19980312 TZHC Tabora1
The respondents breached the contract by unilaterally ceasing work for nine days without consulting the appellant, justifying the appellant's engagement of other carpenters and entitling him to relief.
- Citation
- 19980312 TZHC Tabora1
- Parties
- Appellant: Ally Msabaha; Respondent: Hamis Nrisho; Respondent: Hamis Hussein
- Court
- TZHC
- Jurisdiction
- Tanzania
- Judgment Date
- 12 March 1998
- Procedural Posture
- Civil Appeal / Second Appeal
- Outcome
- appeal allowed with costs
- Legal Topics
- Breach of Contract, Remedies for Breach, Contractor and Subcontractor Disputes
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 3
Parties
Ally Msabaha
Appellant
Hamis Nrisho
Respondent
Hamis Hussein
Respondent
Procedural Posture
Civil Appeal / Second Appeal
Legal Issues
- 1 Whether the appellant or the respondents breached the contract
- 2 Entitlement to return of advance payment and compensation for expenses
Ratio Decidendi
The respondents breached the contract by unilaterally ceasing work for nine days without consulting the appellant, justifying the appellant's engagement of other carpenters and entitling him to relief.
Court Disposition
appeal allowed with costs
Orders
- Appeal allowed
- Appellant awarded costs
Full Case Text
Judgment text and source record