Download PDF

Tanzania Judgment

TZCA

gbl associates ltd vs tanzania portland cement co 1995 tzca 53 8 june 1995

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable without obtaining the Right of Occupancy, which was the appellant's responsibility. The respondent had overpaid the appellant by Shs. 1.7 million, but no enforceable order for repayment could be made due to the struck-out counterclaim. Orders for penalties and further payments were set aside as untenable.

Court disposition

Appeal dismissed with costs; High Court judgment set aside except for costs; substituted order for payment of Shs. 775,000 to appellant; declaration of overpayment by respondent.

Orders

  • Appellant's claim allowed at Shs. 775,000
  • Declaration that respondent overpaid appellant by Shs. 1.7 million
  • Respondent at liberty to apply for refund of deposited money

02

Material facts

Parties

G.B.L. & Associates Ltd.

Appellant Counsel: Mr. Kumwembe

Tanzania Portland Cement Co.

Respondent

Amounts and remedies

  • Appellant's Claim (original): TZS 3,367,200
  • Appellant's Entitlement (external Survey): TZS 775,000
  • Respondent's Payment to Appellant (total): TZS 2,475,000
  • Overpayment by Respondent: TZS 1,700,000

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From High Court Judgment

04

Questions and positions

Legal issues

Party arguments

Applicant
The appellant claimed entitlement to fees for both internal and external survey work, asserting completion of contractual obligations and seeking payment of the outstanding balance.
Respondent
The respondent denied completion of all contracted work, contended that only the external survey was completed, alleged overpayment, and sought penalties for delay and overcharging.

05

Court’s reasoning

  1. 01

    Contract Law

    Payment for contractual services is contingent upon completion of specified work and fulfillment of conditions precedent.

  2. 02

    Common Law

    Quantum meruit may apply if work is performed and benefits are conferred, unless contractually excluded or conditions precedent are unmet.

  3. 03

    Civil Procedure

    A party cannot be ordered to pay on a counterclaim that has been struck out or is not maintainable.

06

Ratio, limits and disposition

Ratio decidendi

The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable without obtaining the Right of Occupancy, which was the appellant's responsibility. The respondent had overpaid the appellant by Shs. 1.7 million, but no enforceable order for repayment could be made due to the struck-out counterclaim. Orders for penalties and further payments were set aside as untenable.

Obiter and limits

  • If the Right of Occupancy is unobtainable due to the respondent's fault, the appellant may be entitled to payment for internal survey work.
  • No internal survey should be carried out before obtaining at least an offer of a Right of Occupancy, as expenses would otherwise be wasted.

Court disposition

Appeal dismissed with costs; High Court judgment set aside except for costs; substituted order for payment of Shs. 775,000 to appellant; declaration of overpayment by respondent.

  • Appellant's claim allowed at Shs. 775,000
  • Declaration that respondent overpaid appellant by Shs. 1.7 million
  • Respondent at liberty to apply for refund of deposited money

Source and reliance status

TZCA · 8 June 1995

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

TZCA

Judgment· 8 June 1995

gbl associates ltd vs tanzania portland cement co 1995 tzca 53 8 june 1995

IN THE COURT OF APPSXL OF TANZANIA

AT DAR ES SALAAM CORAM; MUSTAFA, J . A , ; KISANGA, J.A. AND OMAR, J . A . CIVIL APPEAL NO. 24 OF 1984

BETWEEN G.B.L. & ASSOCIATES L T D - . APPELLANT

AND

TANZANIA PORTLAND CEMENT CO RESPONDENT (Appeal from the Judgment of the High Court _of Tanzania at Dar © Salaam) Mr. Justice A. Bahati) dated 25th day of April, 1984 in Civil Case No. 9 of 1982

JUDGMENT OF THE COURT MUSTAFA. J.A.;-: The appellant is a company of consulting engineers and architectural consultants and had entered into a written agreement dated 12.12,1980 with the respondent, a company dealing with cement manufacture. The appellant was according to clause 2 of the agreement to "survey the Wazo Hill area to produce plans, drawi: etc. which will enable to obtain lease (Right of Occupancy) of detailed and designed drawings for proposed future roads, drainages, car parks etc. (hereinafter called the works) all in accordance with the employer's requirements". Clause 13 reads: "All general conditions of this agreement shall be interpreted with the ACE regulations, together with the agreed correspondences between the parties hereto shall form part of Agreement". The appellant as plaintiff sued the respondent in the High Court for unpaid feec amounting to Shs. 3 ,56 7,2 00 later corrected to Shs.3,367,200 for work carried out for the respondent in accordance with the agreement. ......../2 . - 2 The appellant alleged tna'c it was entitled to payment in respect of fees and disbursements in the total sum of Shs. 5,842,200 and that it had received payment from the respondent a sum of Shs. 2,275,000, leaving the balance of Shs. 3,567,200 (corrected to 3,367,200/=) claimed. The appellant alleged that it had completed all the work it had undertaken to do in terms of

the written agreement. In its defence the respondent denied that the appellant had completed its work. It contended that only the main boundary survey, i.e. the external survey was completed by the appellant. The respondent further alleged that "the purpose of the survey was to enable the defendant to procure a Right of Occupancy and not the registration of the survey. No right of occupancy has been procured yet". The respondent alleged tha t it had paid the appellant a sum of Shs. 3,410,351/70, and had in fact overpaid the appellant by Shs. 2,103,351/70. The respondent counterclaimed against the appellant for jtwo items, the alleged overpayment of Shs. 2 ,1 0 3 , 35 1 / 7 0 and a penalty or liquidated damages assessed at Shs. 500 /= p er day in terms of clause 6 of the agreement for the delay by the appellant in completing its work. According to clause 3 of the agreement the work was to commence on 12.12.1980 and to be completed on 12.2.81. The appellant succeeded in the High Court, on a preliminary objection, to have the counterclaim of the respondent struck out as being not maintainable. The order dismissing the counterclaim by the respondent was dated 10.8.82. There were a number of issues in dispute between the parties at the trial. Eventually the trial Judge found as follows: The Judge held 4<1) That the survey was of two categories, an externa" survey and an internal

survey. The appellant h.. completed the external i.e. the boundary survey which was required for the issuance of an offer of a Right of Occupancy by the Ministry of Lands. - 3 - (2) The internal survey, consisting inter alia of detailed and designed drawings of future drainage, car parks, roads etc. was incomplete, as roads and drainages were still to be done. (3) That the survey was for the purpose of obtaining a Right of Occupancy of the area by the respondent, and that it was the responsibility of the appellant to procure it. (4) That internal survey was not to be carried out until an offer of a Right of Occupancy has been obtained and that the appellant knew or should have known this. (5) That if the Right of Occupancy was not obtained or not obtainable no payment for the internal survey carried out by the appellant was payable. (6) That the fee for the external survey was Shs. 77 5,000? and this sum was payable by the respondent. (7) That, as regards the charges for the internal survey, the appellant had claimed an excess of Shs. 572,000t being charges for 52 blocks for which no survey had been carried out. (8) That the appellant was liable to pay a sum of Shs. 499,000 to the respondent as penalty for delay in completing the work. Further penalty at s h s . 500 /- per day was to continue from date of judgment i ee. 25„4.84 until the work was completed or the

contract rescinded. (9) That the appellant, on completion of the internal survey and on obtaining the Right of Occupancy, was entitled to his claim of Shs. 3 , 3 6 7 ,2 00 . (10) That the respondent had paid the appellant, in respect of the work in terms of the contract, a total of Shs. 2,475,000 for both the external and internal survey. The appellant was only entitled, as at the date of the filing of the suit, to Shs. 775,000/- in respect of the external survey, and that the respondent had overpaid the appellant the sum of Shs. 1 ,7 0 0 ,00 0 , which the appellant has to refund. (11) That a fee of Shs. 1 ,5 0 0 ?000 is due and payable for obtaining a Right of Occupancy, which fee the appellant should pay from the excess payment it had received from the respondents (12) That the appellant has to pay the respondent the sum of Shs. 499 ,00Q being penalty for delay and Shs.572,000/- for overcharging for 52 blocks. .0 0 0 .../ . 4 _ 4 - (13) Should the Right of Occupancy be procured and the internal survey completed in respect of roads and drainages, the appellant would be entitled to be paid the net sum of Shs. 3,796,200. (14) Should the appellant fail to complete the internal survey and to obtain the Right of Occupancy the respondent would b e entitled to rescind the contract and the appellant liable to pay the respondent the sum of Shs. 2,771,000. The Judge granted the costs of

the suit to the respondent* From that judgment the appellant has appealed to this c°urfc* We will have to examine the written agreement of 12.12.1980, In terms of Clause 2, already quoted, the survey and the production- of the plans, drawings etc. were to "enable to obtain lease (Right of Occupancy)* the area. It was unclear who was responsible to procure the Right of Occupancy. However the respondent alleged that the appellant was responsible, and a letter written by the appellant to the respondent dated 21.12.1981 stated inter alia "The issue of Right of Occupancy is our job and we shall finalise it without problem s” . This was after the respondent had written to the appellant On several occasions enquiring about the Right of Occupancy, on 20.5.1981, 9.6.1981, and 18.12.1981. We are satisfied that the Judge was right in holding that the survey was for the procurement of a right of occupancy over the Wazo Hill area and that the appellant was responsible for obtaining it. There was evidence that a sum of Shs. 1 ,500^000 would be required for the issue of the Right of Occupancy, and we think that the Judge was right, on the evidence adduced, to conclude that the respondent was not informed nor asked by the appellant to produce that sum. Despite the assurance given by the appellant in its letter of 21.12.81, the appellant had not even obtained an offer of a right of occupancy,

let alone a right of occupancy. Both Counsel agree that the work consisted of an internal and an external survey. Two witnesses P.W.l and D.W.2 testified that the offer of a right of occupancy was obtainable when an external survey was done, and an external survey was done in is ca se. - 5 - There wat evidence, by P.W.l and D.W.2, both qualified surveyors, and acce^i.ecj ^y the j ucjge, that an internal survey is carried out only ^fter a right of occupancy has been obtained (per P.W.l) or after ^ right of occupancy has been offered (per D.W.2), D.W.2 also staio,-} that professional surveyors, and the appellant was engaged were supposed to know this. The trial Judge had erre^ When he stated that "The regulation prohibiting internal survey U/,ti]_ there is a right of occupancy obtained is a sound regulati‘,n ti? as there was no "regulation" as su4h. But in effect he came the right conclusion, as, although it was not a regulation, it was c matter of common practice that no internal survey is carried u n tii a right of occupancy has been granted or at least offered. The reason is clear. If no right of occupancy is obtainec^ the expenses incurred in an internal survey would be wast*>cj ancj the sUrvey would be of no value at all. In any event, demand for payment for the internal survey was premature in the ijircumstances. ^'he Judge, held that if no right of occupancy is

obtained, the aP P & n ant would not be entitled fco any payment for the work done or* internal survey, on a quantum meruit or any basis. We thii^ thiw was going too far. It is true that as professional surveyc«rs appe n ant ought not to have commenced the internal survey until it had ensured that at least an offer of a right of ° c c u p a ^ C y was obtained. However if the right of occupancy is un o b t a \ nable due to any act of commission or omission on the part of the respondent, then the appellant would probably be entitled ‘-° P aYVnent for work done on the internal survey even if no right of oc c v j p g ^ y i s obtained. Apart from this qualification we agree with tVje trial Judge that the appellant was responsible for obt ai nin g the right of occupancy, that no internal survey ought ^ i. a v e been done without obtaining at least an offer of a right of occ upancy and in the circumstances, no money for any internal surve\ was p ay abie to the appellant by the respondent at the time the si.jit was filed. - 6 - Since the respondent was not liable to pay for the intern-il survey at this stage, it is not necessary to decide whetha: work on 28 or 50 blocks was carried out, although from the evidence it would seem work on only 28 blocks was done. We think that the Judge was right in holding that the fee for the external survey was Shs. 775,000/— . The appellant

was entitled to payment of this sum. The Judge also ordered the appellant to repay the respondent a sum of shs. 1 ,700^000 which he found was overpaid, as well as shs, 499,000 being penalty for delay in carrying out the contract work. Mr. Kumwembe for the appellant rightly attacked this part of the judgment. The respondent was not allowed to proceed with his counterclaim, which included these two items, and in the circumstances, it is difficult to understand how the judge could order the appellant to pay these two sums to the respondent. This order, together with the order to the appellant to pay 1.5 million shillings to procure the right of occupancy, is clearly untenable. All the judge could do would b e to declare that the respondent had overpaid the appellant the sum of Shs. 1.7 million. The order, or more correctly, the declaration that the appellant, on completion of the internal survey and on obtaining the right of occupancy would be entitled to the sum of Shs. 3,796,20#, was unnecessary and indeed irrelevant. If and when the appellant completed the work in terms of the contract and the respondent doas not pay, it is up to the appellant to take whatever steps would be necessary, but that is not a matter with which the trial court or this court is concerned. The appellant had sued for a sum of money i.e. Shs, 3 , 367 ,2 00? and the trial judge in effect found that the

appellant was only entitled to Shs. 775,000 and not more. He also found that the respondent had paid an excess of shs. 1.7 million to the appe1 int. The judge should have made an Order g i v i n g judgment only f°r the sum found due, and made a declaration that an overpayment of shs. 1.7 million had been made. - 7 In the result we dismis?- 1 with costs. We also set aside the judgment and dec .• High Court, except its order for costs, and s u b s t i t m r an order allowing the appellant's claim at Shs. 775 We also declare that the respondent had overpaid tl jnt a sum of shs. 1.7 million. The respondent is at lib apply for the refund of the money, if any, it had depositee ur t. DATED at DAR ES SALAAM thi 3th day of June, 1985. ,A. MUST.

JUSTICE OF PPEAL R» H. KIS a NGA

JUSTICE OF APPEAL a . m. A. omar

JUSTICE OF APPEAL I certify that this is a tt>ue c o p y of the original. (B.-PV MOSHI) SENIOR DEPUTY REGISTRAR.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

No structured authorities are available for this judgment.

Refer to the full judgment and official source for citations that have not yet been extracted.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.