Download PDF

South Africa Judgment

Labour Court Johannesburg

Workforce Group (Pty) Ltd v National Textile Bargaining Council and Another (J1186/11) [2011] ZALCJHB 57; [2011] 11 BLLR 1136 (LC); (2011) 32 ILJ 3042 (LC) (7 July 2011)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The application was struck from the roll due to lack of urgency, which was self-created by the applicant's delay in launching both the review and stay applications. The applicant failed to establish a prima facie right to interim relief, as it had an adequate alternative remedy by seeking postponement at the CCMA. The Labour Court reaffirmed its reluctance to intervene in uncompleted arbitration proceedings except in exceptional circumstances, emphasizing that such intervention undermines the expeditious and informal nature of labour dispute resolution. The applicant's prospects of success on review were found to be slim, as the demarcation dispute was clearly set out and the jurisdictional issues could be properly ventilated during arbitration. Costs were awarded against the applicant, but not on a punitive scale.

Court disposition

Application struck from the roll for lack of urgency; costs awarded against the applicant.

Orders

  • The application is struck from the roll due to lack of urgency.
  • The applicant is ordered to pay the first respondent's costs.

02

Material facts

Parties

Workforce Group (Pty) Ltd

Applicant Counsel: Bruce Jackson

National Textile Bargaining Council

Respondent Counsel: Mark Euijen

CCMA

Respondent

03

Procedural history

  1. Posture

    Stay Application / Urgent Application to Stay Arbitration Pending Review

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that the matter was urgent as the arbitration was scheduled to continue shortly and that the review application challenging the arbitrator's jurisdictional ruling was pending. It argued that without a stay, it would suffer irreparable harm by being forced to proceed with arbitration before the review was determined. The applicant claimed the demarcation application was vague and embarrassing and that the CCMA lacked jurisdiction absent prior conciliation.
Respondent
The first respondent argued that urgency was self-created due to the applicant's delay in launching both the review and stay applications. It asserted that the applicant was attempting to delay the demarcation proceedings and that the Labour Court should not intervene in uncompleted CCMA arbitrations except in exceptional circumstances. The respondent maintained that the applicant had an alternative remedy by seeking postponement at the CCMA and that the demarcation dispute was clearly set out.

05

Court’s reasoning

  1. 01

    Trustees for the time being of the National Bioinformatics Network Trust v Jacobson and Others (2009) 30 ILJ 2513 (LC)

    The Labour Court should be slow to intervene in uncompleted CCMA arbitration proceedings, except in exceptional circumstances, to preserve the expeditious and informal nature of labour dispute resolution.

  2. 02

    Jiba v Minister of Justice and Constitutional Development [2005] ZALC 15; [2009] 10 BLLR 989 (LC)

    Applications to review and set aside rulings made in uncompleted proceedings are undesirable except in exceptional circumstances.

  3. 03

    EOH Abantu (Pty) Ltd v CCMA & others (2010) 31 ILJ 937 (LC)

    The expeditious resolution of labour disputes is not served by a piecemeal approach; parties should allow arbitration to run its course before seeking court intervention.

  4. 04

    Southern Sun Hotel Interests (Pty) Ltd v CCMA & others (C255/09; C362/09; unreported, 21 June 2011)

    A party seeking interim relief must show a prima facie right, absence of adequate alternative remedy, apprehension of irreparable harm, and that the balance of convenience favours it.

06

Ratio, limits and disposition

Ratio decidendi

The application was struck from the roll due to lack of urgency, which was self-created by the applicant's delay in launching both the review and stay applications. The applicant failed to establish a prima facie right to interim relief, as it had an adequate alternative remedy by seeking postponement at the CCMA. The Labour Court reaffirmed its reluctance to intervene in uncompleted arbitration proceedings except in exceptional circumstances, emphasizing that such intervention undermines the expeditious and informal nature of labour dispute resolution. The applicant's prospects of success on review were found to be slim, as the demarcation dispute was clearly set out and the jurisdictional issues could be properly ventilated during arbitration. Costs were awarded against the applicant, but not on a punitive scale.

Obiter and limits

  • The court criticized the applicant's leisurely approach to launching the review and stay applications, noting that urgency was self-created.
  • The court reiterated that intervention in part-heard CCMA proceedings by way of interdict should be limited to exceptional circumstances.
  • The court noted that the applicant could have sought postponement at the CCMA, which is a clear alternative remedy.

Court disposition

Application struck from the roll for lack of urgency; costs awarded against the applicant.

  • The application is struck from the roll due to lack of urgency.
  • The applicant is ordered to pay the first respondent's costs.

Source and reliance status

Labour Court Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Labour Court Johannesburg

Judgment

[2011] ZALCJHB 57

REPUBLIC OF SOUTH AFRICA

Reportable

Of interest to other judges

THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG

JUDGMENT

CASE NO: J 1186 / 11

In the matter between:

WORKFORCE GROUP (PTY) LTD …...........................................APPLICANT

AND

NATIONAL TEXTILE BARGAINING COUNCIL …........FIRST

RESPONDENT

CCMA …....................................................................SECOND

RESPONDENT

Heard: 6 July 2011

Delivered: 7 July 2011

judgment

STEENKAMP J

Introduction

This is an urgent application brought during the July court recess to stay arbitration proceedings under the auspices of the CCMA (the second respondent) due to continue on 13 July 2011.

Background

The first respondent, the National Textile Bargaining Council, applied to the CCMA in terms of s 62 of the Labour Relations Act1 on 9 February 2011 to determine a demarcation dispute. It sought a demarcation that the whole or part of the Workforce Group (Pty) Ltd falls within the textile sector; and, to the extent that it does, that it is obliged to give effect to the Main Collective Agreement governing that sector.

The Workforce Group (the applicant in these proceedings) is a temporary employment service as defined in s 198 of the LRA. It

supplies labour to a number of entities in the textile sector.

The matter was set down for arbitration in Ladysmith, KwaZulu-Natal on 9 May 2011. The applicant raised two points in limine: one pertaining to the CCMA’s jurisdiction to hear the dispute; and the other raising an exception, alleging that the application for demarcation was vague and embarrassing. The jurisdictional point was based on an argument that the dispute first had to be conciliated and that the CCMA did not have jurisdiction to arbitrate absent conciliation.

Although he did not give written reasons for his ruling, the arbitrator dismissed both points in limine on the same day, ie 9 May 2011.

The deponent to the founding affidavit, Rian Ferreira (the applicant’s Group Legal Director) says, somewhat coyly, that

“subsequent to the proceedings in Ladysmith on 9 May 2011,” the applicant launched an application in this Court to review and set aside the arbitrator’s ruling. What he does not say, is that the review application was only launched on 15 June 2011; and that this application to stay the continuation of the arbitration proceedings, pending the review application, was only delivered on 29 June 2011.

Urgency

The ruling that forms the subject matter of the review application was made on 9 May 2011. It is now almost two months later. Yet the applicant wishes this application to be dealt with on an urgent basis outside of the court term.

The applicant submits that the matter is urgent because it advised the Council’s attorneys on 1 June 2011 that it was “in

the process of applying for review” and that, if no agreement could be reached, it would apply for the arbitration to be stayed pending the outcome of the review application. In the same letter of 1 June 2011, though, the applicant says that it and its counsel are available from 13-15 July 2011, should the CCMA “...still wish to have the matter set down for arbitration.”

The applicant did nothing further, other than delivering the review application on 15 June 2011 – ie two days short of the prescribed six-week time limit – until 23 June 2011. On that day, its attorneys sent a letter marked “urgent” to the Council’s attorneys, asking them to advise it by the next day “...whether your client would be amenable to postpone the arbitration set down at the National Textile Bargaining Council, Durban, on 13 July 2011, pending the outcome of our client’s review application.”

The council’s attorneys responded the next day, declining an agreement to postpone; alleging that the applicant was merely

seeking to delay the demarcation proceedings, and bringing the applicant’s attention to the fact that this Court is opposed

to Bargaining Council and CCMA rulings being challenged in media res, as set out in Goldfields Mining SA (Pty) Ltd (Kloof Gold Mine) v CCMA & others.2

On 29 June 2011 the applicant delivered this urgent application.

The applicant indicated to the Council’s attorneys on 27 May 2011 that it was “in the process of applying for review”;

yet the review application was delivered in the nick of time, despite the generous six week period allowed for in s 145(1) of the LRA; and the urgent application to stay the arbitration proceedings was delivered more than seven weeks after the arbitrator made his ruling, and almost a month after the applicant indicated its and its counsel’s availability to continue with the arbitration on 13 July 2011.

This is a prime example of self-created urgency. The applicant did not act with any expedition – in fact, even the review

application which underlies the basis of bringing this application was dealt with in a fairly leisurely fashion, and the application – comprising an affidavit of nine pages – was barely delivered in time. The applicant then sought to have this matter heard out of term time on an urgent basis. It has not established sufficient grounds for urgency.3 The matter should be struck off the roll for this reason alone.

But aside from my view on urgency, I would not have been inclined to grant the relief sought on the merits. I will provide brief reasons for my views in this regard as well.

The merits

In order to obtain the relief sought, the applicant has to fulfil the requirements for interim relief, i.e. a prima facie right; the absence of an adequate alternative remedy; the apprehension of irreparable harm; and an indication that the balance of convenience

favours it.

Alternative remedy

The applicant has a clear alternative remedy, namely to apply for a postponement at the CCMA pending the finalisation of the review application. In terms of CCMA rule 23, an arbitration may be postponed by agreement between the parties; or by application and on notice to the other parties. In this case, the applicant has made no effort to apply for a postponement at the CCMA. There is nothing in the CCMA rules preventing the arbitrator from postponing the continuation of the arbitration pending the finalisation of the review application.

I have recently expressed the opinion that, in uncompleted proceedings, such as the current one, the applicant should have

attended the part heard arbitration in order to finalise the matter. Had it still being dissatisfied, it could have taken the arbitration

award on review. Alternatively, it could have applied to the arbitrator already hearing the matter to postpone the hearing

pending the outcome of the review application of his jurisdictional ruling. Had the arbitrator refused, the CCMA would have been functus officio. The applicant could then have applied to the Labour Court to review and set aside the arbitrator's refusal to postpone.4

Prospects of success on review.

In order to establish a prima facie right for the urgent interim relief sought, the applicant has to show that this is one of those exceptional circumstances where the court should intervene in uncompleted arbitration proceedings. The numerous cases dealing with the stay of a writ of execution pending the review proceedings to which Mr Jackson, for the applicant referred, are not helpful in cases such as these were the applicant seeks to stay the continuation of arbitration proceedings.

Mr Jackson referred me in his oral argument to the case of EOH Abantu (Pty) Ltd v CCMA & another.5 He did so in order to show that this court has jurisdiction to review a jurisdictional ruling; and that, in that case, the court

granted an urgent application to stay a further arbitration proceedings before the CCMA pending the outcome of a review application. What he did not refer me to, is the subsequent judgement of Cele J involving the same parties where the earlier judgement was not followed.6 In the 2010 judgment, Cele J had the following to say7, and I agree with him:

“[E]ven if the court finds that the decision of the [CCMA] is one which could be reviewed, the appropriate remedy is to discharge the interdict against the [CCMA], because:

The expeditious resolution of labour disputes is not served by a piecemeal approach such as the one adopted by the applicant in this matter. Had the issue of jurisdiction properly been considered by the arbitrator after the benefit of hearing oral

evidence on both the merits and the jurisdictional issue, then the Labour Court would have been saved [sic] on two occasions...

The applicant will suffer no prejudice should the matter proceed to arbitration. It will be able to raise the jurisdictional issues. It would like to, and the Commissioner will be able to weigh evidence on the issue (after hearing all the evidence as this is an issue which is linked to the merits) and give a binding award. At that stage, would any party be dissatisfied, it will be able to seek to review the award in accordance with the LRA. This will mean the Labour Court will have the benefit of the CCMA's decision and will not become involved prematurely in matters. This will prevent a flood of similar applications."

In the Southern Sun case8, I aligned myself with the sentiments expressed by Van Niekerk J in Trustees for the time being of the National Bioinformatics Network Trust v Jacobson and Others9 regarding the practice of seeking the court to intervene in part heard CCMA proceedings by way of interdict:

"There are at least two reasons why the limited basis for intervention in criminal and civil proceedings ought to extend to uncompleted arbitration proceedings conducted under the auspices of the CCMA, and why this court ought to be slow to intervene in those proceedings. The first is a policy related reason – for this court routinely to intervene in uncompleted arbitration proceedings would undermine the informal nature of the system of dispute resolution established by the Act. The second (related) reason is that to permit applications for review on a piecemeal basis would frustrate expeditious resolution of labour disputes. In other words, in general terms, justice would be advanced rather than frustrated by permitting CCMA arbitration proceedings to

run the course without intervention by this court.”

As the court pointed out in Bioinformatics, this conclusion was recently underscored by the Constitutional Court in Commercial Workers Union of SA v Tao Ying Metal Industries and Others.10

Similarly, in Jiba v Minister of Justice and Constitutional Development11, this Court stated:

“Exceptional circumstances aside, it is undesirable for this court to entertain applications to review and set aside rulings made in uncompleted proceedings.”

For this reason also, I would have dismissed the application for interim relief pending the review application.

Furthermore, the allegation that the applicant did not know what case to meet appears to be baseless. The demarcation dispute is clearly set out in the application to determine the dispute in the prescribed form LR 3.23. On this ground also, the applicant’s

prospects of success are slim and it has not made out a prima facie right.

Costs

Mr Euijen, for the Council, submitted that this application was brought merely to delay the demarcation dispute further; that it was part of a pattern of delaying tactics; and that costs should be awarded on a punitive scale.

Although the application is, in my view, without merit and did not warrant an urgent application during the recess, there is not enough evidence on the papers before me to bear out the contention that the application forms part of a pattern of delaying tactics. In law and fairness, costs should follow the result; however, I do not agree that it warrants a punitive costs order.

Ruling.

The application is struck from the roll due to lack of urgency. The applicant is ordered to pay the first respondent's costs.

_______

Anton Steenkamp

Judge

APPEARANCES

APPLICANT: Bruce Jackson

Instructed by Hunts (inc Borkums), Parktown.

FIRST RESPONDENT: Mark Euijen

Instructed by Cheadle Thompson & Haysom, Johannesburg.

1Act 66 of 1995 (“the LRA”)

2(2010) 31 ILJ 371 (LC) at 380.

3For this court’s approach to urgency, see, for example, Chiloane v Nhluvuto Agricultural Project & others [2000] 4 BLLR 392 (LC).

4See Southern Sun Hotel Interests (Pty) Ltd i.r.o. Southern Sun Waterfront Hotel v CCMA & others (C255/09; C 362/09; unreported, 21 June 2011).

5(2008) 29 ILJ 2588 (LC).

6EOH Abantu (Pty) Ltd v CCMA & others (2010) 31 ILJ 937 (LC).

7At 942H – 943C in para [16].

8Supra footnote 4.

9(2009) 30 ILJ 2513 (LC) at paras 3 and4.

10(2008) 29 ILJ 2461 (CC) at paras 62-5 (per Ngcobo J).

11[2005] ZALC 15; [2009] 10 BLLR 989 (LC) para [11].

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Goldfields Mining SA (Pty) Ltd (Kloof Gold Mine) v CCMA & others (2010) 31 ILJ 371 (LC)

Case cited

Chiloane v Nhluvuto Agricultural Project & others [2000] 4 BLLR 392 (LC)

Case cited

Southern Sun Hotel Interests (Pty) Ltd v CCMA & others (C255/09; C362/09; unreported, 21 June 2011)

Case cited

EOH Abantu (Pty) Ltd v CCMA & another (2008) 29 ILJ 2588 (LC)

Case cited

EOH Abantu (Pty) Ltd v CCMA & others (2010) 31 ILJ 937 (LC)

Case cited

Trustees for the time being of the National Bioinformatics Network Trust v Jacobson and Others (2009) 30 ILJ 2513 (LC)

Case cited

Commercial Workers Union of SA v Tao Ying Metal Industries and Others (2008) 29 ILJ 2461 (CC)

Case cited

Jiba v Minister of Justice and Constitutional Development [2005] ZALC 15; [2009] 10 BLLR 989 (LC)

Case cited

Labour Relations Act 66 of 1995

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.