neco data ltd vs t revenue authority 3 others 2006 tzhccomd 61 28 august 2006
The applicant demonstrated a prima facie case and risk of irreparable injury if denied access to the project, which could not be compensated by damages. The balance of convenience favored granting the injunction to prevent greater hardship to the applicant.
- Citation
- neco data ltd vs t revenue authority 3 others 2006 tzhccomd 61 28 august 2006
- Parties
- Plaintiff/respondent: NECO DATA LIMITED; 1st Defendant/respondent: TANZANIA REVENUE AUTHORITY; 2nd Defendant/applicant: NICO (ZAMBIA) LTD; 3rd Defendant/respondent: ALFRED ADAM LYIMO; 4th Defendant/respondent: NECO ZAMBIA LTD
- Court
- TZHCCOMD
- Jurisdiction
- Tanzania
- Judgment Date
- 28 August 2006
- Procedural Posture
- Commercial Case / Ruling on Application for Interim Injunction
- Outcome
- Application granted
- Legal Topics
- Interim Injunctions, Joint Venture Disputes, Contractual Obligations, Access to Project Sites
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
NECO DATA LIMITED
Plaintiff/respondent
TANZANIA REVENUE AUTHORITY
1st Defendant/respondent
NICO (ZAMBIA) LTD
2nd Defendant/applicant
ALFRED ADAM LYIMO
3rd Defendant/respondent
NECO ZAMBIA LTD
4th Defendant/respondent
Procedural Posture
Commercial Case / Ruling on Application for Interim Injunction
Legal Issues
- 1 Whether the applicant is entitled to an interim injunction restraining the plaintiff/respondent from denying access to project premises and interfering with contract execution
Ratio Decidendi
The applicant demonstrated a prima facie case and risk of irreparable injury if denied access to the project, which could not be compensated by damages. The balance of convenience favored granting the injunction to prevent greater hardship to the applicant.
Court Disposition
Application granted
Orders
- Interim injunction granted restraining the plaintiff/respondent and its agents from denying entrance, blocking, prohibiting, restraining, threatening, harassing, evicting or interfering with the applicant and its agents from accessing premises, machinery, technology or documents related to the project until final...
- Each party to bear its own costs of the application.
Full Case Text
Judgment text and source record