bp tanzania limited vs sanyo services station limited 2023 tzca 17619 13 september 2023

bp tanzania limited vs sanyo services station limited 2023 tzca 17619 13 september 2023

The applicant accounted for all days of delay in filing the appeal, and the single Justice erred by focusing on the missing letter dated 6th July, 2012 and requiring unnecessary affidavits. The applicant did not rely on the missing letter for exclusion of time but instead accounted for the entire period of delay....

Source-derived case information.

Citation
bp tanzania limited vs sanyo services station limited 2023 tzca 17619 13 september 2023
Parties
Applicant: B.P Tanzania Limited (Now Puma Energy Tanzania Limited); Respondent: Sanyou Services Station Limited
Court
TZCA
Jurisdiction
Tanzania
Judgment Date
13 September 2023
Procedural Posture
Civil Reference / Ruling on Reference From Single Justice's Decision
Outcome
Application for reference allowed; decision of single Justice reversed.
Legal Topics
Extension of Time, Reference From Single Justice, Computation of Time for Appeal, Affidavit Evidence, Discretion of Appellate Court
Source Language
en
Civil Procedure Appellate Practice Extension of Time Reference From Single Justice Computation of Time for Appeal Affidavit Evidence Discretion of Appellate Court

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

B.P Tanzania Limited (Now Puma Energy Tanzania Limited)

Applicant

Sanyou Services Station Limited

Respondent

Procedural Posture

Civil Reference / Ruling on Reference From Single Justice's Decision

  1. 1 Whether the applicant showed good cause for extension of time to file memorandum and record of appeal
  2. 2 Whether the single Justice erred in law and fact in refusing extension of time
  3. 3 Whether the applicant was required to provide affidavits regarding missing documents

Ratio Decidendi

The applicant accounted for all days of delay in filing the appeal, and the single Justice erred by focusing on the missing letter dated 6th July, 2012 and requiring unnecessary affidavits. The applicant did not rely on the missing letter for exclusion of time but instead accounted for the entire period of delay. The Court found the applicant met the threshold for extension of time and exercised its discretion to grant the application.

Court Disposition

Application for reference allowed; decision of single Justice reversed.

Orders

  • Applicant granted sixty (60) days from date of ruling to lodge memorandum and record of appeal.
  • Each party to bear own costs.