alinaswe levis msukwa vs china hunan construction engineering group africa ltd 2020 tzhc 1022 21 may 2020
The applicant failed to provide good or sufficient cause for the delay; reasons such as the court being in criminal session or administrative issues do not constitute valid grounds for extension of time under the law.
- Citation
- alinaswe levis msukwa vs china hunan construction engineering group africa ltd 2020 tzhc 1022 21 may 2020
- Parties
- Applicant: Alinaswe Levis Msukwa; Respondent: China Hunan Construction Engineering Group Africa Ltd
- Court
- TZHC
- Jurisdiction
- Tanzania
- Judgment Date
- 21 May 2020
- Procedural Posture
- Misc. Labour Application / Ruling on Application for Extension of Time
- Outcome
- Application dismissed
- Legal Topics
- Extension of Time, Review of Court Rulings, Sufficient Cause for Delay
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Alinaswe Levis Msukwa
Applicant
China Hunan Construction Engineering Group Africa Ltd
Respondent
Procedural Posture
Misc. Labour Application / Ruling on Application for Extension of Time
Legal Issues
- 1 Whether the applicant has shown sufficient and reasonable cause for extension of time to file an application for review against the ruling delivered on 15/04/2019
Ratio Decidendi
The applicant failed to provide good or sufficient cause for the delay; reasons such as the court being in criminal session or administrative issues do not constitute valid grounds for extension of time under the law.
Court Disposition
Application dismissed
Orders
- No order as to costs
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment