kbl enterprises ltd vs cdi cotton distributors inc 2012 tzhccomd 54 25 april 2012

kbl enterprises ltd vs cdi cotton distributors inc 2012 tzhccomd 54 25 april 2012

The court found the petitioner's explanation for delay unsatisfactory and considered the prolonged failure to file submissions as lack of interest, thus ordered enforcement of the arbitral award.

Citation
kbl enterprises ltd vs cdi cotton distributors inc 2012 tzhccomd 54 25 april 2012
Parties
Petitioner: KBL Enterprises Limited; Respondent: CDI Cotton Distributors Inc.
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
25 April 2012
Procedural Posture
Miscellaneous Commercial Case / Ruling on Enforcement of Arbitral Award
Outcome
petition dismissed, arbitral award enforced
Legal Topics
Enforcement of Arbitral Awards, Extension of Time, Failure to File Submissions
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

KBL Enterprises Limited

Petitioner

CDI Cotton Distributors Inc.

Respondent

Procedural Posture

Miscellaneous Commercial Case / Ruling on Enforcement of Arbitral Award

  1. 1 Whether the petitioner's failure to file written submissions within the prescribed time warrants extension of time or enforcement of the arbitral award

Ratio Decidendi

The court found the petitioner's explanation for delay unsatisfactory and considered the prolonged failure to file submissions as lack of interest, thus ordered enforcement of the arbitral award.

Court Disposition

petition dismissed, arbitral award enforced

Orders

  • The arbitral award is enforced as an order of the court.