future century ltd vs tanzania electical supply co ltd 2007 tzhccomd 28 18 april 2007
- Citation
- future century ltd vs tanzania electical supply co ltd 2007 tzhccomd 28 18 april 2007
- Status
- Judgment
- Jurisdiction
- Tanzania
- Court
- TZHCCOMD
- Decision
- 18 April 2007
- Posture
- Commercial Case / Judgment
- Language
- English
More details
- Court
- TZHCCOMD
- Decision
- 18 April 2007
- Posture
- Commercial Case / Judgment
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The Plaintiff failed to prove its claims for special and general damages as required by law. The delay in installation of meters was justified due to unresolved issues regarding the origin of materials, and both parties contributed to the delay. The Plaintiff did not prove that its image was tarnished or that the Defendant's letter was defamatory. The Defendant failed to prove its counterclaim for the value of materials. Both the Plaintiff's claim and the Defendant's counterclaim are dismissed with costs.
Court disposition
Plaintiff's claim dismissed with costs; Defendant's counterclaim dismissed with costs.
Orders
- Plaintiff's case dismissed with costs.
- Defendant's counterclaim dismissed with costs.
02
Material facts
Parties
Future Century Limited
Plaintiff Counsel: Mr. MdamuTanzania Electrical Supply Co. Ltd (TANESCO)
Defendant Counsel: Mr. JohnsonAmounts and remedies
- Plaintiff's Claim for Special Damages: TZS 59,000,000
- Plaintiff's Claim for General Damages: TZS 600,000,000
- Defendant's Counterclaim for Value of Materials: TZS 15,324,475
03
Procedural history
Posture
Commercial Case / Judgment
04
Questions and positions
Legal issues
- 01
Whether the Defendant caused delay in power supply for the 25 Blocks at Kijitonyama
- 02
Whether the delay was justified
- 03
Whether the materials used for construction were lawfully acquired by the Plaintiff
- 04
Whether the Plaintiff's image was tarnished by the Defendant's letter
- 05
What reliefs are the parties entitled to
Party arguments
- Applicant
- The Plaintiff argued that it fulfilled its obligations under the contract, that the Defendant's refusal to install the meters was unreasonable, and that the Defendant's actions led to loss of business, reputation, and specific damages. The Plaintiff claimed special damages of TShs 59,000,000 and general damages of TShs 600,000,000 upwards, asserting that the Defendant's letter to NSCD tarnished its image and led to contract termination.
- Respondent
- The Defendant argued that the Plaintiff contributed to the delay by failing to explain the source of materials, that the installation of meters was not automatic and required technical inspection, and that some materials found at the site belonged to TANESCO. The Defendant denied defamation, claimed the Plaintiff's work was incomplete, and counterclaimed for TShs 15,324,475 as value of materials allegedly belonging to TANESCO.
05
Court’s reasoning
Legal principles
- 01
Section 111, 112, 115 of the Evidence Act
The burden of proof in civil proceedings lies on the party who would fail if no evidence were given.
- 02
Zuberi Augustino v Anicet Mugabe 1992 TLR 137; Cooper Motors Corporation (T) Ltd v Arusha Int Conference Centre 1991 TLR 165
Special damages must be specifically pleaded and proved.
- 03
Winfield and Jolowicz on Tort
For defamation, the words must be defamatory, refer to the plaintiff, and be maliciously published.
06
Ratio, limits and disposition
Ratio decidendi
The Plaintiff failed to prove its claims for special and general damages as required by law. The delay in installation of meters was justified due to unresolved issues regarding the origin of materials, and both parties contributed to the delay. The Plaintiff did not prove that its image was tarnished or that the Defendant's letter was defamatory. The Defendant failed to prove its counterclaim for the value of materials. Both the Plaintiff's claim and the Defendant's counterclaim are dismissed with costs.
Obiter and limits
- The arrangement between the Plaintiff and Defendant was vague and lacked necessary specifications, leading to uncertainties.
- Both parties had a duty to clarify the origin of materials, but failed to do so.
Court disposition
Plaintiff's claim dismissed with costs; Defendant's counterclaim dismissed with costs.
- Plaintiff's case dismissed with costs.
- Defendant's counterclaim dismissed with costs.
Source and reliance status
TZHCCOMD · 18 April 2007
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
TZHCCOMD
Judgment· 18 April 2007
IN THE HIGH COURT OF TANZANIA (COMMERCIAL DIVISION)
AT PAR ES SALAAM COMMERCIAL CASE NO. 58 OF 2006 FUTURE CENTURY LIMITED..... PLAINTIFF
VERSUS
TANZANIA ELECTRICAL SUPPLY CO.LTD........................... DEFENDANT
JUDGMENT Date of final submission March 21, 2007 Date of Judgm ent June 18, 2007.
MJASIRI J The Plaintiff in this case Future Century Limited, is a company registered under the Companies Ordinance Cap.212 and carrying on diverse business including electrical engineering. The Defendant is a public corporation engaged in supplying and distributing electricity to its customers in Tanzania. The Plaintiffs claim against the Defendant is for the following orders: l a) A declaration that the Defendant's refusal to install two bulky meters on No 25 Blocks com prising o f 8 A p a rtm en ts is unreasonable a n d unjustifiable. b) A n order compelling the D efendant to install the two bulky meters. c) Specific dam ages in the sum o f S h s 59,000,000. d) Punitive a n d general dam ages to be assessed by the Court but preferably from S ix H undred M illion Shillings. The Defendant denied the Plaintiffs claim and filed a counter claim against the Plaintiff for breach of contract and asking for special damages of Tshs 15,324,475 and general damages. The following issues were framed by the parties with the approval of the court.
1. Whether the D efendant occasioned/ caused the delay in respect o f the pow er supply for the 25 Blocks o f 8 A p a rtm en ts each at K ijitonyam a. 2 2. I f the answer to Issue N o .l is in the affirm ative whether there was any justification for the said delay.
3. Whether the m aterials used for the construction of the H igh Tension Line (HT) and Low Tension Line (LT) were law fully acquired by the P la in tiff 4. Whether the P la in tiffs image was tarnished in view of the D efendant's letter dated A u g u st 28th 2006.
5. What reliefs are the parties entitled to. The Plaintiff was represented by Mr. Mdamu Advocate and the Defendant was represented by Mr. Johnson Advocate. The Plaintiff called one witness one Albert Albino who is the Managing Director of the Plaintiff Company. PW1 testified to this effect. His company deals with the supply and installation of power lines to clients. He constructs power lines on behalf of his client in order for them to be connected with the
TANZANIA ELECTRICITY SUPPLY COMPANY (TANESCO) System. According to PW1 sometime in July 3 2005 his company was subcontracted by the NATIONAL SERVICE CONSTRUCTION DEPARTMENT “NSCD” together with Dunstan Electrical Engineering Services Limited and Namis Corporate for the project of power supply on the 25 Blocks at Kijitonyama Housing Estate which was meant for the employees from the President’s office. A contract was executed by the parties on August 4, 2005 (Exhibit PI). PW l’s duty under the contract was to supply power to the main contractor, that is NSCD. The value of the contract was TShs 119,789,230. The works under the contract was supposed to be completed after 4 weeks. According to PW1 he was then introduced to TANESCO as the job could not be done without TANESCO. He therefore wrote to TANESCO asking for the requirements for the Project, on August 10, 2005 TANESCO replied to him on August 30, 2005. The conditions imposed by TANESCO were th at he should construct the power line and must pay TANESCO before doing so. He therefore paid TShs 960,000 as supervision fees for High Tension (HT) Lines and TShs 600,000 inclusive of VAT being commission fees for HT 4 Line and Transformer substation. (Exhibit P2 and P3) Receipts were issued by TANESCO for the payments. PW1 further testified that the other condition to be fulfilled under the contract was to let TANESCO inspect all the
materials that would be used for the construction work. TANESCO inspected the materials and supervised the works from the state of the pole holes to the time the line was being energized; that is up to the time the line is charged. The line is then joined to TANESCO’s existing system. TANESCO does this to ensure that the power line is well built as it would become the property of TANESCO. Payment was made in November 2005 because the reply from TANESCO reached PW1 in November 2005. After payment was made PW l further stated that TANESCO came to the site, inspected all the materials and allowed the construction to proceed. TANESCO employees were present at the site on a daily basis inspecting and supervising the works. The construction of the power line was completed on December 18, 2005. TANESCO charged the line and what remained was for the metres to be installed. A letter dated December 19, 2005 was sent to TANESCO asking TANESCO for the installation of Bulk Metres (Exhibit P4). TANESCO was supposed to give a quotation and to install the said metres. The Bulk Metres were required to enable NSCD to use power for construction purposes and for use by residents once the apartm ents were ready for occupation. The first reminder was sent to TANESCO on July 11, 2006 and the second on August 27, 2006 (Exhibit P5). PW1 further stated that during site meetings he was given a deadline
by his client that power must be available at the site by September 31, 2006 otherwise his contract would be terminated. According to PW1 TANESCO sent a reply on August 28, 2006, and PW1 was asked to explain to TANESCO where he obtained the construction materials. The letter was copied to the client as well. The client was concerned and wanted to know what was going on. He further stated that in view of this he decided to come to court. He would not be paid the remaining balance by NSCD as he had not fully completed the contract. As a result his contract was 6 terminated by the client National Service Construction Department (Exhibit P7). PW1 further stated that the metres were installed following a court order. According to PW1 before the construction took place TANESCO had already asked him where he obtained the materials. PW1 showed them receipts indicating where he purchased the materials. He has been buying materials from Automech and some of the materials he purchased from TANESCO. PW1 further stated he had obtained work from other companies as well such as CELTEL and TTCL. PW1 testified that the materials used for construction of the line alleged to have been stolen from TANESCO were worth TShs 15,000,000, but the materials used by him for construction was worth TShs 96,700,000. PW1 further testified th at in view of the termination of the contract by the National
Service Construction Department, their image was tarnished completely. They 7 lost NSCD immediately after being accused of theft. They lost NSCD as a client. They also failed to pay some of their suppliers, as some suppliers are paid after the work is completed. They also lost three technical experts. PW1 also testified that their annual turnover declined from TShs 1.4 billion to TShs 365,000,000. PW1 further testified th at the Dodoma Project and Kijitonyama Projects were more or less the same. Therefore the remaining m aterial bought from TANESCO in Dodoma was used by them for the Kijitonyama Project. On cross examination by Mr. Johnson Advocate for the Defendant he stated th a t though he is not an electrical engineer, the construction of the power lines related to his academic qualifications. The work done by his company was supervised by a TANESCO Engineer one Mr. Mmari. The person supervising him issued a certificate as to quality of goods, quality of the construction and source of materials. PW1 denied that he testified in court that TANESCO delayed in issuing him quotations. PW1 also testified that the power was there and the issue in question was the installation of bulk meters, PW1 further testified that after installation of bulk meters the client was to pay for the tariff. PW l further testified that the installation of the metre was not automatic, a contract was
required between the client (NSCD) and TANESCO. PW l stated that he was supposed to handover the Project by August 31, 2006. TANESCO refused to avail him the procedure for meter installation unless he explained how he acquired the m aterial used for the power line installation. With regards to informing TANESCO how he got the materials PW l stated that according to conditions given to him by TANESCO, TANESCO was supposed to conduct inspection before the construction work, which they did. PWl stated that he did not reply to the letter by TANESCO asking where he obtained the property TANESCO suspected to be theirs. 9 PW l further stated that he has proof that after the dispute with TANESCO, if he tendered for a job, he did not get it. PW l stated th at the materials bought from TANESCO took place after a request placed by him. There were no special conditions for such a sale. The Defendant called one witness. DW1 Nsajigwa Jam es Mwaisaka testified as under. He is the Distribution and Safety Manager of the Defendant, since 2006 and before that he was the Regional Manager Temeke. According to DW1 his duties are to prepare specifications for materials for the company and to ensure there are enough m aterial for the company work. DW1 testified th at PW l’s company was prequalified by TANESCO to undertake distribution work. Though the Plaintiff Company performed well but there was
a problem as some of TANESCO materials were found at the Plaintiffs site. 10 DW1 further stated th at for this job the Plaintiff Company was subcontracted by NSCD. TANESCO was to supervise the work for a fee. TANESCO supervision was required to ensure that the work was done according to standards required by law and in compliance with TANESCO rules and regulations. The origin of the material had to be known and acceptable, in order to ensure that the materials are not fake. Though the standard of the materials was acceptable the materials was illegally obtained from TANESCO. The first supervisor from TANESCO did not do a good job and was interdicted. The said supervisor failed to disclose that the material used by the Plaintiff belonged TANESCO. The name of the supervisor is engineer Eva Fumbuka. DW1 in his testimony made reference to Exhibit P6 a letter from TANESCO dated August 28, 2006 requiring clarification on how the m aterials used for construction of HT lines, the property of TANESCO was obtained by the Plaintiff. According to DW1 the Plaintiff did not reply to the said letter but came to court instead. 11 DW1 further stated that the metres were installed following a court order dated September 7, 2007. DW1 further testified th at the receipts admitted as Exhibit P8 are not all related to the issue. The Dodoma site was visited and from the work done at the site
there could not have been a lot of materials left for the Kijitonyama works. DW1 further stated that they do not store any m aterials at Automech. DW1 also stated that a transformer ordered from India by TANESCO was found at the Plaintiffs site. The manufacturer in India VJ was contacted. According to the said manufacturer no transform er was sold to the Plaintiff. (Exhibit D2) e-mail from VJ to TANESCO. DW1 further stated that on making enquiries to ABB another manufacturer of transformers, ABB also indicated th at no transformer was sold to the Plaintiff (Exhibit D3). 12 On the counter claim filed by TANESCO DW1 stated that TANESCO is claiming to be paid back for the materials that belonged to TANESCO. The total value of the material is TShs 15,324,475. These were materials found at the site belonging to TANESCO. Exhibit D4 (List of materials drawn by TANESCO). Some of the materials found at the site belonged to the Plaintiff. DW1 also stated that for instance out of many wooden poles they found at the site 4 belonged to TANESCO. A report was made after TANESCO inspected the 25 blocks (Exhibit D5). DW1 also stated that the m atter is still under investigation. However for the Kijitonyama project they were sure th at the materials used were theirs and he asked the court to order Future Century to pay for the materials and to dismiss the Plaintiffs claim. On cross examination
by Mr. Mdamu learned Advocate for the Plaintiff DW1 stated that Fumbuka and Mmari TANESCO supervisors messed up. However this was contributed by the Plaintiff an outsider and TANESCO has to make a claim against the Plaintiff. 13 DWl also stated th at TANESCO did not carry out its duties properly under Engineer Fumbuka, but properly carried out its duties under another manager. According to DWl the line was not energised by December 2005. Until the metre is energized, by TANESCO the work would not be considered completed. According to DWl the works was not completed by December, 2005. Even after the court order for installation of the meters was made the installation could not be done at once as there was a problem. DWl also testified th at TANESCO never authorized Diason Cable to sell materials to the Plaintiff, materials meant for TANESCO. The purported letter never reached Diason Cable. DWl stated that the Project was not complete before the installation of the metres. DWl further testified that TANESCO will have a problem if Diason Limited sold materials with TANESCO marks to the Plaintiff. Even if TANESCO allowed the 14 Plaintiff to make purchases from such places authorisation from TANESCO must be shown. DW1 testified that the Plaintiff did not tell them of the problem it was having with NSCD. DW1 further stated th at TANESCO does not sell materials to parties contracted.
Parties contracted supplied the labour and TANESCO supplied the materials. On re examination by Mr. Johnson DW1 stated that if TANESCO staff handed over its materials to an outsider it had to make a follow up on the said materials. TANESCO was not a party to a contract between NSCD and the Plaintiff. Mr. Mdamu learned Counsel in his written submissions argued as follows: On issue No.l Mr.Mdamu submitted that the Plaintiff fulfilled its obligations under the contract with the Defendant, the construction could not have commenced if no inspection of the materials was done. The Plaintiff should not be penalised because of the fault of the Defendant’s employees. The construction work was 15 completed by the Plaintiff on December 18, 2005 (Exhibit P4). Efforts were made by the Plaintiff to follow up, and letters were sent to the Defendant dated August 27, 2006 and July 11, 2006 (Exhibit P5). The Defendant’s query as to how the Plaintiff obtained its m aterial was ridiculous and unreasonable. Counsel asked the court to answer Issue No.l in the affirmative. With regards to Issue No.2 counsel for the Plaintiff stated th at the delay was not justified. According to Counsel once a line is energised it becomes an exclusive property of TANESCO. With regards to Issue No.3 Counsel submitted that according to the testimony of PW l before the commencement of the construction work the
Defendant’s office inspected all the materials at the site for quality and standard and source of materials. The Plaintiff was given a go ahead for construction. Exhibit P4 does not clearly state the criteria used in identifying items belonging to TANESCO. In the absence of a detailed audit report TANESCO’s claim of ownership over the materials 16 cannot stand. Therefore the Plaintiffs counter claim has no basis. With regards to Issue No.4 whether the Plaintiffs image was tarnished Counsel for the Plaintiff submitted that the Plaintiffs image was tarnished as a result of the Defendant’s act of copying Exhibit P6 to its client NSCD who were the main contractors. This was the letter from Defendant asking the Plaintiff to explain how he obtained the materials belonging to TANESCO. Counsel submitted that NSCD terminated the Plaintiffs contract (Exhibit P7). The termination was a result of Exhibit P6. Counsel therefore requested the court to answer Issue No.4 in the affirmative. With regards to the reliefs claimed Counsel for the Plaintiff submitted that the Plaintiff is entitled to special damages of TShs 59,000,000 which the plaintiff lost as a result of the Defendant’s delay in metre installations. Counsel also submitted that the allegations of theft tarnished the Plaintiffs image. Plaintiffs former 17 customers like TANESCO, CELTEL, TTCL and NSCD are no longer interested to work
with the Plaintiff. The Plaintiff experienced a drop of income, the plaintiff is entitled to general damages of TShs Six Hundred Million upwards. Mr. Johnson learned counsel for the Defendant submitted as follows. With regards to Issue No.l, Counsel submitted that the Engineers who supervised the works, Engineers Fumbuka and Mmari were interdicted for failure to properly supervise the work carried out by the Plaintiff. Counsel further submitted that, that the supply of power was not automatic and the Defendant had to conduct a technical inspection before power was supplied to the premises. Counsel further submitted that if there was a delay then the Plaintiff contributed enormously for the said delay for failure to disclose the source of materials. The two bulky meters were connected after the Defendant was satisfied that the installation by the Plaintiff was proper. The Defendant is still working on the information sent by the Plaintiff, and this forms the subject m atter of 18 Commercial Case No.72/2006 between the same parties pending before the court. The Plaintiff rushed to court without informing the Defendant of his intention to do so. Counsel further testified th at there was no delay in the installation of the metres as the Plaintiffs work was incomplete. When the site was inspected it was found not to be in a good condition for power supply, and the Plaintiff was
required to do the necessary work. The metres were installed after a month Therefore the Plaintiff cannot say that the work was completed. With regards to Issue No.2, Counsel submitted that since there was no delay and the Defendant’s acts were justifiable and if there is delay, the Plaintiff contributed to the same. With regards to Issue No.3 whether the materials used for the construction of the HT Line and LT Line were lawfully acquired by the Plaintiff; Counsel submitted that the position is not clear. Counsel further submitted that according to Exhibits D2 and D3 the manufacturers of some of the items stated categorically 19 that they never sold the items to the Plaintiff. Counsel for the Defendant further stated that the explanation given by the Plaintiff on the items listed in Exhibit D4 was so generalised to bring any meaningful assistance as to how the items were found at the site. According to Counsel this was meant to hide the fact that the goods were obtained through unscrupulous means from the Defendant, using unfaithful employee of the Defendant. Counsel further stated that since the Plaintiff failed to give proper explanation on how he came into possession of the items and since the items have already been installed at the site the court should order the Plaintiff to pay to the Defendant for the value of the said items, i.e the sum of TShs 15,324,475,000. With
regards to Issue No.4as to whether the Defendant’s image was tarnished counsel submitted that para 13 of the Defendant’s W ritten Statem ent of Defence, which addresses that issue should form part of the Defendant’s submission. Counsel further submitted that there was justification as the Defendant had a reasonable suspicion on where the materials were obtained and that NSCD as main contractors who introduced the Plaintiff to 20 the Defendant were entitled to know the progress of the work. The words complained of were not defamatory at all since they were depicting a true picture of what was found at the site during the inspection. No reasonable man would interpret otherwise. According to Counsel no particulars of defamation were given. Counsel cited the case of Waters Vs Sunday P ictorial Newspapers 1961 IW L.R 967. Counsel submitted that it was stated in the above case that the Defendants can justify any meaning which the words are complained in the statem ent of claim in their proper context within the publication as a whole are reasonably capable of bearing irrespective of what meanings are pleaded. Counsel submitted that the Plaintiff s image was not tarnished and the claim for damages should therefore fail. With regards to Issue No.5, Counsel submitted that as some of Defendant’s items were found at the site of the Plaintiff, the Plaintiff should pay the Defendant
TShs 15,324,475 being the value of the said properties. Counsel 21 further submitted that the Plaintiffs claim has not been proved to the required standard and should be dismissed with costs. Counsel further submitted that the Plaintiffs claim for TShs 59,000,000 is unjustifiable. NSCD is not a party to the proceedings. Any claim for damages for breach of contract should be made to NSCD, who are the parties who term inated the Plaintiffs contract. At the time of installation of the bulky meters on 13.10.2006 the site was still manned by the Plaintiff. No other contractor was found at the site. The allegations of the Plaintiff are therefore unfounded. Counsel prayed that the Plaintiffs case be dismissed with costs and Judgment be entered for the Defendant on the counter claim as prayed. After carefully reviewing the evidence adduced in court in respect of this case and the submissions made by Counsels, I would like to state as follows: With regards to issue No.l, whether the Defendant occasioned/caused the delay in respect of power supply for 22 the 25 Block in Kijitonyama, it is my finding that there was a delay in respect of the power supply for the 25 Blocks in Kijitonyama. According to the agreement entered between the Plaintiff and NSCD exhibit PI, the Plaintiff and two other contractors were supposed to complete the works within 4 weeks from the date of the agreement. The
Agreement between the parties was dated August 4, 2005. The Defendant, TANESCO was not a party to the contract entered between the Plaintiff and NSCD. The arrangement entered between the Plaintiff and the Defendant is based on a letter dated August 30, 2005 Exhibit P2. The said arrangem ent was vague and lacked details. According to PWl the Defendant refused to install the metres in question, in view of their query on materials belonging to the Defendant found at the site of the Plaintiff. DWl confirmed the said position, however DWl testified th at the works had not yet been finalised by the Plaintiff. According to DWl even following a court order it took almost a month to have the metres installed because the works was not completed. According to DWl, materials belonging to the Defendant were found at the 23 Plaintiffs site. A list of the materials in question was produced by DW1 (Exhibit D4) and an investigation report on the materials found conducted by TANESCO officials (Exhibit D5). According to DW1 the Defendant wanted to know how the Plaintiff happened to be in possession of the said materials before the metres were installed. The delay in the installation by the Defendant therefore came about because of the query on the materials belonging to the Defendant, which was not responded to by the Plaintiff. The Plaintiff therefore was also responsible to the said delay. This
issue is still unresolved by the parties and there is no evidence on record as to how this issue was being addressed. I would also like to mention in passing that the arrangement reached between the Plaintiff and the Defendant was too general and lacked specifications on the materials to be used, the time factor, the type of supervision to be carried out by the Defendant. This left a lot of room for vagueness and uncertainties. 24 It is therefore my finding that in the light of the prevailing circumstances, the delay was justified. This addresses issue No.2. With regards to Issue No.3 whether the materials used for the construction of the High Tension Line (HT) and Low Tension Line were lawfully acquired by the Plaintiff. According to PW l some of the materials used for the construction of the power line were bought from TANESCO and some were bought from other suppliers. This is the reason why materials with TANESCO emblem were found at the site. However DW1 testified to the effect that the materials bought from TANESCO were for construction of the site in Dodoma and could not have remained for use in the Kijitonyama 25 Blocks. The evidence on record does not clearly establish which materials were bought from TANESCO, and which materials were not. Evidence was also adduced by DW1 th at some of the suppliers denied selling materials (such as transformers) to the Plaintiff. Both
parties did not come out clearly as to the origin of 25 the materials. It is my view th at each party had a duty and responsibility to come up clearly with the position. Based on the evidence on record, the issue of materials was still under investigation and in the light of the prevailing state the court is not in a position to conclude that the materials used for the construction were lawfully acquired. Section 111 of the Evidence Act provides as follows: “The burden o f proof in a suit proceedings lies on that person who would fail if no evidence at all were given at all on either side.” Section 112 provides as follows: “The burden o f proof as to any pa rticu la r fact lies on that person who wishes the court to believe its existence unless it is provided by any law that the p ro o f o f that fact shall lie on any particular person . ” Section 115 provides as under: “In civil proceedings when any fact is especially within the knowledge of any person the burden of proving the fact is upon him.” 26 With regards to whether the Plaintiffs image was tarnished in view of the Defendant’s letter dated August 28th 2006, it is my finding that the Plaintiffs image was not tarnished. The letter was copied to NSCD, who was the Plaintiffs client. The relevant part of the letter is reproduced as under: “Before we give you quotation for service line & meter connection a n d supply pow er
to the project nam ely 25 Blocks K ijitonyam a, we would like your office to clarify to us of how you obtained the m aterials used for construction of H T Line, D istrib u tio n /tra n sfo rm e rs/ substation an d LT Line at the prem ises all the m aterials appear to be of T A N E S C O .” The letter was not copied to any other party apart from NSCD, the Plaintiffs client. The Plaintiff has not brought any evidence to show how the wording of the said letter tarnished the image of the Plaintiff or th at the said information was published to other parties. No particulars of defamation were given. 27 According to Winfred and Jolowicz on Tort for an action of defamation to succeed the following factors must be present: 1. the words must be defamatory. 2. they must refer to the plaintiff. 3. they must be maliciously published. The above factors are not present in this case. The onus is on the Plaintiff to establish malice. I am of the view that the natural plain and ordinary meaning of the words complained of were in the context used not defamatory. The Defendant was justified in making the enquiry following the behaviour of its employees, entrusted with the supervision of the works. With regards to the Defendant’s counter claim I would like to state as follows. A counter claim is substantially a cross a suit and the Defendant has the burden of proving its claim on the balance of
probability. From the evidence adduced in court, the Defendant has failed to discharge the said burden. 28 Section 110(1) and (2) of the Evidence Act provides as under: “Whoever desires any court to give ju d g m e n t as to any legal right or liability dependent on the existence of facts which he asserts m u st prove that those facts exist. “When a person is bound to prove the existence of any fact, it is said that the burden of pro o f lies on that person. ” The Defendant has failed to prove his counter claim and it is therefore dismissed with costs. On the relief claimed by the parties, the position is as under: With regards to the Plaintiffs claim for specific damages of Tsh 59,000 it is my finding that special damages must be proved. In Zuberi Auaustino V Anicet Mugabe 1992 TLR 137 and Cooper Motors Corporation (T) Ltd V Arusha Int Conference Centre 29 I 1991 TLR 165 it was stated th at special damages must be specifically pleaded and proved. No documentary proof has been made available on the project costs of TShsll9,789,230.00 and the outstanding balance of TShs 59,000,000. No breakdown of the payment process and how each of the three contractors engaged by NSCD were to be paid. No evidence was brought to establish and to justify the claim of Tshs 59,000,000. In view of my finding on issues No.l and 2, 3 & 4 the Plaintiff prayers for punitive and general damages
cannot stand. General damages and punitive damages are assessed by the court, taking into consideration the circumstances of the case. The prevailing circumstances do not w arrant for award of such damages. With regards to the prayer for a declaration th at in the circumstances of the Defendants refusal to install 2 bulky meters into the 25 blocks of eight apartm ents each at Kijitonyama is unreasonable and unjustified, it is my finding th at in view of the evidence adduced in court and my findings on issues Number 1, 2 and 3 the said declaration cannot be made by the court. The Plaintiff 30 abandoned the prayer for an order compelling the Defendant to install the 2(two) bulky metres in view of he court order. Costs follow the event, therefore in the light of what has been stated hereinabove the Plaintiffs case is hereby dismissed with costs. The Defendant’s counter claim is also hereby dismissed with costs. It is so ordered. Sauda Mjasiri, Judge June 18, 2007 Delivered in Chambers this 18th day of June 2007 in the presence of the Plaintiff and Mr. Johnson Advocate for the Defendant and in the absence of Mr. Lutema Advocate for the Plaintiff. Sauda Mjasiri, Judge June 18, 2007 5,963- words jd 31
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.