GAS ENTEC

GAS ENTEC

The defendant was not liable for breach of contract because the plaintiff suspended the project for three months and notified the defendant, who was justified in retaining the crane for the agreed suspension period. The plaintiff contributed to the breach by suspending and later requesting the crane before the...

Source-derived case information.

Citation
GAS ENTEC
Parties
Plaintiff: Gas Entec Co. Limited; Defendant: Magare Co. Limited
Court
TANZLII
Jurisdiction
Tanzania
Judgment Date
1 January 2019
Procedural Posture
Civil / Final Judgment
Outcome
claim dismissed with costs
Legal Topics
Breach of Contract, Damages, Contributory Fault
Source Language
en
Contract Law Breach of Contract Damages Contributory Fault

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Gas Entec Co. Limited

Plaintiff

Magare Co. Limited

Defendant

Procedural Posture

Civil / Final Judgment

  1. 1 Whether the defendant breached a 70-ton crane rental agreement entered between the parties
  2. 2 Whether the plaintiff suffered damages as a result of breach of a 70-ton crane agreement
  3. 3 Whether the plaintiff contributed to the breach of the crane agreement

Ratio Decidendi

The defendant was not liable for breach of contract because the plaintiff suspended the project for three months and notified the defendant, who was justified in retaining the crane for the agreed suspension period. The plaintiff contributed to the breach by suspending and later requesting the crane before the suspension period expired.

Court Disposition

claim dismissed with costs

Orders

  • Plaintiff's claim dismissed with costs
  • Right of appeal explained to the parties