james abiud nyakisagane vs tanzania electrick supply company tanesco 2022 tzhclandd 120 28 february 2022

james abiud nyakisagane vs tanzania electrick supply company tanesco 2022 tzhclandd 120 28 february 2022

The plaintiff, having consented to the compensation assessment and payment, is estopped from claiming additional compensation for land or the hut. Claims for higher land value, loss of income, and general damages were unproven. However, the plaintiff is entitled to interest for delayed payment as compensation was...

Source-derived case information.

Citation
james abiud nyakisagane vs tanzania electrick supply company tanesco 2022 tzhclandd 120 28 february 2022
Parties
Plaintiff: James Abiud Nyakisagane; Defendant: Tanzania Electrical Supply Company (TANESCO)
Court
TANZLII
Jurisdiction
Tanzania
Judgment Date
28 February 2022
Procedural Posture
Land Case / Judgment
Outcome
Partly allowed
Legal Topics
Compulsory Acquisition, Compensation for Land, Interest for Delayed Payment, General Damages, Loss of Income
Source Language
en
Land Law Compensation Law Compulsory Acquisition Compensation for Land Interest for Delayed Payment General Damages Loss of Income

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 16 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

James Abiud Nyakisagane

Plaintiff

Tanzania Electrical Supply Company (TANESCO)

Defendant

Procedural Posture

Land Case / Judgment

  1. 1 Whether the plaintiff is entitled to extra compensation for land acquired by TANESCO
  2. 2 Whether the plaintiff is entitled to compensation for a two-roomed hut
  3. 3 Whether the plaintiff is entitled to loss of income

Ratio Decidendi

The plaintiff, having consented to the compensation assessment and payment, is estopped from claiming additional compensation for land or the hut. Claims for higher land value, loss of income, and general damages were unproven. However, the plaintiff is entitled to interest for delayed payment as compensation was paid two months after the statutory six-month period.

Court Disposition

Partly allowed

Orders

  • Plaintiff awarded TZS 9,450,320 as interest for delayed payment
  • All other claims dismissed