Holding and result

The appellant breached the contract by not following the approved plan and boundaries, resulting in demolition of the construction. He is liable to refund the advance payment received.

Court disposition

appeal dismissed

Orders

  • appellant to refund the advance payment to the respondent
  • appellant to pay costs

02

Material facts

Parties

Faraji Issa Mbulilo

Appellant

Victorian Mfaike

Respondent

Amounts and remedies

  • Advance Payment to Be Refunded: TZS 5,500

03

Procedural history

  1. Posture

    Civil Appeal / Judgment

04

Questions and positions

Legal issues

Party arguments

Applicant
The appellant argued that he did not see one of the beacons marking the boundaries and that he was not given an opportunity to call witnesses.
Respondent
The respondent alleged that the house was not built according to the plan and boundaries, leading to demolition and sought refund of the advance payment.

05

Court’s reasoning

  1. 01

    court's reasoning

    A party who breaches a contract by failing to perform according to agreed specifications is liable to refund any advance payments received.

06

Ratio, limits and disposition

Ratio decidendi

The appellant breached the contract by not following the approved plan and boundaries, resulting in demolition of the construction. He is liable to refund the advance payment received.

Court disposition

appeal dismissed

  • appellant to refund the advance payment to the respondent
  • appellant to pay costs

Source and reliance status

TZHC · 17 November 1987

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

TZHC

Judgment· 17 November 1987

19871117 TZHC Dar es Salaam

~ IN THE HIGH COURT OF TANZ 1.J'HA AT DAR ES SALA~1 CIVIL APPEAL NO. 41 OF 1985 (Original Kilombero br,1 1 s Court in Civil Case No~ 4 of 1984). FARAJ! ISSA MBULILO •••••••••••••• APPELLANT versus VICTORIAN MFAIK.E ••••••••••••••••• RESPONDENT

JUDGMENT MAINA 2 J. The parties entered into a contract whereby it was agreed that the appellant Faraji Issa Mbuliio would construct a house I t for the respondent, Victorian Mfaike, for S~s. 17,000/=• The appellant received cash Shs, 5,500/= as advance payment·~ He started the construction ,but the respondent a:1.leged that the house was not built according to the plc,n and further that the appellant had built the house without observing the bounderies of the plot, The house was demolished; The district court ordered the appellant to refund the money which he received as advance payment·~ There was believable evidence that the appellant built the house without following the approved plano The rooms "·'')l"~ smaller than what the approved plan provided.· Furthermore, the appellant did not construct the house within the bounderies of the plot. He did not follow the bounderies and so he built I it too close to the road. He agreed be fora mom~~:;:-3 of the reconciliation board to demoiish the whole foundation and start afresh·• The appeliant demolished the foundation because it was of poor workmanship ·and the rooms were not according to specifications and also because it was not built within the bounderies ~. He told this court he did not see one of the beacons·~ If that was so, he should have reported to the respondent or to the Land Office a.o that he could be shown where the

beacons marking the bounderies were~ •'f•h ••: 1 •' • ,?\~.~:>' ~~;'1i>J~?~:~\ The appellant. f s allegat.io:h • ' ' ,~.•~:;~,: ;.h~ij~~;-~·"•~ ·;~, ,_.~~;•<· :,lhd~:. t~e trial . ~o~rt, I II r~fused him a.ri Opportunity to call witnesses cannot be accepted.; The record shows that he specifically told the magistrate that he had no witness to call·. I, am satisfied that the trial court arrived at a sound decision that the appellant had breached the contract·. It was due to his fault that the foundation of the house had to be demolished. He must refund the money which he received from the respondent. The appeal is dismissed with costs. (,~ . ~lj'\/\ l,"-.W\__, W• J. l\1AINA ~, JJJDGE

MOROGORO 17th November, 1987. Appeila.nt - present. Respondent.: present. I

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

No structured authorities are available for this judgment.

Refer to the full judgment and official source for citations that have not yet been extracted.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.