute further proceedings within the stipulated 60 days, instead prolonging the matter without justification. The court held that new matters raised in replying and supplementary affidavits were impermissible and struck them out. The interim interdict had become academic and its continued operation...

Court Disposition

Interim interdict discharged; punitive costs order against first to fourth applicants.

Orders

  • The rule nisi issued by Halgryn AJ on 20 March 2010 is discharged as the respondent has satisfied its terms.
  • First to fourth applicants are ordered to pay the costs of the application on an attorney and client scale, including costs of two counsel.