Download PDF

South Africa Ruling

South Gauteng High Court, Johannesburg

Wolfsberg Arch Investments (Pty) Ltd v Pentad Quantity Surveyors (Pty) Ltd (27254/2009) [2013] ZAGPJHC 72 (15 March 2013)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the plaintiff failed to prove damages arising from the defendant's breach of the consultancy agreement. The evidence presented by the plaintiff's managing director was vague and lacked specificity regarding the steps that would have been taken to avoid the cost overrun, the timing of such steps, and their impact on the budget and project costs. The court held that mere assertions without factual support do not establish causality or quantum of damages. Furthermore, the damages claimed, being the cost of the overrun, did not constitute recoverable loss as the plaintiff received corresponding value for the changes made. The Tswelena case was distinguished as it was decided on exception and involved different considerations. The court concluded that there were no reasonable prospects of success on appeal and refused leave to appeal.

Court disposition

Leave to appeal is refused with costs, including the costs of senior counsel.

Orders

  • Leave to appeal is refused.
  • Plaintiff to pay the costs of the application, including the costs of senior counsel.

02

Material facts

Parties

Wolfsberg Arch Investments (Pty) Ltd

Plaintiff Counsel: Adv AJ Daniels

Pentad Quantity Surveyors (Pty) Ltd

Defendant Counsel: Adv P Ellis SC

03

Procedural history

  1. Posture

    Leave to Appeal / Application for Leave to Appeal Following Judgment on Contractual Damages

04

Questions and positions

Legal issues

Party arguments

Applicant
The plaintiff argued that the unchallenged evidence of its managing director, McKenzie, established that steps would have been taken to manage the cost overrun had the defendant notified the plaintiff earlier, as required by the consultancy agreement. It was submitted that this evidence, together with the reasoning in the Tswelena case, was sufficient to prove patrimonial loss, as the plaintiff had no effective means to avoid the overrun once it became aware of it.
Respondent
The defendant contended that the plaintiff's evidence was vague and unsupported, failing to specify what steps would have been taken, when, and how these would have impacted the budget or project costs. The defendant argued that the damages claimed were not proven, as the plaintiff received corresponding value for the changes made, and the Tswelena case was not applicable since it was decided on exception and involved different considerations.

05

Court’s reasoning

  1. 01

    General principles of South African contract law

    Damages must be proven with sufficient evidence establishing causality and quantum; vague or unsupported assertions are insufficient.

  2. 02

    Wolfsberg Arch Investments (Pty) Ltd v Pentad Quantity Surveyors (Pty) Ltd [2013] ZAGPJHC 72

    A plaintiff cannot claim as damages the cost of changes for which corresponding value was received.

  3. 03

    Tswelena case (referenced in para 12 and 13 of main judgment)

    The relevance of precedent depends on the factual and procedural similarity; cases decided on exception may not be applicable to substantive proof of damages.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the plaintiff failed to prove damages arising from the defendant's breach of the consultancy agreement. The evidence presented by the plaintiff's managing director was vague and lacked specificity regarding the steps that would have been taken to avoid the cost overrun, the timing of such steps, and their impact on the budget and project costs. The court held that mere assertions without factual support do not establish causality or quantum of damages. Furthermore, the damages claimed, being the cost of the overrun, did not constitute recoverable loss as the plaintiff received corresponding value for the changes made. The Tswelena case was distinguished as it was decided on exception and involved different considerations. The court concluded that there were no reasonable prospects of success on appeal and refused leave to appeal.

Obiter and limits

  • The grounds for leave to appeal were neither clear nor precise, and the arguments advanced were described as flimsy.
  • The comparison to the Tswelena case was of academic interest only and did not assist the plaintiff's case.
  • The plaintiff's claim was not based on loss of a bargain but on the cost of the overrun, which was not recoverable in the circumstances.

Court disposition

Leave to appeal is refused with costs, including the costs of senior counsel.

  • Leave to appeal is refused.
  • Plaintiff to pay the costs of the application, including the costs of senior counsel.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Ruling

[2013] ZAGPJHC 72

NOT REPOTABLE

IN THE SOUTH GAUTENG HIGH COURT

(JOHANNESBURG)

CASE NO:27254/2009

DATE:15/03/2013

In the matter between

WOLFSBERG ARCH INVESTMENTS (PTY) LTD …....................................PLAINTIFF

and

PENTAD QUANTITY SURVEYORS (PTY) LTD.............................................DEFENDANT

Appeal-application for leave to appeal-consideration s arising-reasonable prospects of a successful appeal-absence of-leave to appeal refused.

J U D G M E N T

(LEAVE TO APPEAL)

VAN OOSTEN J:

[1] The unsuccessful plaintiff now seeks leave to appeal against that part of my judgment dealing with the proof of damages arising from the defendant’s breach of the consultancy agreement and the order non-suiting the plaintiff on its claim for contractual damages. The grounds in support of the application for leave to appeal as set out in the notice of application for leave to appeal are anything but a model of clarity or precision. Counsel for the plaintiff (who did not appear at the trial), however,confined his argument to two contentions, which Inow proceed to deal with.

[2] The first contention relies solely on the evidence of McKenzie, the managing director of the plaintiff, that he would have taken steps to manage the overrun, had he known of it at an earlier stage, which of course is the time the defendant in terms of the consultancy agreement, should have informed the plaintiff of the overrun. Counsel for the plaintiff emphasised the fact that his evidence on this score was not challenged and submitted that it indeed was sufficient to sustain the plaintiff’s damages. In the notice of application for leave to appeal the contention,in a somewhat diluted form, is articulated thus:

‘5. The court ought to have found that the applicant’s patrimonial loss, both on the reasoning of the court in the Tswelena case and on the evidence adduced before it, had been satisfactorily proven and that the applicant, by the time the loss sustained by it had come to its attention, had little if indeed any “space” within which to manoeuvre, that is, no effective means of avoiding the overrun and the loss sustained by it.”

The contention is flawed in its premise: the evidence relied on was nothing more than a vague unsupported proposition, or as counsel for the plaintiff preferred to refer to it, flimsy evidence, advanced by McKenzie. Seemingly absent from his evidence is firstly, any indication as to the nature of the “steps” the plaintiff would have taken, secondly, when that would have happened and, thirdly,and most importantly, how those “steps” would have impacted not only on the budget but also on the costs of the project as a whole. The mere suggestion made by McKenzie, in the absence of causality as to the damages allegedly suffered by the plaintiff, in my view, cannot be considered sufficient to prove damages.

[3] The second contention raised by counsel for the plaintiff concerned the applicability and relevance of the Tswelena judgment referred to in para [12] and [13] of my judgment. The comparison is nothing more than of academic interest. As stated in my judgment Tswelena was decided on exception and merely concerned the plaintiff’s case as pleaded where significantly different considerations apply. Furthermore, the plaintiff’s case in this matter, in any event, was not based on the loss of a “bargain”. The damages claimed is for the amount of the costs of the overrun on the basis of “had the defendant not breached the consultancy agreement and properly performed its obligations in terms of the consultancy agreement, the development could and would have been completed within the budgeted estimate”,as I have dealt with in paragraphs 10 and 11 of the judgment. The amount of the costs of the overrun cannot, on its own, constitute damages as the plaintiff has received corresponding value in the changes that were of necessity effected to the demising walls. In the absence of any factual support the notion of damages simply falls away.

[4] I am not persuaded that another court will reasonably come to a different conclusion concerning proof of damages. In the absence of reasonable prospects of a successful appeal, leave to appeal ought to be refused.

[5] In the result leave to appeal is refused with costs including the costs of senior counsel.

_____

FHD VAN

OOSTEN

JUDGE

OF THE HIGH COURT

COUNSEL FOR PLAINTIFF: ADV AJ DANIELS

PLAINTIFF’ ATTORNEYS: ANDREW MILLER & ASS

COUNSEL FOR DEFENDANT : ADV P ELLIS SC

DEFENDANT’S ATTORNEYS: GILDENHUYS MALATJIINC

DATE OF HEARING: 14 MARCH 2013

DATE OF JUDGMENT : 15 MARCH 2013

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Tswelena case (referenced in para 12 and 13 of main judgment)

Case cited

Wolfsberg Arch Investments (Pty) Ltd v Pentad Quantity Surveyors (Pty) Ltd [2013] ZAGPJHC 72

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.