WJ Building & Civil Engineering Contractors CC v Umhlathuze Municipality and Another (4139/2013) [2013] ZAKZDHC 16; 2013 (5) SA 461 (KZD) (6 May 2013)

WJ Building & Civil Engineering Contractors CC v Umhlathuze Municipality and Another (4139/2013) [2013] ZAKZDHC 16; 2013 (5) SA 461 (KZD) (6 May 2013)

The court found that the applicant established a prima facie right to fair administrative action in the adjudication of the tender, and that the reasons advanced by the first respondent for awarding the contract to the second respondent were arbitrary and not based on objective criteria as required by the PPPFA and...

Source-derived case information.

Citation
[2013] ZAKZDHC 16
Parties
Applicant: WJ Building & Civil Engineering Contractors CC; Respondent: Umhlathuze Municipality; Respondent: PMPZ Construction CC
Court
Kwazulu-Natal High Court, Durban
Jurisdiction
South Africa
Case Number
4139/2013
Procedural Posture
Urgent Application / Interim Interdict Pending Review
Outcome
Interim interdict granted pending review; strict time limits imposed for review proceedings; costs reserved for decision in review.
Judges
Lopes
Legal Topics
Tender Review, Preferential Procurement Policy Framework Act, Interim Interdict, Internal Remedies Exhaustion, Balance of Convenience
Administrative Law Civil Procedure Tender Review Preferential Procurement Policy Framework Act Interim Interdict Internal Remedies Exhaustion Balance of Convenience

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

WJ Building & Civil Engineering Contractors CC

Applicant

Umhlathuze Municipality

Respondent

PMPZ Construction CC

Respondent

Procedural Posture

Urgent Application / Interim Interdict Pending Review

  1. 1 Whether the award of the tender to the second respondent complied with the 90/10 evaluation scoring system under the Preferential Procurement Policy Framework Act.
  2. 2 Whether the applicant lodged a valid objection within the time period prescribed by the Supply Chain Management Policy.
  3. 3 Whether the applicant is entitled to an interim interdict pending review of the tender award.

Ratio Decidendi

The court found that the applicant established a prima facie right to fair administrative action in the adjudication of the tender, and that the reasons advanced by the first respondent for awarding the contract to the second respondent were arbitrary and not based on objective criteria as required by the PPPFA and its regulations. The applicant lodged a valid written objection within the prescribed period, and the failure of the first respondent to provide adequate reasons or follow internal processes contributed to the delay. The applicant faces irreparable harm if the project proceeds before its objection is resolved, and has no adequate alternative remedy. The balance of convenience...

Court Disposition

Interim interdict granted pending review; strict time limits imposed for review proceedings; costs reserved for decision in review.

Orders

  • The applicant is directed to institute a review application against the proceedings relating to the evaluation and adjudication of tenders in respect of contract 8/2/1/151: Mzingazi Village Sewer : Phase 1 and the award of that contract, within five days of the date of this order.
  • The first respondent is directed to produce a record of the proceedings within ten days of delivery of the review application.