NA TZCA Dar es Salaam 2
The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable until a Right of Occupancy was obtained. The respondent's counterclaim for overpayment and penalties, having been struck out, could not be granted. The trial judge erred in ordering repayment and...
Source-derived case information.
- Citation
- NA TZCA Dar es Salaam 2
- Parties
- Appellant: G.B.L. & Associates Ltd.; Respondent: Tanzania Portland Cement Co.
- Court
- TZCA
- Jurisdiction
- Tanzania
- Judgment Date
- 1 January 1982
- Procedural Posture
- Civil Appeal / Judgment on Appeal
- Outcome
- appeal dismissed with costs
- Legal Topics
- Consultancy Agreements, Payment of Professional Fees, Right of Occupancy, Quantum Meruit, Counterclaim Procedure
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
G.B.L. & Associates Ltd.
Appellant
Tanzania Portland Cement Co.
Respondent
Procedural Posture
Civil Appeal / Judgment on Appeal
Legal Issues
- 1 Whether the appellant was entitled to payment for internal and external survey work under the contract
- 2 Whether the appellant was responsible for procuring the Right of Occupancy
- 3 Whether the respondent was entitled to recover alleged overpayments and penalties after its counterclaim was struck out
Ratio Decidendi
The appellant was only entitled to payment for the external survey (Shs. 775,000) as the internal survey was not payable until a Right of Occupancy was obtained. The respondent's counterclaim for overpayment and penalties, having been struck out, could not be granted. The trial judge erred in ordering repayment and penalties to the respondent. The proper order was judgment for the appellant for Shs. 775,000 and a declaration of overpayment by the respondent of Shs. 1.7 million.
Court Disposition
appeal dismissed with costs
Orders
- Set aside the High Court judgment except for the order allowing the counterclaim to be struck out.
- Declare that the respondent overpaid the appellant by Shs. 1.7 million.
Full Case Text
Judgment text and source record
1 paragraphs
., ,- IN THE COURT OF APPEFAL OF TANZANIA I. AT DAR ES SALAAM CORAM: MUSTAFA, ·JoA._ i KISANGA, J.Ao AND OMAR,. J.Ao CIVIL APPEAL NO. 24 OF 1984 BETWEEN I GoB.L. & ASSOCIATES LTDo • .. • APPELLANT AND TANZANIA PORTLAND CEMENT COo • 0 • • RESPONDENT ' (ApJ?~eaI---"i~om the Judgment of the High Court ·. _.-c{f Tanzania at Dar~ Salaam) Mr. Justice ___..,--- A~ Bahati) dated 25th day of Apr.il, 1984 in Civil Case No. 9 of 1982 JUDGMENT OF THE COURT • MUSTAFA, J oA.--: d ·--- C • • - • ~ • - • • • - •• ' The appellant is a company of consulting ei,gineers and aitchitectural consultants and had entered into a written ag.reement dated 1201201980 with the respondent, a company dealing with cement manufacture. The appellant was according to clause.......~---------~ -.. _ of the agreement to ltsurvey the Wazo Hill area to produce plans, drawings etca which will enable to obtain lease (Right Of Occupancy) of detailed and designed drawings for proposed future roads, drainages, car parks etc. (hereinafter called t~e works) all in accordance with the employe~'s requirements". Clause 13 reads: ~ "All general condi•tions of this agteement shall be interpreted with the ACE regulations, together with the agreed correspondences between the parties t hereto shall form part of.Agreement". t The appellant as plaintiff sued the respondent in the High Court for unpaid feec amounting to Shso 3,567,200 later corrected to Shso 3,367,200 for work carried out for the respondent in, accordance with the agreement. • o • o ft o • • / ~"'• • 2 L The appellant alleged tha·c it was entitled to payme~t in respect of fees and disbursements in the total sum of Shs. 5,842,200 and that ·1t·had received payment from the respondent a sum of Shs.·2,~7~,ooo, leaving the balance of Shs: 3,567~200 (corrected to 3,367,200/=) claimed. The appellant all~ged that it had . completed· all the work it had undertaken to do in terms Of the written agreement. In its defence the respondent denied that the appellant had completed its work. It contended that only the main boundary survey, ioeo the external survey was completed by the appellantQ The respondent further alleged that "the purpose of the survey was to enable the defendant to procure a Right of Occupancy and not the registration of the surveyo No right Qf occupancy has been procr.1red yet". The r;esP,;o_ndent alleged thi'lt it had paid the appellant a. sum of Shso 3,410;351/70, and had in fact overpaid the appellant by Shs. ·2, 103, 351/70. The· respondent counterclaimed against the appellant for·two items, the alleged overpayment of Sh·s~ 2,103, 351/70 and a penalty or liquidated damages assessed ·at ·shso 500/= per day in terms of clause 6 of the agreement for the delay by the appellant in completing its work. According to,__clause 3 of the agreement the work was to commence on 1201201980 1 and to be completed on 12o2~81c The appellant succeeded in the High Court, on a preliminary objection, to have the counterclaim of the respondent struck out as being not maintainable. The order dismissing the counterclaim by the respondent was dated 10v8o82o There were a number of issues in dispute between the parties at the trialo Eventually the trial Judge found as follows: The Judge held That tr:e survey was of tw".) categories, an externa] survey and an internal survey., The appellant he.· completed the external iueo the boundary survey which was required for the issuance of an offer of a Right of Occupancy by the Ministry of Lands. •000000•/30 / 3 (2) The internal survey, consisting inter alia of detailed and designed drawings of future drainage, car parks, roads etc .. was incomplete, as roads and drainages were still to be done. (3) That the survey was for the purpose of obtaining a Right of Occupancy of the area by the respondent, and that it was the responsibility of the appellant to procure it. (4) That internal survey was not to be carried out until an offer of a Right of Occupancy has been obtained and that the appellant knew or should have known this .. (5) That if the Right of Occupancy was not obtained or not obtainable no payment for the internal survey carried out by the appell&nt was payable. (6) That the fee for the external survey was Shs. 775,000, and this sum was payable by the respondent. (7) That, as regards the chargP.s for the internal survey, the appellant had claimed an P.xcess of Shsa 572,000, being charges for 52 blocks for which no survey had been carried out. (8) That the appellant was liable to pay a sum of Shs. 499,000 to the respondent as penalty for delay in completing the work. Further penalty at shs.500/- per day was to continue from date of judgment iee• .25.,4.84 until the work was completed or the contract rescinded. (9) That the appellant, on completion of the internal survey and on obtaining the Right of Occupancy, was entitled to his claim of Shs. 3,367,200. (10) That the respondent had paid the appellant, in respect of the work in terms of the contract, a total of \ Sh's. 2,475,000 for both the external and internal survey. The appellant was only entitled, as at the date of the filing of the suit, to Shs. 775,000/- in respect of the external survey, and that the respondent had overpaid the appellant the sum of Shs. 1,700,000, which the appellant has to refund. (11) That a fee of Shsft 1,soo,000 is due and payable for obtaining a Right of Occupancy, which fee the appellant should pay from the excess payment it had received from the respondentc (12) That the appellant has to poy the respondent the sum of Shso 499,000 being penalty for delay and Shs 572,000/- 0 for overcharging for 52 blocks. •oooooa/4. (13) Should the Right of Occupancy be procured and the internal survey completed in respect of roads and drainages, the appellant would be entitled to be paid the net sum of Shso 3,796,200. (14) Should the appellant fail to complete the internal survey and to obtain the Right of Occupancy the respondent would be entitled to rescind the contract and the appellant liable to pay the respondent the sum of Shs. 2,771,000. The Judge granb;d the costs of the suit to the resi,ondent. from that judgment the appellant has appealed to this court:. We will have to examine the written agreement of 12012.1980• ,. In terms of Clause 2, already quoted, the survey and the produc:tion: of tpe plans, drawings etco were to "enable to obtain lease (Right of Ocqupancy)• ~f the area. It was unclear who was responsible to procure the Right of Occupancyo However the respondent alleged that the appellant was responsible, and a letter written by the appellant to the respondent dated 21.12 o1981 stated inter alia "The issue of Right'of Occupancy is our job a_nd we shall. finalise it without problems 0. This was after the respondent had written to the appellant on several occasions enquiring about the Right of Occupancy, on 2005.1981, 9o6._1981, and 18.12e1981 .. We are satisfied that the Judge was right in holding that the survey was for the procurement of a right of occupancy over the Wazo Hill area and that the appellant was responsible for obtaining it. There was evidence that a sum of Shso 1,500,000 would be requ.ired for the issue of the Right of Occupancy, and we think that the Judge was right, on the evidence adduced, to conclude that the respondent was not informed nor asked by the appellant to produce that sumo Despite the assurance given by the appellant in its letter of 21012081, the appellant had not even obtained an offer of a right of occupancy, let alone a right of occupancyo Both Counsel agree that the work consisted of an internal and an external surveyo Two witnesses PaW.1 and DoWo2 testified that the offer of a right of occupancy was obtainable when an external survey was done, and an external survey was done in !:>is case. •ooooo•o/5. i 5 There was evidence, by P.Wc1 and DaW.2, both qua:lified surveyors, and accepted by the Judge, that an internal survey is carried out only after a right of occupancy has been obtained (per·P.Wo1) or after a right of occupancy has been offered (per DoW.2), o.w.2 also stated that professional surveyors, and the appellant was engaged as su~ji, were supposed to know this. The trial Judge ,.:,... had erred when he stated that "The regulation prohibiting internal survey until there is a right of occupancy ObtaJned is a sound regulation", as there was no "regulation" as su4h. But in effeet he came to the right conclusion;- as, al though it was not a regulation, it was a matter of common practice that no internal survey is carried out until a right of occupancy has been granted or at least offered.. The reason is clear. If no right of oecupancy is obtainedi all the eypenses incurred in an internal survey would be wasted and the survey would be of no value at all. In any event, the demand for payment for the internal survay was premature in the circumstances. The Judge held that if no right of occupancy is.obtained, the appellant would not be entitled -.o any payment for the work done on the internal survey, on a quantum meruit or any basis. We think thiw was going too faro It is true that as professional surveyors the appellant ought not to have commenced the internal surv~y until it had ensured that at least an offer of a right of occupancy was obtained. However if the right of occupancy is unobtainable due to any act of commission or om.ission on tne part of the respondent, then the appellant would probably be entitled to payment for wor]c done on the internal survey even if no right of occupancy is obtained. Apart from this qualification we agree with the trial Judge that the appellant was responsible for obtaining the right of occupancy, that no.internal survey ought to have been done without obtaining at least an offer of a right qf occupancy and in the circumstances, no money for any internal s\Jrvey was payable to the appellant by the respondent at the time the suit was filed. .I 'j 6 Since the respondent was not liable to pay for the internal survey at this stage, it is not necessary to decide whethr work on 28 or 50 blocks was carried out, although from the evidence it would seem work on only 28 blocks was done. We think that the Judge was right in holding that the fee for the external survey was Shs. 775,000/-. The appellant was entitled to payment of this sum. The Judge also ordered the appellant to repay the respondent a sum of shso 1,700,000 which he found was overpaid, as well as shso 499,000 being penalty for delay in carrying out the contract work. Mro Kumwembe for the appellant rightly attacked this part of the judgmento The respondent was not allowed to proceed with his counterclaim, which included these two items, and in the circumstances, it is difficult to understand how the judge could order the appellant to pay these two sums to the respondent. This order, together with the Order to the appellant to pay 1.5 million shillings to procure the right of occupancy, is clearly untenable. All the judge could do would be to declare that the respondent had overpaid the appellant· the sum of Shs. lo? million. The order, or more correctly, the declaration that the appellant, vn completion uf the internal survey and on obtaining the right of o~cupancy would be entitled to the sum of Shs. 3,796,201, was unnecessary and indeed irrelevanto If and when the appellant _,..--· completed the work in terms of the contract and the respondent does not pay, it is up to the appellant to take whatever steps would be necessary, but that is not a matter with which the trJal court or this court is concerned. The appellant had sued for a sum of money i.eo Shss3,367,200, and the trial judge in effect found that the appellant was only entitled to Shso 775,000 and not moreo He also found that the respondent had paid an excess of shso lo7 million to the appe 1 ~nt. The judge should have made an order giving judgment only for the sum found due, and made a declaration that an overpayment of shso lo7 million had been made. e•oeooooo/7. c:-··· ~ _ : ; . : ; ~ .1 I In the result we dismi~ --'r u.:r with costs. 1 We also set aside the judgment and deG 1 I High Court, except its I can order allowing the We also declare that ant a sum of shs. 1.7 million. I for the refund of the -' I of June, 1985. JUSTICE OF .i?PEAL . Ro H. KISANGA ,..,. I ; I JUSTICE OF APPEAL -.J ' A .. Mo Ao OMAR. JUSTICE OF APPEAL ~ ,....., ·. ""' ♦ '•·', .. ' ' "i ...... I certify that this A:§a..:.f~e 'c"opy of the original • .· / • .. I -~i?;~'.:: ....:· .-.,. :.w ·\ / . ~ .- - ! \ ( i:l;~p·;""M6SHI) SENIOR DEPUTY REGI.S'TRAR. ~ f l l ) --~ -.. --.