baco ayub co ltd vs permanent secretary ministry of defence and national sercive 2023 tzhccomd 15 9 february 2023

baco ayub co ltd vs permanent secretary ministry of defence and national sercive 2023 tzhccomd 15 9 february 2023

A binding contract was formed by the letter of award; the Defendants breached the contract by unilaterally cancelling the tender and failing to pay after the Plaintiff performed its obligations. The Plaintiff is entitled to the contract sum and general damages, but not to unproven specific or punitive damages.

Source-derived case information.

Citation
baco ayub co ltd vs permanent secretary ministry of defence and national sercive 2023 tzhccomd 15 9 february 2023
Parties
Plaintiff: Baco and Ayub Co. Limited; 1st Defendant: Permanent Secretary Ministry of Defence and National Service; 2nd Defendant: The Chief of Defence Forces, People’s Defence Forces Head Quarters; 3rd Defendant: The Hon. Attorney General
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
9 February 2023
Procedural Posture
Commercial Case / Judgment After Rehearing Following Review and Prior Appeal Withdrawal
Outcome
Judgment for the Plaintiff
Legal Topics
Breach of Contract, Specific Performance, Damages, Public Procurement Procedures
Source Language
english
Contract Law Public Procurement Breach of Contract Specific Performance Damages Public Procurement Procedures

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 13 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Baco and Ayub Co. Limited

Plaintiff

Permanent Secretary Ministry of Defence and National Service

1st Defendant

The Chief of Defence Forces, People’s Defence Forces Head Quarters

2nd Defendant

The Hon. Attorney General

3rd Defendant

Procedural Posture

Commercial Case / Judgment After Rehearing Following Review and Prior Appeal Withdrawal

  1. 1 Whether a contract was concluded between the parties and if so, whether there was breach thereof
  2. 2 Whether the goods were imported in the names of the 1st and 2nd Defendants
  3. 3 Whether the goods were cleared by the 1st and 2nd Defendants

Ratio Decidendi

A binding contract was formed by the letter of award; the Defendants breached the contract by unilaterally cancelling the tender and failing to pay after the Plaintiff performed its obligations. The Plaintiff is entitled to the contract sum and general damages, but not to unproven specific or punitive damages.

Court Disposition

Judgment for the Plaintiff

Orders

  • Defendants breached the contract of supply of Meals Ready to Eat (Tender No. ME-020/2012/13/HG/G/01).
  • Defendants to pay Plaintiff TZS 4,913,131,500 as the agreed principal amount.