Professional case brief
Research organized from the available case record
01
Holding and result
Ultimate Security Tanzania Limited is liable for compensation to Tanzania Railways Limited for losses due to theft at Moshi and Dar es Salaam, as the security company failed to perform its contractual duties or was negligent, with liability capped as per contract terms and subject to insurance indemnification.
Court disposition
Plaintiff liable for compensation and indemnification; Defendant's counterclaim partially upheld.
Orders
- Plaintiff to process insurance indemnification for Defendant's losses of THz 23,326,000 and USD 277,186.
- Plaintiff to pay compensation to Defendant, either THz 50,000,000 or 70% of total loss, whichever is less, offset against unpaid invoices.
- No interest payable to either party.
- Plaintiff to bear costs of the suit.
02
Material facts
Parties
Ultimate Security Tanzania Limited
PlaintiffTanzania Railways Limited
DefendantAmounts and remedies
- Outstanding Unpaid Invoices as at February 2012: TZS 1,369,270,399.01
- Preliminary Decree Paid: TZS 639,067,715
- Disputed Claim After Preliminary Decree: TZS 815,880,710
- Loss at Moshi: TZS 23,326,000
- Loss at Dar Es Salaam Supplies Office: USD 277,186
- Compensation Cap Per Contract: TZS 50,000,000
03
Procedural history
Posture
Commercial Case / Final Judgment
04
Questions and positions
Legal issues
- 01
Whether materials were stolen at Moshi and Dar es Salaam Supplies Offices
- 02
What was the cost of the materials stolen
- 03
Who is responsible for the stolen materials
- 04
Whether the Defendant is entitled to compensation/indemnification
Party arguments
- Applicant
- Plaintiff claims outstanding payment for security services and denies liability for stolen goods, arguing lack of proof for claimed losses and asserting Defendant's negligence contributed to theft.
- Respondent
- Defendant disputes claimed amounts, asserts contract ended earlier, acknowledges partial payment, and counterclaims for compensation for stolen/lost property at Moshi and Dar es Salaam, alleging Plaintiff's negligence.
05
Court’s reasoning
Legal principles
- 01
Clause 4.1 of Security Agreement
Liability for loss or damage caused by negligent or intentional acts of the security company, limited to THz 50,000,000 or 70% of value of loss, whichever is less, over and above insurance compensation.
- 02
Clause 3.1 of Security Agreement
Duty to guard and protect client property from theft, burglary, vandalism, looting, arson, damage or undesirable acts.
06
Ratio, limits and disposition
Ratio decidendi
Ultimate Security Tanzania Limited is liable for compensation to Tanzania Railways Limited for losses due to theft at Moshi and Dar es Salaam, as the security company failed to perform its contractual duties or was negligent, with liability capped as per contract terms and subject to insurance indemnification.
Obiter and limits
- Plaintiff must process insurance claims for Defendant's losses.
- No interest is payable to either party.
- Costs of the suit are to be borne by the Plaintiff.
Court disposition
Plaintiff liable for compensation and indemnification; Defendant's counterclaim partially upheld.
- Plaintiff to process insurance indemnification for Defendant's losses of THz 23,326,000 and USD 277,186.
- Plaintiff to pay compensation to Defendant, either THz 50,000,000 or 70% of total loss, whichever is less, offset against unpaid invoices.
- No interest payable to either party.
- Plaintiff to bear costs of the suit.
Source and reliance status
TZHC · 4 September 2015
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
TZHC
Judgment· 4 September 2015
- -· '• . ' ·( ·,;. - ' ·]N THE:HIGH COURT OF·T.ANZANIA·-·- (COMMERCI/(L D.IVISION)
AT DAR ES SALAAM COMMERCIAL CASE NO.
31. OF 2012 ULTIMATE SECURITY' TANZANIA LIMITED ............................................ PLAINTIFF
VERSUS TANZANIA RAILWAYS LIMITED ..... : ................ DEFENDANT
JUDGMENT Mansoor, J: Date of Judgment- 4 TH SEPTEMBER 2015 The Plaintiff's claim against the Defendant is for the sum of THz 1,455,948,416.02 being the balance as at 13 th March 2012 due from the Defendant to the Plaintiff in respect of· Guards Services provided by the Plaintiff to the Defendant l .. inclu$1ve, of,int~rests .ch.arges,arising Jrom .,delayed paym.en'.t$~:,; • ,' .. • ::. • • • • • • + • • • The· Plaintiff alleges . . that . they entered into an agreement with . the . Defendant on . 30 th July 2009 for prov1s1on of guard/ sec11rity services, and the Plaintiff has availed the security guards ·to the Defendant. It is alleged by the Plaintiff in its plaint that -the Defendant has neglected or failed to · hono1:1r the payments for the services. The Plaintiff has filed in· Court a statement of accounts outlining the Defendant's i1;1debtedness and the unpaid invoices. To the above. claims, the Defendants filed a written statement ·of defence, and a counterclaim. In their written statement of . . defence, the Defendants disputed the amount of claim, and also disputed the period of the contract stating that th~ Plaintiffs contract ended on 29 th February 2012. The Defendants claims that the unpaid balance as at the end on the· contract, 1.e. on 29 th February 2012 was THz 1,369,270,399.01. In their defence, the Defendant annexed a letter dated 7 th February 2012, and
marked as ·annexlli"e D3 to the written statement of defence, this letter is from the 2 1. August 2011, this letter"provides as· follo.ws: PAYMENT PLANS·FOR OUTSTANDING BALANCE We acknowledge receipt of your letter ref. JFY / JFY / 082511- 283LET dated 26 th August 2011 on clearance of outstanding balance of THz 592,565,898.41 in your favour. In the absence of any analysis based on invoice numbers, we are unable to know whether recent payments·have been taken into account. We request you to provide· such details to facilitate reconciliation. Our balance slightly differs with yours." Taking due consideration of the results of the reconciliation as stated above, TRL will endeavour to clear the outstanding balance by 30 th November, 2011 from our own source of funds. We therefore kindly request you to extend the contract." Yours sincerely . - Ag. Managihg,::director- . Also. in a letter dated 24 th F~bruary ,2012, (this letter 1s annexed to the written statement of defence as Annexure D2), the Defendants are writing to the Plaintiff accepting the termination of the agreement and . asking the Plaintiff to remove all the guards from the Defendants premises on J st March 2012, and handing over. This letter also acknowledges the . outstanding debt and has said tha,t the government has a . provision- of THz 795,220,083 to be ·paid to the Plaintiff, and promised to settle the amount as
soon as possible. They also asked the Plaintiff in this letter to submit the final invoices for reconciliation. The Defendant also annexed a report and marked as Annexure D 1 to the written statement of defence, showing and acknowledging the outstanding amo_unt of indebtedness of THz 1,369,270,399.01 as at February 2012. This is"" pleaded in paragraph 3 of the Defendant's written statement of defence. ::; -. In the D_efendant's counter claim, the Defendant i& ·claiming against the Plaintiff compensation for the stolen/lost property at Moshi . station during the. month · of . September. 201J amounting to THz 286,737,084, and also they , claim compensation for the stolen/lost property at the Dar es · Salaam Chief Supplies office on 12 th July 2011 and 11 December 2011 amounting to US$ 277,166. The total amount in the counterclaim, as per the Consent Decree of 5 th Noverriber 2012 is THz ·s15,880,710, thus the Court had on 5 th November 2012, entered a Preliminary Decree of THz 639,067,715.00 in favour of the Plaintiff, and this amount was paid by the Defendant in satisfaction of the·· , , Preliminary Decree. Therefore out of the acknowledged amount of THz 1,369,270,399.01, the amount of THz 639,067,715.00 was already · paid. The disputed claim 1s now THz 815,880,710.00, as in the counter claim. . . . :-:__ , · T,he:Pteliminary- Decree erttered by:the Court on S th ''Novemhet ·
·::: ·;:':: ·' .-\>:~: 2012, resolved issues No.;-xL and 2 of the_ issues framed by the Court, and dete_rmined in its entirety the cl_aims by the Plain~iff .. . . . . . . . . . in its· plaint. There is no dispute· as to whether there· was an agre~ment between the parties, ,and there was no dispute that the outstanding unpaid invoices as at February 2012 was THz 1369,270,399:01. The issues that remained to be determined by this Court are those issues arisen from the counterclaim, i.e. whether materials were stolen at Moshi and Dar es Salaam Supplies Offices, what was the cost~ of the materials stolen, and who is responsible Ior ·the stolen materials, and ~hat is . . .. the amount of compensation, if any, the Defendant is entitled for the stolen materials.
1. Whether the materials were stolen at Moshi and Dar · es Salaam Supplies Offices: The Defendant claims that there was theft occurred in- Moshi during the month of September 2011, and the value of _the . I stolen goods amounts to THz 286,737,084. To prove this the 6 j. • I ' • • counter-clai~. ,Annexµre D4, a letter from the Defendarit to the. Plaintiff dated 27 th February 2012, asking fo~ compensation of stolen property ·at CXR-BCB Moshi amounting>to THz 285,737,084, and supplies office at Dar es Salc~.am valued at US$ 277,156. This letter gave the description, quantity and cost in THz of the ·materials stolen at CXR-BCB Moshi o~ 5 th September 2011. This letter explains that there was an inspection carried out on 8 / 09/2011, and the staff of the Plaintiff were involved .. Annexure DS to the counterclaim, a letter from the Defendant to the Principal Protection Office, dated 08/09/2011, explains, and confirms the theft having occurred, it states as follows: "nimep0kea ·taarifa ya tukio la wizi tarehe 05 / 09/2011 kutoka · kwa msimamizi wa CXR Moshi ndugu Mshanga. Tumekwenda kwenye tukio hilo- tukiongozana na viongozi wa polisi Mo~hi pamoja na viongozi wa ULTIMATE SECURITY 7 . . ...Moshi na, Arusha., _Baad§l ya. kufi~a ·.tulikuta- kweli-" behewa limevunjwa na mali za shiFika zimeibiwa." The Plaintiff denies the cJaim for compensation for the stolen goods saying that there is
no proof that all the listed items in annexure D4 referred herein above have been stolen but they are actually either still in possession of.the Defendant or were removed by RITES. They also deny to accept liability of the lost/stolen goods saying that the staff of the Defendant were negligent, leading to theft in Moshi as well as in Dar es Salaam. The Plaintiff however accepts that they were involved during the inspection carried out in 7 th September 2011 but they deny to have acknowledged that the list of the goods stolen were as that shown in · annexure D3. They claim that the list was prepared by the Defendant after the inspection. The Plaintiff says the value of the stolen items at Moshi was only THz 23, 326,000, and that this is the amount that was reported to the police, and the amount shown in the court Gase, as well as the letter to the police from the Defendant listing the missing items and the value is shown to be of THz 8 __,) \ ,;-•- • - -~ - "• I~ • - ., ,.. • - ~ • •• ~ •• '.! ~_.:: • • /• J_ -.• ·• ...... -· . ' ,.. , . ... - ,23,,1326-,'000-~.iionly;:/;T-he··· Plaintiff, prod,uced lh · Gou.rt ·-· Exh\ :P9',' 0 · which is a letter dated 30 th November ; 2011 ,:: from the Defendant to· the Head of Police, Railway Post, Moshi, giving _ the value of the items stolen to be THz 23,326,000. This letter was written by Eng. A.M Ngaliga, District Mechanical Engineer of
the Defendant. Detective Corporal Franco Mwafongo was . recalled as a witness to specifically testify on this letter. He actually testified that he worked as a police at Moshi Railway .. post since 2008 to 2014, and he acknowledged that Exhibit P9 is a report of theft occurred at CRX Area Moshi, and that he went to inspect the scene of crime, and that there was no breaking, but it was the staff of the Defendant using the master key, who were suspected to be involved in stealing. He however confirmed that _there was theft occurred. This police officer recognised this letter and confirmed that the value of the stolen item in Moshi were THz 23,326,000. R_~garding the stolen items in Dar es Salaam Supplies Office, the Plaintiff denies_ that all "'the items listed were actually stolen. They say some of the items were removed by the former 0 ./ rµan,agem~nt :of the company -i:e; RF:f:ES, befOre-'hattdirtg-thenf·· ·' >· -·-:-\ back to the; Defendant, and the value of the missing items is as confirmed in the joint report of July 2011, which is US$ - -' 184,698. The Pla,intiff claims that the missing items were taken back to India by RITES. The Plaintiff argues that they cannot be held responsible for the theft that occurred before the items were entrusted to them. They seem to agree that they were entrusted to guard the locomotives· during the period from 12 July 2011 to 11 December
2011, and the estimated value of the loss is US$ 92,458, and that they cannot be held responsible for the- theft that occurred before · they were entrusted to guard the locomotives, and that the·· Report of 11 July 2011 was for the period before the locomotive w,ere entrusted to them. The Plaintiff•denies that the locomotives do not belong to the Defendant and so they cannot have any claim over them. From the above, it is confirmed that there were materials stolen at Mos.hi and Dar es Salaam, Supplies Offices. 10 i\t.. _,,J·,-~,...;:,._",......,~----~~-_.,._---~,._...--..,_~ ,.,~..- .. ~.........-...-.,;_.,,.,,,..,_.,.... -,.-·#-..,_-.,..,.·~~•.,.....,.-..,. . ...,..,.~.--,..;"',._"" _.. ....,.,.._,.,.,~,~~---,...-~,.M..,•,~· .. - .. ,,,,.,--'it.r."•1,_-.," .·~• • ••'','T ,-u.P,..•·ti,.:.~-..•~W-"'""'"'"•' !•-~~o:;-~~r:~.u.l,..,.._~~~-"1;"';~...,..,.-.~··,t··-,-,' ... The Defendant claims that the mater.ials stolen at Mosh:i ·on 5 th Nov~rp.ber-~201 lis THz 286,737;084 as evidenced in Annexure D4 and DS. to the counterclaim. The Defendants claims that. the value of the items stolen at Dar es Salaam supplies office is US$ 277,166 . .. For the theft of materials at CXR BCB Moshi on 5 th September 2011, I shall.refer to a letter by the Defendant to the Principal Protection Officer - Moshi dated 08 / 09/2011. This letter was tendered by the Defendant and admitted as Exh D 1
collective. In this letter the Protection Assistant Moshi Mr A.B Kazungu is writing to the ~iincipal Prot€ction Office, Dar es Salaam, stating that after being notified of the theft that occurred on 5 th September 2011 at CXR Moshi, he checked with the Head of CXR Mr A Mshanga and that Mr Mshanga did not know of the list of.items that were actually stolen. Paragraph 3 of this letter reads as follows; 11 ",.p~ada. .ya ,ku,cl).~.ki, ~qye, ·Kiongozi--,va CXI<· ndugu ,A -Mshanga , kuwa ngazi. tatu za aluminium adder (3) zimeibiwa. Kwa kuwa ; ' b~hewa hilo · limeonyesha lilikuwa · na vitu vingj- baada ya kumuhoji msimamizi huyo ndugu A Mshanga -alisema kuwa. yeye baadhi ya vitu vya CXR havij~i ...... hivyo nakushauri kama kiongozi wangu wasiliana na DMEMoshi- Tanga atumie mafundi wa CXR wanaofahamu vifaa hivyo ili tupate uhakika." On 25 th October 2011, Mr J M P Syaizyagi, the Chief Design Draughtsman of the Defendant is writing to the Chief of Finance of the Defendant, giving the cost of machinery and equipment stolen at CXR BCB at - Moshi to be THz 285,737,084, and the letter dated 27 th February 2012 from the Defend~t to the Plaintiff (Exh D3 collective), ·giving the value of the stolen items in Moshi to be THz 285,737,084 states at the second page immediately after the list that the report of 8 th September 2011 of which the staff of the Plaintiff were involved is attached. The
only report of 8 th SeP,tember 2011 attached to the letter of 27 th February 2012, is the letter dated 08 September 2011 from Mr A B Kazungu Protection Assistant l2 . . ,;; ' c:.: .· :;:l\1osb:i caddtessed·'.to··rr61:tre · Prirtdphl,:iP.r:-ofe,ctiofl · Offic~; -t)ar' ··es·~-:· _:·· ·. ~l l:,\ . . . . N Salaam, which.I have t:J.'uoted ·above, basically statirig that Mr A. -: Mshanga, the head of CRX Moshi did not know the. ite'ms whioh were stolen . on 5th September 20 Ll. In this· I'm inclined to helieve Exh P.9 dated 30 th November 2011 tendered by the _Plaintiff and verified by Detective Corporal Franco Mwafongo, . written by Engineer A. M Ngalinga District Mechanical Engineer of the Defendant that the value of the stolen items in Moshi is THz 23,326,000. It should be· noted that Detective Corporal Franco· Mwafongo was present during the inspection ·carried out at CXR-BCB Moshi as his name also appears in the letter' written by Mr A. B Kazungu Protection Assistant Moshi addressed to the Principal Protection Office, Dar es Salaam. The others who were involved in the inspectioh and· verification of the items lost were, as mentioned in the letter written by Mr A. B Kazungu Protection Assistant Moshi - addressed to the Principal Protection Office, Dar es Salaam, on _98 th September 2011; and they are: • Head of Police Moshi- S / SGT Amiri 13 . .,,-- . ;:. J-~-i,~H-':_~. • A
Mshanga- Head of CXR ~oshi • · Awadh Ahmed -Ultimate Security -• Philipa Daniel- Ultimate Security, and • Amos Kazungu. PO Moshi . . Regarding the theft at Dar es Salaam, it is confirmed that there was theft occurred on or between 12 th July 2011 and 11 December 2011 · during which period the Plaintiff were entrusted with guarding the premises of the Defendant as shown in the Agreement dated 30 th July 2009: It is also confirmed that there was a joint Inspection Report carried out on 12 / 07/2011, confirming that the locomotives have been jointly inspected on 11 and .12 July 2011 (Exh D2 collective), and that this report was signed jointly by Mr C.M Sahani the Ultimate Security Representative, Mr L.M Makoye Principal Protection Officer, TRL, Mr Y.S.I Shija TRL Representative, Mr A E Munishi, .Chief Supplies Manager TRL, and Mr Prem _ Chandra, Project Manager RITES Morogoro. Again there is a letter dated 8 th February 2012 from the Chief Supplies 14 Managing .Director of the~ Defendant (Exh- D3 ·collective)-; which 1 confirms that there was a jGint inspection carried out on 21s t January 2012, and that :the representatives from Ultimate. Security were also present. This letter made reference to a letter from RITES Limited dated January 30, 2012 (also Exh D3 collective) confirming that cost details of the materials stolen from the RITES locomotives between 12.07.2011 and
21 - January 2012 was US$ 92,458, and details of materials found stolen from locomotives at the time of first joint inspection on_ 11 and 12· July 2011 was USD 184,698. Hence the total cost of the material stolen is USD 277,156.00 The defence by. the Plaintiff that they were not entrusted vyith- guarding of the materials found ·stolen during the first joint inspection has no substance, as the Plaintiff do not deny that during the period the items were stolen , they were obliged by the Agreement to safeguard ·the properties of the Defendant. Besides, the Plaintiff have not produced any evid~nce to ... substantiate that as to which period they were entrusted to •the Security Agreement to-· guard,,· the Defendant's premises . . . . during the period of Feb,ruary to -March 2011, and that they . were only entrusted to guard the. locomotives after tlle joint . - ~~ . . inspection report of 12 July 2011, as submitted in their . closing submissions. Thus the cost of the items stolen at Moshi is THz 23,326,000, and the total~ costs of the item stolen at Dar es Salaam, Supplies Office is USD 277,166.00 3. Who was responsible for the stolen materials The Agreement entered between the parties imposes a duty upon the Plaintiff to guard and provide security services to the Defendant's property and ensure that the Defendant property including the machines and equipn1ent around and inside
the offices are guarded or protected from theft. Clause 3. 1 of the Agreement reads, and I quote:: 16 guard': o'r protect the properties from~ or_ :-against theft, burglary, ' vandalism, looting, arson, damage or such . u~desirable acts; ,. iii) The Guards shall provide security around and inside the offices and facilrties; - iv) the Company shall provide security services on full time basis i.e. 24 hours/ only 12 hours day shift/ only 12 hours· night shift or as per the Clients request; v) the Company ·shall provide the guards with., equipment's and facilities and shall enable the same to provide · adequate security to TRL of.fices, workshops, Yards, Facilities, Work stations, God · .owris etc. within the ·scope ·of the contract and people working in these places, and shall adequately 17 supervise .. . . . th~ sa_id,guards . .. . to ensu.r~·pro_vi,,sior,i: ' ' :·.,:-: . . .' .' .. . ' oftfiff ·. ~ ... •. ~ - . . Services.-- The evidence presented by the Defendant indicated that the items claimed to have been stolen existed, and they were actually stolen. There are enough reports both by the· police and the reports verified by the Plaintiff during joint inspection reports confirming that indeed theft has occurred, goods were stolen; and value of the goods was given. The reports dia. show the kind, type or inake of the goods that were been· stolen. ·The Defendant has·
disc}:larged its duties of proving its claim on the balance of probabilities, and it is not in dispute that the Plaintiff were put 1n charge of security under the Security Agreement. It is true that Ultimate Security is a security company and undertook or agreed to guard the Defendant's premises at a· fee and it has been proved that Ultimate Security was unable to perform its duties under the agreement or it ·wa~ negligent ... when performing its duties resulting to losses on the part of 18 .,the.Defendant~,_Tli~.t'~'fore·,;-,in i{ns\ver:ito••isstle t.1\ihil:fcir)tiiree:;-}( .,· ... ,.,,· -::."'; .'. . _,, ' . . is Ultimate :S,ecurity Limited who are r:esponsible for guarding and pr-ot~.cting the items,_ stolen, and that~ they either failed to perform thefr:.~uti~.~' or they :were negligent in performing their - duties, as a result, -the Defendant suffers loss.
4. Whether the Defendant is entitled to - compensation/ indemnification Clause 4 of the Secudty Agreement between the Parties herein provide for indemnification, it provides as follows: · 4.1 "the Company will be liable to a maximum of THz 50,000,000 or for 70% of value of loss whichever is less (over and above any compensation, the Client might receive on an insurance policy) in respect of any one claim or .series of claims arising from the same event, for loss or· damage to the client goods (other than . indirect or consequential loss) caused by negligent or intentional acts of the Company, or its servants acting within the course of the employment, . - ex~,~pt, wher~: ..tp~ Jps~--- or- damage howsoever· ca.used has ·beep. contributed by the negligent or ,willful act or omission oLthe client, his servants or cohtractors ...... " 4.2 Subject to the Clause 4.1 herein above, the Client shall be indemnified on the insurance policies against the · losses· to the Clients properties caused by the negligence or by willful defauleby the Company or its employees while performing their duties within the bound$ of this contract ..... " 4. 3 The Company is obliged to process the claim for the loss of the Clients' properties from the Insurance company in order that the client is paid for proceeds of insurance claim not covered by the Company as it is contained under clause 4.1
hereinabove." 20 ·-c•' _: ; ' y:In any '.cas-e trie ,. . re·spon,:sibilityr:of·Ultimatet!-S:echdfy<for the loss·;•;.>· destn1ction or theft -of its client's goods/property as provided ,. in clause 3 of the .agreement reproduced herein above is clear-: ' J Clause 4 of\the Agreement obliged the Plaintiff to compensate the Defendant either THz 50,000,_000 or 70% of the 'value of loss, whichever . is less and this is over and above any compensation the Defendant will receive from the Insurance Company. Under Clause 4.3 of the Agreement, the Plaintiff is obliged to process the claim for the loss from the insurance company. Thus the Plaintiff is required to process immediately with its insurance company for the loss· suffered· by the Defendant amounting to THz 23,326,000 and USD 277,186, and over and above the insurance indemnification, the Plaintiff is i:~quired to pay the Defendant either THz 50,000,000 or 70% of the total loss suffered by the Defendant, whichever is less, as provided in clause 4.1 of the Security Agreement. The amount of THz 50,000,000 or 70% of the total loss suffered by the Defendant, whichever is less may be offset with the unpaid balance·of the invoices i.e. THz 1,369,270,399.01 (minus THz 639,067,715). The amount in USD should be calculated at the ~-------- -·•-.-- •..:.......:, __ rateI:wh~n. th<::!:: los~: .~~tu~lly ·occu,rred i.e. ·the-· rate applicable on · 11,and 12 July 2011. · 5. To what reliefs are the parties entitled: 1. The Plaintiff shall process with _its insurance company and indemnify the Defendant of the loss suffered amounting to THz 23,326,000 and USD 277,186.
2. The Plaintiff shall pay compensation to the Defendant, over and above the indemnification to be ~paid by ·the insurance company, amounting to either THz 50,000,000 or 70% of the total loss suffered by the Defendant and the amount may be offset with outstanding unpaid . . . 1nvo1ces.
3. No interest shall be paid to either of the parties. I 4. Cost of this suit shall be borne by the Plaintiff. It is so ordered. 22 DATED at DAR_ ES SALAAM this 04TH day 0£ September, 2015
MANSOOR