20021111 tzca dar es salaam

20021111 tzca dar es salaam

The interim injunction in Civil Case No. 214 of 2000 lapsed after six months and was not extended. There is no pending appeal in Commercial Case No. 98 of 2001. The applicant has not satisfied the principles for granting a stay of execution. Therefore, the application for stay is dismissed.

Citation
20021111 tzca dar es salaam
Parties
Applicant: Frisia Mwakitwange; Respondent: Respondent Bank
Court
TZCA
Jurisdiction
Tanzania
Judgment Date
11 November 2002
Procedural Posture
Chamber Application for Stay of Execution / Ruling on Application for Stay of Execution
Outcome
application dismissed with costs
Legal Topics
Stay of Execution, Injunctions, Mortgage Without Spousal Consent
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Frisia Mwakitwange

Applicant

Respondent Bank

Respondent

Procedural Posture

Chamber Application for Stay of Execution / Ruling on Application for Stay of Execution

  1. 1 Whether execution of the decree in Commercial Case No. 98 of 2001 should be stayed pending determination of Civil Case No. 214 of 2000
  2. 2 Whether the interim injunction issued in Civil Case No. 214 of 2000 is still valid and operates as a bar to execution

Ratio Decidendi

The interim injunction in Civil Case No. 214 of 2000 lapsed after six months and was not extended. There is no pending appeal in Commercial Case No. 98 of 2001. The applicant has not satisfied the principles for granting a stay of execution. Therefore, the application for stay is dismissed.

Court Disposition

application dismissed with costs