gbl associates ltd vs tanzania portland cement co 1995 tzca 53 8 june 1995

gbl associates ltd vs tanzania portland cement co 1995 tzca 53 8 june 1995

The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable without obtaining the Right of Occupancy, which was the appellant's responsibility. The respondent had overpaid the appellant by Shs. 1.7 million, but no enforceable order for repayment could be...

Source-derived case information.

Citation
gbl associates ltd vs tanzania portland cement co 1995 tzca 53 8 june 1995
Parties
Appellant: G.B.L. & Associates Ltd.; Respondent: Tanzania Portland Cement Co.
Court
TZCA
Jurisdiction
Tanzania
Judgment Date
8 June 1995
Procedural Posture
Civil Appeal / Appeal From High Court Judgment
Outcome
Appeal dismissed with costs; High Court judgment set aside except for costs; substituted order for payment of Shs. 775,000 to appellant; declaration of overpayment by respondent.
Legal Topics
Professional Services Agreement, Quantum Meruit, Overpayment, Right of Occupancy, Penalty for Delay
Source Language
en
Contract Law Civil Procedure Professional Services Agreement Quantum Meruit Overpayment Right of Occupancy Penalty for Delay

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

G.B.L. & Associates Ltd.

Appellant

Tanzania Portland Cement Co.

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Judgment

  1. 1 Whether the appellant was entitled to payment for internal and external survey work under the contract
  2. 2 Whether the appellant was responsible for procuring the Right of Occupancy
  3. 3 Whether the respondent overpaid the appellant and was entitled to a refund

Ratio Decidendi

The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable without obtaining the Right of Occupancy, which was the appellant's responsibility. The respondent had overpaid the appellant by Shs. 1.7 million, but no enforceable order for repayment could be made due to the struck-out counterclaim. Orders for penalties and further payments were set aside as untenable.

Court Disposition

Appeal dismissed with costs; High Court judgment set aside except for costs; substituted order for payment of Shs. 775,000 to appellant; declaration of overpayment by respondent.

Orders

  • Appellant's claim allowed at Shs. 775,000
  • Declaration that respondent overpaid appellant by Shs. 1.7 million