Zanbuild Construction (Pty) Ltd v Absa Bank Limited and Others (2083/2009) [2009] ZAWCHC 233 (19 June 2009)

Zanbuild Construction (Pty) Ltd v Absa Bank Limited and Others (2083/2009) [2009] ZAWCHC 233 (19 June 2009)

The court held that the guarantees must be interpreted in conjunction with the main construction contracts. The department was not entitled to call up the full amount of the guarantees without quantifying the amount due and payable as a result of a breach by the applicant. The guarantee's wording required that only...

Source-derived case information.

Citation
[2009] ZAWCHC 233
Parties
Applicant: Zanbuild Construction (Pty) Ltd; Respondent: Absa Bank Limited; Respondent: Minister of Transport and Public Works: Provincial Government of the Western Cape; Respondent: Head of the Department of Transport and Public Works: Provincial Government of the Western Cape
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
2083/2009
Procedural Posture
Urgent Application / Final Relief Sought After Interim Interdict; Opposed Motion
Outcome
Application granted. Interdicts issued preventing payment under the guarantees unless the department evidences a quantified amount due and payable on the relevant date.
Judges
W J Louw
Legal Topics
Construction Guarantees, Performance Bonds, Interdictory Relief, Contractual Interpretation
Commercial and Corporate Civil Procedure Construction Guarantees Performance Bonds Interdictory Relief Contractual Interpretation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Zanbuild Construction (Pty) Ltd

Applicant

Absa Bank Limited

Respondent

Minister of Transport and Public Works: Provincial Government of the Western Cape

Respondent

Head of the Department of Transport and Public Works: Provincial Government of the Western Cape

Respondent

Procedural Posture

Urgent Application / Final Relief Sought After Interim Interdict; Opposed Motion

  1. 1 Whether the department was entitled to call up the full amount of the construction guarantees issued by ABSA.
  2. 2 Whether the guarantees had lapsed due to extensions of the completion date without new guarantees being requested.
  3. 3 Whether the department complied with the procedural requirements for claiming under the guarantees.

Ratio Decidendi

The court held that the guarantees must be interpreted in conjunction with the main construction contracts. The department was not entitled to call up the full amount of the guarantees without quantifying the amount due and payable as a result of a breach by the applicant. The guarantee's wording required that only amounts 'owing and due' on the expiry date of the notice of withdrawal could be claimed. Since the department neither alleged nor established any quantified claim due on the relevant date, it was not entitled to recover any part of the guaranteed amounts. The guarantees did not operate as unconditional on-demand bonds in the circumstances of this case.

Court Disposition

Application granted. Interdicts issued preventing payment under the guarantees unless the department evidences a quantified amount due and payable on the relevant date.

Orders

  • The Department of Transport and Public Works in the Provincial Government of the Western Cape is interdicted from seeking payment from ABSA under the guarantees unless it evidences that such amount was due and payable on 28 September 2008 under the main construction agreements.
  • ABSA is interdicted from paying out any amount under the guarantees unless the department evidences that such amount was due and payable on 28 September 2008 under the main construction agreements.